Show Job Controls
Bid Cobra

CORYELL FM0107 (6467-39-001)

Items: 22

County: CORYELL
Length: N/A
Highway: FM0107
District: WACO
Control Number: 6467-39-001
DBE Goal: 0.0%
Project: RMC - 646739001
Guaranty: N/A
Time: 83 W
Engineer's Estimate: $3,446,120.07
Date: 06/06/2024 (2 years ago) Changed
Contract Number: N/A
Type: BASE FAILURE PAVEMENT REPAIR
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$3,446,120.07
$2,342,224.75
Over/Under Est: -32.03% -$1,103,895.32
Over/Under Est: -11.74% -$404,644.47
Amt Left: 29.85% $699,250.85
Over/Under Est: -9.39% -$323,506.42
Amt Left: 33.32% $780,388.90
Delta: -2.67% -$81,138.05
$4,301,171.00
Over/Under Est: 24.81% $855,050.93
Amt Left: 83.64% $1,958,946.25
Delta: -37.74% -$1,178,557.35
Subcontractor Percentage Amount
D. I. J. CONSTRUCTION, INC. 2.15% $51,217.08
Total: 2.15% $51,217.08

Bid Items & Bid Tabulations

22 Total 0 of 22
CORYELL  |  FM0107  |  WACO  |  6467-39-001  |  06/06/2024  |  $3,446,120.07  |  RMC - 646739001  |  BASE FAILURE PAVMT REPAIR  |  83 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
TEXAS MATERIALS GROUP, INC.
BIG CREEK CONSTRUCTION, LTD.
FNH CONSTRUCTION, LLC
BACKFILL (TY A OR B)
CY 160.000 $75.000 $250.000 $42.000 $100.000 $450.000
PROOF ROLLING
HR 16.000 $238.460 $100.000 $90.000 $200.000 $150.000
FL BS (RDWY DEL) (TY D GR 5)
TON 2,067.000 $41.510 $78.300 $133.750 $100.000 $60.000
EMULS ASPH (BS OR SUBGR TRT)(CSS-1H)
GAL 24,000.000 $7.250 $3.750 $11.000 $5.000 $5.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 20,000.000 $50.000 $23.900 $28.000 $40.000 $80.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 37,803.000 $45.000 $35.000 $38.000 $40.000 $45.000
MOBILIZATION
LS 1.000 $264,477.040 $73,100.000 $300,000.000 $300,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $8,500.000 $980.000 $19,850.000 $250.000 $15,000.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,440.000 $2.000 $1.000 $1.000 $1.500 $6.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,115.000 $2.000 $1.000 $1.000 $1.500 $6.000
REFL PAV MRK TY I (W)8"(LNDP)(100MIL)
LF 100.000 $2.200 $2.350 $2.000 $2.250 $10.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 160.000 $10.250 $11.800 $10.000 $12.500 $20.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 3,295.000 $1.000 $0.950 $0.800 $0.820 $2.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 13,150.000 $1.000 $1.000 $0.870 $0.890 $2.000
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 7,795.000 $0.900 $1.000 $0.830 $0.850 $2.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 31,150.000 $1.000 $1.000 $0.820 $0.840 $2.000
REFL PAV MRKR TY I-C
EA 335.000 $6.000 $7.000 $6.000 $7.000 $6.000
REFL PAV MRKR TY II-A-A
EA 166.000 $6.000 $9.400 $8.000 $9.000 $6.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 83.000 $150.000 $295.000 $110.000 $125.000 $150.000
TMA (STATIONARY)
DAY 83.000 $255.000 $15.000 $271.000 $350.000 $250.000
TMA (MOBILE OPERATION)
HR 830.000 $85.000 $95.000 $20.000 $62.500 $55.000
MAINTENANCE SPEED LIMIT SIGNING
DAY 83.000 $80.000 $15.000 $395.000 $150.000 $150.000
Totals: $3,446,120.070 $2,342,224.750 $3,041,475.600 $3,122,613.650 $4,301,171.000