PREPARING ROW
|
AC
|
48.000
|
$5,000.000
|
$10,000.000
|
$14,500.000
|
$5,000.000
|
$11,643.360
|
$1,991.910
|
|
|
REMOVING STAB BASE & ASPH PAV (8"-10")
|
SY
|
26,900.000
|
$4.500
|
$1.250
|
$2.100
|
$4.500
|
$1.960
|
$10.110
|
|
|
OBLITERATING ABANDONED ROAD
|
STA
|
55.000
|
$1,575.000
|
$1,000.000
|
$2,500.000
|
$1,000.000
|
$579.360
|
$722.950
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
17,626.000
|
$7.500
|
$4.000
|
$20.000
|
$9.000
|
$8.960
|
$11.120
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
1,088.000
|
$9.350
|
$8.900
|
$10.000
|
$17.000
|
$6.160
|
$20.220
|
|
|
EXCAVATION (SPECIAL)
|
CY
|
40.000
|
$10.000
|
$75.000
|
$30.000
|
$50.000
|
$33.600
|
$217.390
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY A)
|
CY
|
107,263.000
|
$8.000
|
$12.000
|
$23.000
|
$22.000
|
$12.100
|
$25.580
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
AC
|
48.000
|
$1,000.000
|
$450.000
|
$1,060.560
|
$465.000
|
$609.000
|
$436.800
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
AC
|
48.000
|
$350.000
|
$450.000
|
$323.090
|
$465.000
|
$609.000
|
$439.840
|
|
|
STRAW/HAY MLCH SEED(PERM)(URBAN)(SANDY)
|
AC
|
48.000
|
$1,350.000
|
$1,400.000
|
$1,627.500
|
$1,400.000
|
$1,890.560
|
$1,365.010
|
|
|
VEGETATIVE WATERING
|
MG
|
2,510.000
|
$15.000
|
$18.000
|
$22.000
|
$20.000
|
$86.160
|
$50.560
|
|
|
IRRIGATION SYSTEM LOCATION A
|
LS
|
1.000
|
$50,000.000
|
$130,000.000
|
$307,017.540
|
$120,000.000
|
$112,000.000
|
$118,700.430
|
|
|
IRRIGATION SYSTEM LOCATION B
|
LS
|
1.000
|
$60,000.000
|
$125,000.000
|
$185,279.280
|
$117,000.000
|
$112,000.000
|
$116,464.850
|
|
|
PLANT MATERIAL (1-GAL)
|
EA
|
970.000
|
$15.000
|
$12.000
|
$13.000
|
$12.000
|
$15.240
|
$10.970
|
|
|
PLANT MATERIAL (3-GAL)
|
EA
|
657.000
|
$25.000
|
$48.000
|
$12.540
|
$47.000
|
$63.020
|
$45.500
|
|
|
PLANT MATERIAL (5-GAL)
|
EA
|
798.000
|
$35.000
|
$48.000
|
$29.650
|
$50.000
|
$63.020
|
$45.500
|
|
|
PLANT MATERIAL (15-GAL)
|
EA
|
61.000
|
$200.000
|
$210.000
|
$122.600
|
$210.000
|
$277.200
|
$200.200
|
|
|
PLANT MATERIAL (30 GAL) (TREE)
|
EA
|
69.000
|
$350.000
|
$520.000
|
$322.240
|
$500.000
|
$683.200
|
$493.430
|
|
|
PLANT MATERIAL (45 GAL) (TREE)
|
EA
|
43.000
|
$500.000
|
$660.000
|
$321.470
|
$700.000
|
$865.760
|
$624.870
|
|
|
LANDSCAPE EDGE (TYPE I)
|
LF
|
1,583.000
|
$20.000
|
$2.100
|
$20.460
|
$4.000
|
$11.200
|
$15.170
|
|
|
LANDSCAPE EDGE (TYPE II)
|
LF
|
476.000
|
$25.000
|
$4.250
|
$27.520
|
$9.000
|
$11.200
|
$25.280
|
|
|
LANDSCAPE EDGE (TYPE III)
|
LF
|
1,052.000
|
$10.000
|
$10.000
|
$28.000
|
$10.000
|
$11.200
|
$9.470
|
|
|
FL BS (RDWY DEL) (TY A GR 1-2)
|
TON
|
13,353.000
|
$30.000
|
$29.000
|
$35.000
|
$39.000
|
$29.120
|
$34.380
|
|
|
CEMENT
|
TON
|
1,027.000
|
$120.000
|
$191.000
|
$200.000
|
$280.000
|
$196.000
|
$288.170
|
|
|
CEMENT TREAT (NEW BASE) (8")
|
SY
|
31,654.000
|
$2.750
|
$3.450
|
$2.750
|
$3.100
|
$2.240
|
$6.070
|
|
|
CEMENT TREAT (SUBGRADE)(6")
|
SY
|
103,111.000
|
$2.500
|
$2.700
|
$3.000
|
$2.900
|
$1.980
|
$6.070
|
|
|
PRIME COAT (MULTI OPTION)
|
GAL
|
19,613.000
|
$3.500
|
$6.000
|
$3.220
|
$6.500
|
$5.060
|
$10.110
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
36,412.000
|
$3.000
|
$6.300
|
$2.990
|
