Show Job Controls
Bid Cobra

CORYELL FM 182 (1219-02-017)

Items: 62

County: CORYELL
Length: N/A
Highway: FM 182
District: WACO
Control Number: 1219-02-017
DBE Goal: N/A
Project: BR 2023(976)
Guaranty: N/A
Time: 270 WORKING DAYS
Engineer's Estimate: $4,205,680.80
Date: 06/28/2023 (2 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$4,205,680.80
$3,507,187.52
Over/Under Est: -16.61% -$698,493.28
Over/Under Est: -1.31% -$54,930.82
Amt Left: 18.35% $643,562.46
Subcontractor Percentage Amount
HODGES AND SON CONSTRUCTION COMPANY, INC. 3.97% $141,099.12
DIIBS SPECIALISTS, LLC 2.70% $95,961.62
JB PINNACLE GROUP, LLC 1.93% $68,594.79
CND CONTRACTING 1.53% $54,378.25
WOLFE CONSTRUCTION GROUP, INCORPORATED 1.48% $52,601.18
TIMBER T'S TREE SERVICE, LLC 1.34% $47,625.40
D. I. J. CONSTRUCTION, INC. 0.89% $31,631.79
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.85% $30,210.14
PRIMATE CONSTRUCTION, LP 0.48% $17,059.84
WILKO INDUSTRIAL, L.L.C. 0.17% $6,042.03
AWP SAFETY 0.14% $4,975.79
MURRAY CONSTRUCTION 0.08% $2,843.31
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
Total: 15.56% $553,023.26

Bid Items & Bid Tabulations

62 Total 0 of 62
CORYELL  |  FM 182  |  WACO  |  1219-02-017  |  06/28/2023  |  $4,205,680.80  |  BR 2023(976)  |  REPLACE BRIDGE AND APPROACHES  |  270 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
JAMES CONSTRUCTION GROUP, LLC
PREPARING ROW
STA 20.900 $4,262.000 $4,350.000 $6,277.600
REMOV STAB BASE AND ASPH PAV (10"-18")
SY 4,890.000 $10.000 $6.000 $13.080
REMOVING STAB BASE & ASP PAV (18"-24")
SY 1,506.000 $10.000 $9.750 $17.550
EXCAVATION (ROADWAY)
CY 831.000 $20.000 $31.000 $69.210
EXCAVATION (CHANNEL)
CY 568.000 $10.000 $42.000 $78.560
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 3,384.000 $15.000 $24.000 $37.950
FURNISHING AND PLACING TOPSOIL (4")
SY 8,403.000 $1.000 $1.500 $3.210
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 8,403.000 $2.300 $1.000 $1.310
BROADCAST SEED (TEMP) (WARM)
SY 4,202.000 $0.970 $1.160 $1.680
BROADCAST SEED (TEMP) (COOL)
SY 4,202.000 $0.580 $1.160 $1.680
VEGETATIVE WATERING
MG 136.000 $43.000 $25.000 $34.370
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 8,403.000 $4.000 $1.750 $2.180
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 1,776.000 $67.000 $75.000 $93.920
PRIME COAT(MC-30 OR AE-P)
GAL 1,253.000 $6.000 $9.500 $8.710
ASPH (CRS-2P)
GAL 3,759.000 $8.000 $5.500 $8.710
AGGR(TY D GR 3 OR TY L GR 3)
CY 67.000 $500.000 $400.000 $943.940
CEM STABIL BKFL
CY 274.000 $264.000 $295.000 $301.080
DRILL SHAFT (24 IN)
LF 705.000 $228.000 $310.000 $239.810
CL C CONC (ABUT)(HPC)
CY 66.800 $1,200.000 $1,850.000 $1,857.600
CL C CONC (CAP)(HPC)
CY 41.300 $1,300.000 $2,000.000 $2,973.890
CL C CONC (COLUMN)(HPC)
CY 16.200 $1,180.000 $2,250.000 $5,599.560
REINF CONC SLAB (SLAB BEAM)
SF 10,278.000 $26.000 $25.000 $35.620
APPROACH SLAB
CY 165.200 $637.000 $700.000 $904.590
PRESTR CONC SLAB BEAM (4SB12)
LF 1,736.000 $244.000 $215.000 $293.950
PRESTR CONC SLAB BEAM (4SB15)
LF 791.380 $255.000 $225.000 $262.270
RIPRAP (STONE PROTECTION)(18 IN)
CY 2,340.000 $227.000 $148.000 $186.270
RIPRAP (MOW STRIP)(4 IN)
CY 109.000 $626.000 $700.000 $623.240
RAIL (TY T223)
LF 228.000 $168.000 $170.000 $123.100
RAIL (TY SSTR)
LF 488.000 $95.000 $170.000 $136.370
ARMOR JOINT (SEALED)
LF 178.000 $152.000 $130.000 $128.310
RC PIPE (CL III)(18 IN)
LF 50.000 $80.000 $110.000 $134.580
RC PIPE (CL III)(24 IN)
LF 80.000 $99.000 $125.000 $178.850
RC PIPE (ARCH)(CL III)(DES 1)
LF 50.000 $189.000 $245.000 $256.870
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,343.000 $1,500.000 $2,607.700
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,832.000 $2,000.000 $2,832.090
SET (TY II) (DES 1) (RCP) (6: 1) (P)
EA 4.000 $2,038.000 $2,000.000 $2,323.130
REMOV STR (SET)
EA 2.000 $661.000 $750.000 $650.960
REMOV STR (PIPE)
LF 77.000 $21.000 $50.000 $32.510
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $30,990.000 $35,000.000 $18,332.400
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $96,990.000 $42,000.000 $36,664.800
MOBILIZATION
LS 1.000 $650,000.000 $350,000.000 $225,225.900
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $9,500.000 $3,450.000 $3,607.990
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 503.000 $50.000 $42.000 $58.810
ROCK FILTER DAMS (REMOVE)
LF 503.000 $10.000 $12.000 $43.570
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,435.000 $4.000 $7.000 $5.080
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,435.000 $1.000 $1.150 $1.450
DRIVEWAYS (ACP)
SY 366.000 $45.000 $95.000 $146.540
MTL W-BEAM GD FEN (STEEL POST)
LF 975.000 $29.000 $35.000 $42.840
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 12.000 $2,452.000 $3,500.000 $3,485.310
SHORT RADIUS
LF 72.000 $101.000 $35.000 $43.570
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $927.000 $950.000 $1,161.770
MTL BM GD FEN TRANS (31"-28")(25')
EA 1.000 $549.700 $1,000.000 $1,270.690
GUARDRAIL END TREATMENT (INSTALL)
EA 11.000 $3,106.000 $3,400.000 $4,284.030
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 2.000 $483.000 $1,750.000 $649.140
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 18.000 $22.000 $35.000 $43.350
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 66.000 $4.000 $30.000 $77.970
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 4,240.000 $1.000 $3.750 $1.580
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 716.000 $1.000 $0.180 $1.580
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 3,524.000 $1.000 $3.750 $1.580
REFL PAV MRKR TY II-A-A
EA 55.000 $11.000 $29.000 $10.890
D-GR HMA TY-C SAC-B PG64-22 (EXEMPT)
TON 689.000 $575.000 $175.000 $252.690
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 168.000 $131.000 $100.000 $78.830
Totals: $4,205,680.800 $3,507,187.520 $4,150,750.000