Show Job Controls
Bid Cobra

CORYELL BS 36-E (0184-05-005)

Items: 58

County: CORYELL
Length: N/A
Highway: BS 36-E
District: WACO
Control Number: 0184-05-005
DBE Goal: N/A
Project: F 2022(557)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $1,028,751.36
Date: 06/02/2022 (4 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$1,028,751.36
$1,274,745.89
Over/Under Est: 23.91% $245,994.53
Over/Under Est: 23.92% $246,101.84
Amt Left: 0.01% $107.31
Over/Under Est: 26.7% $274,710.67
Amt Left: 2.25% $28,716.14
Delta: -2.24% -$28,608.83

Bid Items & Bid Tabulations

58 Total 0 of 58
CORYELL  |  BS 36-E  |  WACO  |  0184-05-005  |  06/02/2022  |  $1,028,751.36  |  F 2022(557)  |  SURF/ROADWAY RESTOR  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
BIG CREEK CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 10.000 $18.000 $190.000 $50.000 $383.000
BACKFILL (TY B)
STA 57.900 $175.000 $318.000 $250.000 $130.000
BLOCK SODDING
SY 100.000 $3.000 $11.000 $15.000 $10.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 1,000.000 $45.000 $60.850 $65.000 $69.000
PLANE ASPH CONC PAV (1.5")
SY 35,077.000 $2.000 $1.600 $2.000 $1.800
TRENCH EXCAVATION PROTECTION
LF 3.000 $150.000 $22.250 $50.000 $20.000
TEMPORARY SPL SHORING
SF 105.000 $20.000 $111.000 $80.000 $100.000
DRILL SHAFT (TRF SIG POLE) (30 IN)
LF 22.000 $372.530 $440.000 $1,200.000 $396.000
RIPRAP (CONC)(5 IN)
CY 10.000 $425.000 $835.000 $650.000 $750.000
RIPRAP (MOW STRIP)(4 IN)
CY 34.000 $500.000 $835.000 $650.000 $750.000
CONC BOX CULV (8 FT X 4 FT)(EXTEND)
LF 6.000 $700.000 $1,111.000 $2,200.000 $1,000.000
WINGWALL (FW - 0) (HW=6 FT)
EA 1.000 $7,900.000 $13,890.000 $17,000.000 $12,500.000
ADJUSTING MANHOLES
EA 1.000 $850.000 $3,335.000 $2,000.000 $3,000.000
CLEAN EXIST CULVERTS
EA 1.000 $2,000.000 $2,700.000 $4,000.000 $2,500.000
MOBILIZATION
LS 1.000 $120,000.000 $78,718.000 $126,000.000 $104,050.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $8,200.000 $5,400.000 $4,000.000 $13,600.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 35.000 $32.000 $40.000 $30.000 $38.000
ROCK FILTER DAMS (REMOVE)
LF 35.000 $9.250 $10.000 $6.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 500.000 $2.750 $13.300 $5.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 500.000 $0.800 $2.250 $1.000 $2.000
MTL W-BEAM GD FEN (STEEL POST)
LF 600.000 $30.000 $38.350 $42.000 $31.500
REMOVE METAL BEAM GUARD FENCE
LF 700.000 $2.040 $2.250 $7.500 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $139.880 $278.000 $550.000 $150.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,800.000 $3,390.000 $4,000.000 $2,900.000
ALUMINUM SIGNS (TY A)
SF 66.000 $36.640 $144.000 $35.000 $130.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 2.000 $390.450 $575.000 $1,000.000 $1,600.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 9.000 $32.000 $39.000 $30.000 $35.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 2,266.000 $0.200 $1.200 $0.850 $0.770
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 480.000 $0.200 $2.750 $0.850 $0.770
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 1,138.000 $0.230 $1.200 $0.850 $0.770
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 164.000 $1.010 $0.950 $1.500 $1.050
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,244.000 $1.010 $0.950 $1.500 $1.050
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 363.000 $1.020 $2.750 $1.100 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 804.000 $0.810 $1.550 $1.100 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 394.000 $7.150 $8.000 $8.500 $7.770
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
EA 2.000 $430.000 $445.000 $300.000 $275.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 280.000 $0.400 $2.250 $0.550 $0.520
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 11,118.000 $0.530 $0.500 $0.550 $0.520
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,260.000 $0.200 $0.550 $0.550 $0.520
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 11,318.000 $0.270 $0.480 $0.550 $0.520
PREFAB PAV MRK TY C (W) (ARROW)
EA 6.000 $210.000 $272.000 $300.000 $275.000
PREFAB PAV MRK TY C (W) (WORD)
EA 6.000 $265.000 $350.000 $375.000 $340.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 25.000 $30.000 $55.550 $37.000 $34.000
REFL PAV MRKR TY I-C
EA 76.000 $3.800 $5.350 $3.800 $3.470
REFL PAV MRKR TY II-A-A
EA 1,704.000 $3.300 $5.300 $3.800 $3.470
ELIM EXT PAV MRK & MRKS (4")
LF 3,293.000 $0.400 $1.100 $1.100 $1.000
VEH SIG SEC (12")LED(YEL)
EA 10.000 $287.920 $350.000 $500.000 $315.000
BACK PLATE (12")(1 SEC)
EA 10.000 $120.000 $174.000 $250.000 $156.000
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 2.000 $5,314.820 $8,655.000 $6,000.000 $7,789.000
INS TRF SIG PL AM (S)1 ARM(28')
EA 2.000 $8,000.000 $11,055.000 $14,000.000 $9,949.000
CAM (ASPHALT) PG(70-22)
TON 131.000 $150.000 $175.550 $180.000 $206.000
CAM (AGGREGATE)
TON 1,798.000 $149.600 $175.550 $180.000 $206.000
TOM-C PG76-22 SAC-A
TON 1,930.000 $135.000 $184.000 $180.000 $200.800
TACK COAT
GAL 7,016.000 $3.000 $4.450 $2.000 $0.010
UNDERSEAL COURSE
GAL 8,769.000 $3.010 $5.250 $2.000 $0.010
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $125.000 $275.000 $150.000 $130.000
TMA (STATIONARY)
DAY 43.000 $190.000 $540.000 $150.000 $286.000
TMA (MOBILE OPERATION)
HR 90.000 $55.000 $91.000 $100.000 $25.000
Totals: $1,028,751.360 $1,274,745.890 $1,274,853.200 $1,303,462.030