$6.500
|
$5.040
|
$10.110
|
|
|
AGGR(TY-PB GR-4 SAC-A)
|
CY
|
291.000
|
$72.000
|
$137.000
|
$130.000
|
$100.000
|
$145.600
|
$232.560
|
|
|
AGGR (TY-B GR-3)
|
CY
|
355.000
|
$225.000
|
$158.000
|
$107.500
|
$90.000
|
$112.000
|
$176.950
|
|
|
D-GR HMA TY-D PG64-22
|
TON
|
12,026.000
|
$60.000
|
$108.000
|
$68.440
|
$110.000
|
$112.000
|
$106.570
|
|
|
SUPERPAVE MIXTURES SP-B PG64-22
|
TON
|
7,658.000
|
$75.000
|
$101.000
|
$73.060
|
$112.000
|
$112.000
|
$110.210
|
|
|
SUPERPAVE MIXTURES SP-C SAC-A PG64-22
|
TON
|
1,280.000
|
$80.000
|
$117.000
|
$75.410
|
$115.000
|
$112.000
|
$112.230
|
|
|
PLANE ASPH CONC PAV (1/2" TO 2")
|
SY
|
8,340.000
|
$5.000
|
$1.500
|
$3.000
|
$2.500
|
$1.680
|
$6.070
|
|
|
CONC PVMT (CONT REINF - CRCP) (10")
|
SY
|
56,401.000
|
$75.000
|
$70.000
|
$90.000
|
$97.500
|
$100.800
|
$77.350
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
3,264.000
|
$5.000
|
$5.000
|
$2.500
|
$4.000
|
$1.350
|
$10.110
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
66.000
|
$230.000
|
$470.000
|
$447.000
|
$500.000
|
$339.410
|
$451.970
|
|
|
RETAINING WALL (SPECIAL)
|
SF
|
5,484.000
|
$45.000
|
$39.000
|
$95.000
|
$70.000
|
$72.800
|
$30.330
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
47.000
|
$650.000
|
$480.000
|
$484.050
|
$600.000
|
$531.920
|
$742.160
|
|
|
RIPRAP (CONC)(6 IN)
|
CY
|
15.000
|
$450.000
|
$505.000
|
$738.690
|
$700.000
|
$651.840
|
$742.160
|
|
|
RIPRAP (CONC)(CL B)
|
CY
|
40.000
|
$275.000
|
$200.000
|
$980.000
|
$500.000
|
$593.600
|
$742.160
|
|
|
RAIL (TY T552)
|
LF
|
340.000
|
$75.000
|
$124.000
|
$85.000
|
$115.000
|
$91.280
|
$50.560
|
|
|
CONC BOX CULV (6 FT X 3 FT)
|
LF
|
276.000
|
$300.000
|
$690.000
|
$600.000
|
$380.000
|
$395.360
|
$767.440
|
|
|
CONC BOX CULV (7 FT X 3 FT)
|
LF
|
316.000
|
$375.000
|
$760.000
|
$700.000
|
$550.000
|
$460.770
|
$966.630
|
|
|
CONC BOX CULV (8 FT X 4 FT)
|
LF
|
357.000
|
$380.000
|
$980.000
|
$800.000
|
$650.000
|
$549.030
|
$1,043.480
|
|
|
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
|
LF
|
184.000
|
$480.000
|
$925.000
|
$1,000.000
|
$750.000
|
$462.620
|
$1,108.190
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
112.000
|
$200.000
|
$370.000
|
$400.000
|
$300.000
|
$224.000
|
$299.290
|
|
|
HEADWALL (CH - FW - 0) (DIA= 48 IN)
|
EA
|
2.000
|
$8,000.000
|
$12,500.000
|
$15,583.320
|
$7,500.000
|
$10,080.000
|
$33,704.680
|
|
|
WINGWALL (FW - 0) (HW=5 FT)
|
EA
|
2.000
|
$8,500.000
|
$10,500.000
|
$27,333.780
|
$5,200.000
|
$11,200.000
|
$10,785.620
|
|
|
WINGWALL (FW - S) (HW=4 FT)
|
EA
|
4.000
|
$15,000.000
|
$8,900.000
|
$25,780.520
|
$5,700.000
|
$21,000.000
|
$8,628.900
|
|
|
WINGWALL (FW - S) (HW=5 FT)
|
EA
|
2.000
|
$6,050.000
|
$13,500.000
|
$12,935.290
|
$6,500.000
|
$15,680.000
|
$10,785.620
|
|
|
WINGWALL (FW - S) (HW=7 FT)
|
EA
|
2.000
|
$10,000.000
|
$9,000.000
|
$25,000.000
|
$8,500.000
|
$26,320.000
|
$15,100.070
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$2,360,956.340
|
$2,450,000.000
|
$3,288,577.730
|
$1,500,000.000
|
$2,336,432.000
|
$3,819,708.020
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
22.000
|
$6,500.000
|
$7,900.000
|
$5,000.000
|
$12,000.000
|
$10,181.820
|
$5,472.690
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
