CORYELL FM 1783 (1594-02-012)

Items: 60

County: CORYELL
Length: N/A
Highway: FM 1783
District: WACO
Control Number: 1594-02-012
DBE Goal: N/A
Project: BR 2018(547)
Guaranty: N/A
Time: 170 WORKING DAYS
Engineer's Estimate: $1,116,438.81
Date: 02/01/2018 (8 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$1,116,438.81
$1,048,921.12
Over/Under Est: -6.05% -$67,517.69
Over/Under Est: 7.1% $79,270.89
Amt Left: 13.99% $146,788.58
Over/Under Est: 10.38% $115,929.43
Amt Left: 17.49% $183,447.12
Delta: -3.07% -$36,658.54
Over/Under Est: 14.44% $161,233.94
Amt Left: 21.81% $228,751.63
Delta: -3.68% -$45,304.51
$1,316,303.90
Over/Under Est: 17.9% $199,865.09
Amt Left: 25.49% $267,382.78
Delta: -3.02% -$38,631.15
$1,358,470.61
Over/Under Est: 21.68% $242,031.80
Amt Left: 29.51% $309,549.49
Delta: -3.20% -$42,166.71
Over/Under Est: 34.24% $382,300.39
Amt Left: 42.88% $449,818.08
Delta: -10.33% -$140,268.59
Over/Under Est: 46.35% $517,503.49
Amt Left: 55.77% $585,021.18
Delta: -9.02% -$135,203.10

Bid Items & Bid Tabulations

60 Total 0 of 60
CORYELL  |  FM 1783  |  WACO  |  1594-02-012  |  02/01/2018  |  $1,116,438.81  |  BR 2018(547)  |  REPLACE BRIDGE AND APPROACHES  |  170 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
ELLIS-MCGINNIS CONSTRUCTION CO.
JAMES CONSTRUCTION GROUP, L.L.C.
PROJECT ALLIED RESOURCES, LLC
PIERCE R & B LLC
ALTUS CONSTRUCTION LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
REECE CONSTRUCTION CO., INC.
PREPARING ROW
STA 11.000 $1,306.000 $1,000.000 $1,500.000 $9,600.000 $2,650.000 $1,450.000 $6,230.120 $3,200.000 $1,500.000
EXCAVATION (ROADWAY)
CY 518.000 $25.000 $16.000 $8.000 $6.500 $16.000 $15.000 $11.660 $16.000 $25.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 1,180.000 $11.000 $12.500 $12.000 $21.000 $21.300 $19.000 $11.600 $20.000 $25.000
FURNISHING AND PLACING TOPSOIL (4")
SY 12,313.000 $1.000 $1.250 $2.000 $1.100 $1.070 $2.000 $1.250 $3.000 $1.500
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 12,313.000 $0.270 $0.100 $0.300 $0.100 $0.460 $0.270 $1.060 $0.500 $0.250
DRILL SEEDING (TEMP) (WARM)
SY 6,157.000 $0.250 $0.130 $0.300 $0.130 $0.520 $0.270 $1.060 $0.400 $0.250
DRILL SEEDING (TEMP) (COOL)
SY 6,157.000 $0.250 $0.130 $0.300 $0.130 $0.400 $0.270 $1.060 $0.400 $0.250
VEGETATIVE WATERING
MG 198.000 $17.000 $5.000 $26.000 $19.000 $0.890 $25.000 $14.520 $1.000 $150.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 12,313.000 $1.800 $1.000 $0.900 $1.050 $0.920 $0.890 $1.910 $1.200 $1.200
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 713.000 $45.000 $45.000 $46.000 $48.000 $59.000 $53.000 $55.810 $80.000 $70.000
PRIME COAT(MC-30 OR AE-P)
GAL 610.000 $3.500 $6.000 $3.300 $3.430 $4.590 $3.480 $4.680 $5.000 $3.250
ASPH (CRS-2)
GAL 1,828.000 $6.000 $3.000 $2.600 $2.740 $3.080 $5.870 $3.890 $3.000 $2.600
AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B)
CY 24.000 $400.000 $235.000 $430.000 $453.200 $280.000 $450.000 $354.070 $300.000 $430.000
ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR)
