CORYELL 704540 (0909-36-198)

Items: 70

County: CORYELL
Length: 0.0000 MILES
Highway: 704540
District: WACO
Control Number: 0909-36-198
DBE Goal: 0.0%
Project:
Guaranty: $100,000.00
Time: 210 WORKING DAYS
Engineer's Estimate: $5,528,179.14
Date: 06/04/2025 (1 year ago)
Contract Number: 6253037
Type: RECONSTRUCT EXISTING ROADWAY
Project ID: A00201726
Project Description: THIS PROJECT CONSISTS OF RECONSTRUCTING AND WIDENING TURKEY RUN RD FROM CLEAR CREEK RD TO WEST RANGE RD (APPROX. 5,300’ X 24’, WITH 10’ UNPAVED SHOULDER, EACH SIDE).
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MICHAEL YATES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$5,528,179.14
$4,647,464.00
Over/Under Est: -15.93% -$880,715.14
Over/Under Est: -1.85% -$102,304.99
Amt Left: 16.75% $778,410.15
Over/Under Est: 9% $497,496.70
Amt Left: 29.66% $1,378,211.84
Delta: -11.05% -$599,801.69
$6,551,084.37
Over/Under Est: 18.5% $1,022,905.23
Amt Left: 40.96% $1,903,620.37
Delta: -8.72% -$525,408.53
Subcontractor Percentage Amount
LONE STAR PAVING COMPANY 15.07% $700,372.82
BRYANT & FREY CONSTRUCTION CO. 2.68% $124,552.04
WOLFE CONSTRUCTION GROUP, INCORPORATED 1.30% $60,417.03
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.88% $40,897.68
D. I. J. CONSTRUCTION, INC. 0.80% $37,179.71
Total: 20.73% $963,419.28

