CORYELL US0084 (6492-20-001)

Items: 25

County: CORYELL
Length: 0.0100 MILES
Highway: US0084
District: WACO
Control Number: 6492-20-001
DBE Goal: 0.0%
Project: RMC - A00218028
Guaranty: $15,000.00
Time: 365 CALENDAR DAYS
Engineer's Estimate: $736,524.75
Date: 01/14/2026 (4 months ago) Changed
Contract Number: 1260906
Type: BASE FAILURE PAVEMENT REPAIR
Project ID: A00218028
Project Description: BASE FAILURE REPAIR OF VARIOUS ROADWAYS ACROSS CORYELL, HAMILTON AND BOSQUE COUNTIES.
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$736,524.75
$555,360.00
Over/Under Est: -24.6% -$181,164.75
Over/Under Est: 11.62% $85,611.75
Amt Left: 48.04% $266,776.50
Over/Under Est: 11.67% $85,974.25
Amt Left: 48.1% $267,139.00
Delta: -0.04% -$362.50

Bid Items & Bid Tabulations

25 Total 0 of 25
CORYELL  |  US0084  |  WACO  |  6492-20-001  |  01/14/2026  |  $736,524.75  |  RMC - A00218028  |  BASE FAILURE PAVMT REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
TEXAS MATERIALS GROUP, INC.
D-GR HMA TY-C PG70-22
TON 1,405.000 $265.000 $127.000 $154.700 $163.000
D-GR HMA TY-D PG70-22
TON 800.000 $138.000 $132.000 $149.500 $165.000
TACK COAT
GAL 500.000 $4.000 $4.000 $8.200 $3.000
SP MIXES SP-C PG70-22
TON 500.000 $142.250 $127.000 $181.750 $217.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 1,550.000 $35.000 $35.000 $68.550 $77.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 900.000 $70.000 $70.000 $126.350 $139.000
PLANE ASPH CONC PAV(2")
SY 7,500.000 $3.250 $3.250 $6.150 $6.600
MOBILIZATION (CALLOUT)
EA 6.000 $1.000 $250.000 $4,150.000 $10.000
MOBILIZATION (EMERGENCY)
EA 3.000 $220.000 $400.000 $2,235.000 $5,360.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $90.000 $105.000 $278.000 $65.700
TMA (STATIONARY)
DAY 60.000 $150.000 $210.000 $660.000 $89.000
TMA (MOBILE OPERATION)
HR 60.000 $75.000 $100.000 $96.000 $30.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 150.000 $1.000 $2.000 $1.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 150.000 $1.000 $2.000 $1.000 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 50.000 $7.500 $15.000 $15.000 $14.000
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 1,000.000 $0.700 $2.500 $2.450 $2.250
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 1,000.000 $0.620 $2.750 $2.700 $2.500
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 1,000.000 $0.680 $2.500 $2.550 $2.350
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 1,000.000 $0.600 $2.750 $2.700 $2.500
PREFAB PM TY C (W)(ARROW)
EA 9.000 $225.000 $325.000 $339.000 $315.000
PREFAB PM TY C (W)(WORD)
EA 9.000 $263.750 $450.000 $458.000 $425.000
REFL PAV MRKR TY I-C
EA 150.000 $5.000 $6.500 $6.450 $6.000
REFL PAV MRKR TY II-A-A
EA 1,200.000 $5.000 $6.500 $6.450 $6.000
UNDERSEAL COURSE
GAL 1,800.000 $3.700 $4.000 $7.200 $4.200
MAINTENANCE SPEED LIMIT SIGNING
DAY 20.000 $100.000 $300.000 $65.000 $1.000
Totals: $736,524.750 $555,360.000 $822,136.500 $822,499.000