950.000
|
$45.000
|
$29.000
|
$58.000
|
$45.000
|
$55.440
|
$58.640
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
950.000
|
$12.000
|
$7.500
|
$10.550
|
$9.000
|
$2.240
|
$9.050
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
448.000
|
$35.000
|
$36.000
|
$22.110
|
$35.000
|
$48.040
|
$20.220
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
448.000
|
$10.000
|
$8.100
|
$7.370
|
$9.000
|
$1.120
|
$10.110
|
|
|
CONSTRUCTION PERIMETER FENCE
|
LF
|
26,300.000
|
$2.500
|
$5.000
|
$8.000
|
$3.500
|
$4.480
|
$8.090
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
400.000
|
$3.500
|
$7.100
|
$2.710
|
$6.000
|
$6.720
|
$2.730
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
400.000
|
$1.500
|
$1.100
|
$0.710
|
$2.000
|
$0.120
|
$9.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
2,700.000
|
$35.000
|
$10.000
|
$80.000
|
$82.000
|
$89.600
|
$70.780
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
4,620.000
|
$7.000
|
$4.250
|
$6.000
|
$7.000
|
$2.790
|
$5.820
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
2,700.000
|
$7.000
|
$5.500
|
$6.000
|
$10.000
|
$5.600
|
$10.110
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
20,659.000
|
$20.000
|
$15.200
|
$17.110
|
$22.000
|
$23.520
|
$19.210
|
|
|
CONC SIDEWALKS (4")
|
SY
|
1,323.000
|
$45.000
|
$59.000
|
$69.930
|
$40.000
|
$50.400
|
$65.520
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,600.000
|
$20.000
|
$35.000
|
$33.500
|
$28.000
|
$19.590
|
$33.870
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
12.000
|
$1,200.000
|
$1,600.000
|
$1,500.000
|
$1,300.000
|
$1,279.040
|
$1,516.680
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
LF
|
1,600.000
|
$22.000
|
$35.500
|
$33.500
|
$28.000
|
$21.560
|
$33.870
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
12.000
|
$2,600.000
|
$3,700.000
|
$3,500.000
|
$2,900.000
|
$3,088.960
|
$3,538.920
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
2.000
|
$10,000.000
|
$9,500.000
|
$9,700.000
|
$9,500.000
|
$7,840.000
|
$9,807.870
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
3.000
|
$3,000.000
|
$1,300.000
|
$1,850.000
|
$1,300.000
|
$746.680
|
$1,870.570
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$1,500.000
|
$690.000
|
$1,550.000
|
$800.000
|
$1,120.000
|
$1,567.240
|
|
|
WIRE FENCE (TY A)
|
LF
|
8,613.000
|
$10.000
|
$5.800
|
$17.750
|
$12.000
|
$9.910
|
$10.110
|
|
|
IN RD IL (TY SA) 40T-8 (250W EQ) LED
|
EA
|
26.000
|
$3,400.000
|
$7,300.000
|
$6,892.000
|
$7,000.000
|
$4,048.800
|
$6,968.640
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
5,567.000
|
$12.000
|
$20.000
|
$18.650
|
$21.000
|
$10.660
|
$18.860
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
11,274.000
|
$1.750
|
$3.500
|
$3.250
|
$3.500
|
$2.760
|
$3.290
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
29.000
|
$600.000
|
$770.000
|
$733.000
|
$780.000
|
$672.000
|
$741.150
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
11.000
|
$545.000
|
$1,060.000
|
$987.000
|
$1,100.000
|
$672.000
|
$997.980
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
2.000
|
$780.000
|
$1,200.000
|
$1,121.000
|
$1,300.000
|
$672.000
|
$1,133.470
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