Bid Items & Bid Tabulations

70 Total 0 of 70
CORYELL  |  704540  |  WACO  |  0909-36-198  |  06/04/2025  |  $5,528,179.14  |   |  RECON EXIST ROADWAY  |  210 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TTG UTILITIES, INC.
BIG CREEK CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
C. E. BARKER, LTD.
PREPARING ROW
STA 53.000 $1,000.000 $500.000 $1,300.000 $1,200.000 $12,250.000
REMOV CONC (PAV)
SY 12,675.000 $21.000 $6.500 $8.500 $9.000 $3.220
REMOV CONC (DRIVEWAYS)
SY 2,857.000 $12.000 $6.500 $12.000 $15.600 $3.220
EXCAV (ROADWAY)
CY 5,181.000 $12.000 $7.000 $15.000 $15.300 $36.400
EMBANK (FNL)(OC)(TY C1)
CY 16,602.000 $5.000 $10.000 $25.000 $40.000 $36.400
BACKFILL (TY A OR B)
STA 53.000 $400.000 $658.000 $650.000 $500.000 $546.000
FURN & PLACE TOPSOIL (4")
SY 16,823.000 $5.000 $2.650 $3.000 $4.000 $3.770
DRILL SEED (PERM_RURAL_CLAY)
SY 16,823.000 $2.000 $0.350 $0.400 $0.290 $0.290
DRILL SEED (TEMP_WARM_COOL)
SY 16,823.000 $1.500 $0.300 $0.350 $0.240 $0.240
VEGETATIVE WATERING
TGL 274.000 $15.000 $39.000 $40.000 $50.000 $54.600
SOIL RET BLKT(SL_MOD_CLAY_LONG)
SY 8,412.000 $2.000 $1.500 $2.500 $1.200 $1.480
PROOF ROLLING
HR 5.000 $150.000 $74.000 $200.000 $140.000 $91.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 7,308.000 $68.000 $51.000 $72.000 $72.000 $68.950
LIME (COM OR QK)(SLURRY)
TON 276.000 $325.000 $335.000 $300.000 $285.000 $296.400
LIME TRT (EXIST MATL)(6")
SY 13,797.000 $6.000 $5.650 $4.250 $8.000 $5.460
LIME TRT (EXIST MATL)(8")
SY 4,961.000 $7.000 $6.500 $6.000 $8.000 $7.280
SALV, HAUL & STKPL RCL APH PV (2"-6")
SY 14,407.000 $10.000 $2.200 $2.500 $3.000 $4.730
PRIME COAT(MC-30 OR AE-P)
GAL 5,208.000 $4.500 $4.650 $4.250 $4.500 $10.400
ASPH (CRS-2P)
GAL 5,432.000 $6.000 $4.650 $4.500 $3.750 $15.600
AGGR (TY-D OR L, GR-4)
CY 90.000 $180.000 $345.000 $275.000 $325.000 $312.000
D-GR HMA TY-B PG64-22
TON 3,202.000 $100.000 $121.500 $120.000 $148.000 $171.600
SP MIXES SP-C SAC-B PG70-22
TON 1,992.000 $115.000 $150.000 $125.000 $166.000 $192.400
TACK COAT
GAL 2,457.000 $4.000 $4.650 $3.500 $3.050 $6.240
CONC PVMT (CPCD) (10")
SY 4,651.000 $110.000 $115.000 $130.000 $118.000 $91.680
CEM STABIL BKFL
CY 300.000 $100.000 $235.000 $180.000 $235.000 $210.600
TRENCH EXCAVATION PROTECTION
LF 206.100 $30.000 $4.000 $20.000 $4.000 $26.260
CL A CONC (COLLAR)
EA 1.000 $1,500.000 $747.820 $3,750.000 $750.000 $5,460.000
RIPRAP (CONC)(5 IN)
CY 251.000 $575.000 $485.000 $450.000 $495.000 $670.800
RIPRAP (STONE PROTECTION)(18 IN)
CY 976.140 $140.000 $117.000 $125.000 $120.000 $160.160
CONC BOX CULV (8 FT X 6 FT)
LF 550.000 $1,150.000 $785.000 $685.000 $805.000 $922.880
RC PIPE (CL III)(18 IN)
LF 2.000 $150.000 $196.000 $200.000 $200.000 $148.140
RC PIPE (CL III)(24 IN)
LF 44.000 $155.000 $133.000 $175.000 $135.000 $158.410
RC PIPE (CL III)(36 IN)
LF 26.500 $180.000 $240.000 $300.000 $245.000 $208.710
RC PIPE (CL IV)(18 IN)
LF 105.000 $150.000 $160.000 $150.000 $165.000 $148.140
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 2.000 $6,300.000 $5,930.000 $6,500.000 $6,065.000 $6,292.000
INLET (COMPL)(PAZD)(SL)(3FTX3FT)
EA 1.000 $7,500.000 $4,500.000 $8,000.000 $4,590.000 $8,892.000
WINGWALL (PW - 1) (HW=8 FT)
EA 4.000 $60,000.000 $30,000.000 $34,000.000 $30,000.000 $30,680.000
WINGWALL (PW - 1) (HW=11 FT)
EA 2.000 $70,000.000 $38,000.000 $40,000.000 $39,000.000 $40,456.000
SET (TY I) (36 IN) (3: 1) (C)
EA 1.000 $6,000.000 $6,200.000 $14,000.000 $6,350.000 $3,146.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $9,400.000 $920.000 $2,100.000 $940.000 $2,106.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $4,350.000 $1,275.000 $2,300.000 $1,300.000 $2,626.000
JACK BOR OR TUN PIPE(36 IN)(RC)(CL III)
LF 96.000 $1,575.000 $1,640.000 $1,700.000 $1,670.000 $2,280.200
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 4.000 $3,000.000 $750.000 $700.000 $750.000 $546.000
REMOV STR (PIPE)
LF 492.000 $35.000 $19.000 $40.000 $19.000 $27.300
MOBILIZATION
LS 1.000 $502,143.560 $325,000.000 $540,000.000 $591,200.000 $580,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $3,000.000 $1,100.000 $2,500.000 $2,500.000 $3,952.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 350.000 $50.000 $70.000 $38.000 $35.000 $50.860
ROCK FILTER DAMS (REMOVE)
LF 350.000 $17.000 $46.000 $11.000 $10.000 $29.280
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,310.000 $5.000 $3.500 $4.000 $3.850 $4.160
TEMP SDMT CONT FENCE (INLET PROTECTION)
LF 20.000 $7.000 $5.800 $11.000 $10.000 $16.170
TEMP SEDMT CONT FENCE (REMOVE)
LF 10,330.000 $1.600 $1.150 $1.500 $1.250 $1.300
CONC CURB (MONO) (TY II)
LF 98.000 $11.000 $31.000 $40.000 $32.000 $15.600
CONCRETE GUTTER (MODIFIED)
LF 5,980.000 $20.000 $16.500 $38.000 $16.900 $15.600
INTERSECTIONS (CONC)
SY 232.000 $140.000 $145.000 $175.000 $240.000 $102.180
DRIVEWAYS (CONC) (TY 1)
SY 1,998.000 $110.000 $148.000 $140.000 $190.000 $102.180
DRIVEWAYS (CONC) (TY 2)
SY 1,012.000 $140.000 $184.000 $130.000 $210.000 $102.180
ALUMINUM SIGNS (TY A)
SF 66.250 $40.000 $50.000 $40.000 $15.000 $212.160
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 11.000 $850.000 $1,000.000 $800.000 $881.000 $846.820
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
EA 2.000 $400.000 $390.000 $175.000 $764.000 $476.320
REMOVE SM RD SN SUP&AM
EA 11.000 $160.000 $95.000 $150.000 $212.000 $98.800
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 30.000 $1.200 $17.350 $15.000 $15.000 $15.600
PAVEMENT SLER 6"
LF 16,653.000 $0.600 $0.750 $0.450 $0.640 $0.670
PAVEMENT SLER 24"
LF 30.000 $2.800 $4.650 $3.500 $4.000 $4.160
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 9,046.000 $4.000 $1.400 $0.750 $1.200 $1.250
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 436.000 $1.200 $1.150 $1.250 $1.000 $1.040
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 7,852.000 $1.200 $1.400 $1.000 $1.220 $1.270
REFL PAV MRKR TY II-A-A
EA 107.000 $10.000 $8.100 $6.250 $7.000 $7.280
PAV SURF PREP FOR MRK (6")
LF 16,653.000 $0.360 $0.150 $0.350 $0.130 $0.140
PAV SURF PREP FOR MRK (24")
LF 30.000 $2.200 $1.150 $2.500 $1.000 $1.040
AIR RELEASE/VAC RELEASE VALVE (2IN)
EA 1.000 $12,500.000 $15,000.000 $10,000.000 $18,000.000 $3,770.000
Totals: $5,528,179.140 $4,647,464.000 $5,425,874.150 $6,025,675.840 $6,551,084.363
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $25,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $30,000.00
Total: $55,000.00