GAL 1,067.000 $4.000 $3.450 $3.800 $3.950 $5.500 $3.960 $6.940 $5.000 $3.750
AGGR(TY D GR 3 OR TY L GR 3)
CY 33.000 $200.000 $200.000 $335.000 $353.080 $241.000 $350.000 $304.500 $250.000 $335.000
CEM STABIL BKFL
CY 79.000 $175.000 $149.000 $210.000 $135.000 $201.000 $160.000 $87.960 $220.000 $241.000
DRILL SHAFT (24 IN)
LF 144.000 $307.000 $263.000 $220.000 $280.000 $236.000 $245.000 $424.880 $220.000 $343.000
CL C CONC (ABUT)
CY 21.600 $1,200.000 $1,100.000 $900.000 $800.000 $1,020.000 $1,050.000 $1,197.270 $1,100.000 $1,363.000
CL C CONC (CAP)
CY 16.000 $900.000 $1,235.000 $1,040.000 $1,700.000 $1,240.000 $1,150.000 $164.310 $1,100.000 $1,075.000
CL C CONC (COLUMN)
CY 7.700 $1,000.000 $1,370.000 $1,040.000 $1,650.000 $1,110.000 $1,200.000 $173.840 $1,200.000 $1,569.000
REINF CONC SLAB (SLAB BEAM)
SF 3,212.000 $20.000 $16.000 $12.900 $13.000 $17.300 $14.500 $19.830 $18.000 $13.500
APPROACH SLAB
CY 48.400 $460.000 $440.000 $470.000 $500.000 $534.000 $500.000 $546.190 $550.000 $659.000
PRESTR CONC SLAB BEAM (4SB12)
LF 788.000 $173.000 $133.000 $120.000 $130.000 $118.000 $124.000 $209.890 $150.000 $155.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 2.000 $500.000 $1,200.000 $740.000 $1,200.000 $519.000 $1,800.000 $551.500 $1,000.000 $502.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 266.000 $150.000 $85.000 $100.000 $90.000 $104.000 $140.000 $169.950 $120.000 $110.000
RIPRAP (MOW STRIP)(4 IN)
CY 38.000 $484.000 $410.000 $550.000 $510.000 $525.000 $425.000 $601.690 $500.000 $525.000
RAIL (TY T401)
LF 224.000 $100.000 $133.000 $130.000 $115.000 $122.000 $158.000 $132.910 $120.000 $230.000
RC PIPE (CL III)(24 IN)
LF 36.000 $98.000 $58.000 $70.000 $80.000 $110.000 $56.000 $93.010 $60.000 $62.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,223.000 $1,150.000 $1,300.000 $1,500.000 $1,920.000 $1,175.000 $1,687.480 $1,000.000 $1,977.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $34,000.000 $19,000.000 $23,000.000 $20,000.000 $22,500.000 $22,500.000 $39,275.640 $26,000.000 $45,000.000
MOBILIZATION
LS 1.000 $95,000.000 $85,000.000 $80,000.000 $120,000.000 $127,000.000 $125,000.000 $129,278.940 $110,000.000 $136,640.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $3,000.000 $840.000 $625.000 $8,500.000 $1,080.000 $2,700.000 $10,664.550 $3,000.000 $541.250
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 192.000 $30.000 $26.000 $25.000 $26.000 $49.300 $25.500 $50.990 $50.000 $25.000
ROCK FILTER DAMS (REMOVE)
LF 192.000 $8.500 $7.000 $12.000 $7.000 $14.000 $8.500 $12.190 $20.000 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,348.000 $3.260 $4.250 $2.000 $3.000 $4.310 $2.130 $4.250 $4.000 $2.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,348.000 $0.500 $0.500 $1.000 $0.500 $0.970 $1.100 $1.770 $2.000 $0.500
CONSTRUCTING DETOURS
SY 3,799.000 $56.000 $85.000 $130.000 $82.000 $115.000 $115.000 $60.190 $120.000 $148.800
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 2,220.000 $18.000 $14.000 $5.200 $5.750 $8.100 $10.000 $7.050 $26.000 $23.500
