PREPARING ROW
|
AC
|
8.890
|
$50,000.000
|
$9,000.000
|
$3,000.000
|
|
|
REMOVING CONC (RETAINING WALLS)
|
SY
|
679.000
|
$45.000
|
$8.000
|
$30.000
|
|
|
REMOVING STAB BASE & ASPH PAV (0-6")
|
SY
|
8,085.000
|
$1.500
|
$1.500
|
$3.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,156.000
|
$15.000
|
$15.500
|
$15.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY A)
|
CY
|
15,344.000
|
$5.500
|
$28.000
|
$15.000
|
|
|
PROOF ROLLING
|
HR
|
66.000
|
$70.000
|
$70.000
|
$50.000
|
|
|
FL BS (RDWY DEL) (TY A GR 1-2)
|
TON
|
1,931.000
|
$55.000
|
$85.000
|
$60.000
|
|
|
CEMENT
|
TON
|
31.000
|
$310.000
|
$510.000
|
$400.000
|
|
|
CEMENT TREAT (SUBGRADE)(6")
|
SY
|
6,480.000
|
$5.000
|
$2.300
|
$5.000
|
|
|
PRIME COAT (MULTI OPTION)
|
GAL
|
1,272.000
|
$10.000
|
$8.000
|
$8.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
1,048.000
|
$4.000
|
$6.000
|
$5.000
|
|
|
CEM STABIL BKFL
|
CY
|
217.000
|
$200.000
|
$400.000
|
$350.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
200.000
|
$400.000
|
$300.000
|
$350.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
550.000
|
$575.000
|
$500.000
|
$550.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
81.500
|
$2,000.000
|
$1,500.000
|
$2,000.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
91.600
|
$3,000.000
|
$1,850.000
|
$2,500.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
12.900
|
$5,000.000
|
$3,750.000
|
$5,000.000
|
|
|
CL C CONC (WEBWALL)
|
CY
|
21.600
|
$3,000.000
|
$1,500.000
|
$4,000.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
17,000.000
|
$40.000
|
$37.000
|
$40.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
90.000
|
$2,500.000
|
$1,100.000
|
$1,500.000
|
|
|
RETAINING WALL (TEMP WALL)
|
SF
|
6,107.000
|
$35.000
|
$37.000
|
$45.000
|
|
|
PRESTR CONC GIRDER (TX46)
|
LF
|
1,989.180
|
$325.000
|
$300.000
|
$270.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
1,625.000
|
$175.000
|
$150.000
|
$250.000
|
|
|
RIPRAP (MOW STRIP)(5 IN)
|
CY
|
77.000
|
$750.000
|
$700.000
|
$650.000
|
|
|
RAIL (TY SSTR) (W/DRAIN SLOT) (HPC)
|
LF
|
1,100.000
|
$150.000
|
$95.000
|
$140.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
|
LF
|
136.000
|
$300.000
|
$160.000
|
$250.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$550,577.000
|
$380,000.000
|
$550,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
10.000
|
$25,000.000
|
$10,000.000
|
$25,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
20.000
|
$115.000
|
$115.000
|
$50.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
20.000
|
$35.000
|
$39.000
|
$50.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
110.000
|
$42.500
|
$51.000
|
$55.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
110.000
|
$14.000
|
$19.000
|
$25.000
|
|
|
BLADING WORK (EROSION & SEDMT CONT)
|
HR
|
80.000
|
$145.000
|
$148.000
|
$80.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
7,144.000
|
$3.750
|
$4.000
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
7,144.000
|
$1.050
|
$1.100
|
$2.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
6,181.000
|
$95.000
|
$75.000
|
$50.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
8.000
|
$3,500.000
|
$4,000.000
|
$15,000.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
1,980.000
|
$95.000
|
$100.000
|
$80.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
80.000
|
$95.000
|
$100.000
|
$95.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
1,980.000
|
$15.000
|
$15.000
|
$15.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
80.000
|
$15.000
|
$15.000
|
$15.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
4,676.000
|
$1.250
|
$1.500
|
$2.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
825.000
|
$32.500
|
$32.000
|
$35.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,800.000
|
$3,200.000
|
$2,700.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$4,000.000
|
$3,500.000
|
$3,500.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
5.000
|
$1,200.000
|
$1,750.000
|
$1,700.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
6.000
|
$1.250
|
$150.000
|
$500.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
11.000
|
$55.000
|
$60.000
|
$30.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
23.000
|
$60.000
|
$65.000
|
$40.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
96.000
|
$8.750
|
$6.850
|
$8.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
8,310.000
|
$2.200
|
$2.650
|
$6.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
3,840.000
|
$2.200
|
$2.650
|
$6.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
100.000
|
$2.100
|
$2.250
|
$4.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
100.000
|
$2.000
|
$2.250
|
$4.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
100.000
|
$2.000
|
$2.250
|
$4.000
|
|
REFL PAV MRK TY II (W) 6" (SLD)
|
LF
|
5,248.000
|
$1.500
|
$0.400
|
$4.000
|
|
REFL PAV MRK TY II (Y) 6" (BRK)
|
LF
|
2,428.000
|
$1.500
|
$0.400
|
$4.000
|
|
REFL PAV MRK TY II (Y) 6" (SLD)
|
LF
|
1,562.000
|
$1.500
|
$0.600
|
$4.000
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
5,248.000
|
$1.400
|
$1.600
|
$2.000
|
|
|
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
|
LF
|
2,428.000
|
$2.050
|
$1.900
|
$2.000
|
|
|
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
|
LF
|
1,562.000
|
$1.400
|
$1.800
|
$2.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
66.000
|
$9.500
|
$6.850
|
$20.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
4,934.000
|
$0.650
|
$1.450
|
$2.000
|
|
|
D-GR HMA TY-C SAC-A PG70-22 (EXEMPT)
|
TON
|
1,088.000
|
$245.000
|
$280.000
|
$210.000
|
|
|
INSTALL BRIDGE IDENTIFICATION NUMBERS
|
EA
|
2.000
|
$500.000
|
$175.000
|
$1,000.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
3.000
|
$15,000.000
|
$10,000.000
|
$18,000.000
|
|
|
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
|
LF
|
120.000
|
$40.000
|
$24.250
|
$30.000
|
|
|
TMA (STATIONARY)
|
DAY
|
600.000
|
$70.000
|
$75.000
|
$100.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
20.000
|
$375.000
|
$400.000
|
$200.000
|
|
Totals: |
$6,286,135.700
|
$5,340,874.600
|
$5,838,213.600
|