Show Job Controls
Bid Cobra

COOKE FM3164 (6425-80-001)

Items: 21

County: COOKE
Length: N/A
Highway: FM3164
District: WICHITA FALLS
Control Number: 6425-80-001
DBE Goal: N/A
Project: RMC - 642580001
Guaranty: N/A
Time: 36 W
Engineer's Estimate: $2,714,259.64
Date: 12/02/2022 (3 years ago)
Contract Number: N/A
Type: SEAL COAT
Mail/Deliver Bids To: N/A
MICHAEL REYNOLDS
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$2,714,259.64
$2,382,691.00
Over/Under Est: -12.22% -$331,568.64
Over/Under Est: -8.79% -$238,543.18
Amt Left: 3.9% $93,025.46
$3,474,995.72
Over/Under Est: 28.03% $760,736.08
Amt Left: 45.84% $1,092,304.72
Delta: -40.36% -$999,279.26
Over/Under Est: 34.89% $947,048.39
Amt Left: 53.66% $1,278,617.03
Delta: -5.36% -$186,312.31

Bid Items & Bid Tabulations

21 Total 0 of 21
COOKE  |  FM3164  |  WICHITA FALLS  |  6425-80-001  |  12/02/2022  |  $2,714,259.64  |  RMC - 642580001  |  SEAL COAT  |  36 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
NORTHEASTERN PAVERS, LLC
RONALD R. WAGNER & CO., LP
CK NEWBERRY, LLC
PEACHTREE CONSTRUCTION, LTD.
AGGR (LOAD HAUL & DISTRIB)
CY 8,280.000 $17.500 $23.500 $12.000 $60.000 $65.000
ASPH (AC-20-5TR)
GAL 421,682.000 $4.150 $3.300 $3.639 $4.500 $4.640
MOBILIZATION
LS 1.000 $246,751.000 $225,000.000 $290,162.680 $425,000.000 $200,000.000
BARR, SIGNS, TRAFFIC HANDLING
EA 11.000 $887.000 $5,000.000 $0.010 $1,000.000 $13,000.000
INTERSECTIONS (SURF TREAT)
SY 7,681.000 $4.500 $3.000 $2.700 $7.000 $13.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 80.000 $1.000 $0.010 $0.010 $0.010 $4.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 10,359.000 $1.000 $0.010 $0.010 $0.010 $4.000
REF PROF PAV MRK TY I(W)4"(SLD)(090MIL)
LF 215,729.000 $0.590 $0.540 $0.610 $0.650 $0.770
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 292,301.000 $0.500 $0.540 $0.610 $0.650 $0.770
REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL)
LF 57,262.000 $0.550 $0.550 $0.610 $0.750 $1.100
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 56,542.000 $0.510 $0.330 $0.340 $0.430 $0.500
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 11,955.000 $0.500 $0.340 $0.340 $0.510 $0.600
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 162,529.000 $0.490 $0.330 $0.340 $0.430 $0.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 228.000 $13.710 $15.000 $12.000 $13.750 $16.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 1.000 $676.730 $700.000 $600.000 $775.000 $1,100.000
REFL PAV MRKR TY II-A-A
EA 10,359.000 $3.850 $3.750 $3.500 $4.250 $3.850
ELIM EXT PAV MRK & MRKS (24")
LF 228.000 $3.780 $5.000 $4.000 $10.000 $5.500
ELIM EXT PAV MRK & MRKS (RR XING)
EA 1.000 $350.000 $350.000 $200.000 $500.000 $275.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 11,128.000 $4.050 $6.000 $6.000 $4.500 $3.950
TMA (STATIONARY)
DAY 11.000 $225.000 $0.010 $0.010 $500.000 $300.000
TMA (MOBILE OPERATION)
DAY 22.000 $275.000 $0.010 $0.010 $500.000 $800.000
Totals: $2,714,259.640 $2,382,691.000 $2,475,716.468 $3,474,995.720 $3,661,308.030