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 2,220.000 $15.000 $12.000 $5.100 $4.350 $7.200 $10.000 $6.920 $26.000 $17.100
MTL W-BEAM GD FEN (STEEL POST)
LF 150.000 $23.000 $23.000 $23.000 $22.900 $23.800 $28.500 $30.790 $30.000 $24.900
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,595.000 $1,950.000 $1,550.000 $1,546.000 $1,600.000 $2,000.000 $2,232.180 $1,800.000 $1,941.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,200.000 $2,175.000 $2,350.000 $2,346.000 $2,430.000 $2,667.000 $3,071.180 $2,400.000 $2,350.000
CRASH CUSH ATTEN (DES SOURCE)
EA 6.000 $2,500.000 $1,800.000 $1,860.000 $3,000.000 $3,110.000 $5,105.000 $4,856.200 $3,000.000 $2,850.000
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $1,000.000 $700.000 $620.000 $1,000.000 $1,040.000 $1,935.000 $1,385.490 $2,000.000 $1,500.000
WIRE FENCE (TY C)
LF 2,282.000 $12.000 $5.200 $9.000 $11.250 $9.200 $12.000 $14.670 $20.000 $10.000
GATE (TY 1)
EA 1.000 $1,000.000 $525.000 $500.000 $1,114.050 $1,280.000 $750.000 $1,281.090 $1,000.000 $500.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 1.000 $200.000 $205.000 $175.000 $190.000 $197.000 $250.000 $304.120 $200.000 $300.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 1.000 $400.000 $310.000 $300.000 $502.290 $521.000 $500.000 $483.750 $800.000 $472.500
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 2.000 $469.000 $360.000 $350.000 $593.650 $616.000 $500.000 $716.670 $1,000.000 $575.000
REMOVE SM RD SN SUP&AM
EA 2.000 $90.000 $100.000 $30.000 $100.000 $104.000 $250.000 $121.460 $200.000 $100.000
RELOCATE SM RD SN SUP & AM TY TEMP
EA 1.000 $200.000 $205.000 $250.000 $200.000 $343.000 $250.000 $307.350 $600.000 $450.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 6.000 $30.000 $52.000 $50.000 $48.720 $51.000 $40.000 $76.970 $60.000 $43.750
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 4.000 $35.000 $52.000 $16.000 $15.740 $16.300 $40.000 $30.790 $60.000 $15.750
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 2,108.000 $0.270 $0.160 $0.200 $1.500 $1.150 $0.190 $0.330 $1.750 $1.500
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 2,194.000 $0.240 $1.720 $1.700 $1.650 $1.140 $1.750 $0.290 $1.750 $1.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 2,316.000 $1.420 $1.690 $1.650 $1.620 $1.460 $1.710 $0.350 $2.250 $2.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 402.000 $0.890 $2.030 $2.000 $1.950 $1.490 $2.190 $0.370 $5.000 $4.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,206.000 $0.950 $1.690 $1.650 $1.620 $1.510 $1.740 $0.370 $4.000 $3.000
REFL PAV MRKR TY II-A-A
EA 18.000 $5.000 $31.000 $30.000 $30.000 $15.000 $34.740 $3.840 $60.000 $50.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $11,000.000 $2,600.000 $4,670.000 $2,165.000 $10,300.000 $6,500.000 $14,733.210 $10,000.000 $24,383.000
Totals: $1,116,438.810 $1,048,921.120 $1,195,709.700 $1,232,368.240 $1,277,672.750 $1,316,303.900 $1,358,470.626 $1,498,739.200 $1,633,942.300