|
EA
|
2.000
|
$900.000
|
$1,300.000
|
$1,227.000
|
$1,450.000
|
$672.000
|
$1,240.650
|
|
|
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
|
EA
|
8.000
|
$1,640.000
|
$1,700.000
|
$1,552.000
|
$1,700.000
|
$672.000
|
$1,569.260
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
1.000
|
$350.000
|
$785.000
|
$744.000
|
$800.000
|
$448.000
|
$752.270
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
954.000
|
$0.750
|
$1.600
|
$3.500
|
$3.800
|
$1.120
|
$3.540
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
|
LF
|
43,065.000
|
$0.500
|
$0.800
|
$1.500
|
$1.700
|
$0.550
|
$1.520
|
|
|
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
|
LF
|
1,440.000
|
$0.650
|
$0.800
|
$1.500
|
$1.700
|
$2.270
|
$1.520
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
|
LF
|
13,646.000
|
$0.550
|
$0.800
|
$1.500
|
$1.700
|
$2.220
|
$1.520
|
|
PRE PM TY B(ACC PRK)(BL&WH)(W/BORDR)LG
|
EA
|
4.000
|
$350.000
|
$604.000
|
$375.000
|
$400.000
|
$560.000
|
$379.170
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
309.000
|
$2.600
|
$5.800
|
$4.500
|
$4.750
|
$4.720
|
$4.550
|
|
|
LANDSCAPE AMENITY (TY 1)
|
EA
|
38.000
|
$500.000
|
$350.000
|
$450.440
|
$400.000
|
$459.200
|
$331.650
|
|
|
LANDSCAPE AMENITY (TY 2)
|
EA
|
71.000
|
$250.000
|
$320.000
|
$409.240
|
$300.000
|
$420.000
|
$301.310
|
|
|
LANDSCAPE AMENITY (TY 3)
|
EA
|
197.000
|
$100.000
|
$265.000
|
$340.570
|
$270.000
|
$347.200
|
$250.760
|
|
|
LANDSCAPE AMENITY (TY 4)
|
EA
|
1.000
|
$6,680.000
|
$6.300
|
$111.000
|
$20,000.000
|
$2,240.000
|
$5,055.600
|
|
|
LANDSCAPE AMENITY (TY 5)
|
EA
|
1.000
|
$8,400.000
|
$6.300
|
$4,275.000
|
$20,000.000
|
$2,240.000
|
$25,278.000
|
|
|
LOOSE AGGR FOR GROUNDCOVER (TYPE I)
|
CY
|
262.000
|
$250.000
|
$181.000
|
$233.090
|
$180.000
|
$238.000
|
$92.010
|
|
|
LOOSE AGGR FOR GROUNDCOVER (TYPE II)
|
CY
|
13.000
|
$100.000
|
$285.000
|
$368.040
|
$300.000
|
$375.200
|
$226.490
|
|
|
LOOSE AGGR FOR GROUNDCOVER (TYPE III)
|
CY
|
21.000
|
$280.000
|
$350.000
|
$450.440
|
$340.000
|
$459.200
|
$308.390
|
|
|
WHEEL STOPS
|
EA
|
7.000
|
$175.000
|
$207.000
|
$135.640
|
$120.000
|
$112.000
|
$121.330
|
|
|
SAFETY REST AREA
|
LS
|
1.000
|
$9,469,655.660
|
$13,350,000.000
|
$12,498,191.500
|
$14,990,220.000
|
$15,882,055.840
|
$13,840,444.140
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$20,000.000
|
$8,800.000
|
$8,733.710
|
$12,500.000
|
$16,800.000
|
$20,220.400
|
|
|
TMA (STATIONARY)
|
EA
|
1.000
|
$18,000.000
|
$0.010
|
$5,500.000
|
$28,000.000
|
$56,000.000
|
$50,556.000
|
|
|
NGP MAIN (6" DIA STL)
|
LF
|
3,010.000
|
$150.000
|
$66.000
|
$180.000
|
$108.000
|
$59.540
|
$174.920
|
|
|
GAS ELL (6" DIA STL)
|
EA
|
2.000
|
$700.000
|
$1,100.000
|
$1,000.000
|
$200.000
|
$1,120.000
|
$26,963.540
|
|
|
NGP STOPPLE (6" DIA)
|
EA
|
4.000
|
$35,000.000
|
$13,000.000
|
$1,000.000
|
$1,100.000
|
$4,480.000
|
$60,667.200
|
|
|
REMOVAL
|
LF
|
2,799.000
|
$15.000
|
$3.200
|
$40.000
|
$46.500
|
$11.200
|
$27.300
|
|
|
2-INCH STEEL BYPASS
|
EA
|
2.000
|
$10,000.000
|
$3,200.000
|
$2,260.000
|
$2,600.000
|
$5,600.000
|
$20,222.100
|
|
Totals: |
$23,710,369.500
|
$29,328,228.910
|
$32,885,777.330
|
$33,483,624.450
|
$34,012,394.810
|
$35,357,230.370
|