Show Job Controls
Bid Cobra

COOKE COUNTY ROAD 341 (0903-15-106)

Items: 39

County: COOKE
Length: 0.0000 MILES
Highway: COUNTY ROAD 341
District: WICHITA FALLS
Control Number: 0903-15-106
DBE Goal: 5.0%
Project: BR 2024(312)
Guaranty: $55,000.00
Time: 221 WORKING DAYS
Engineer's Estimate: $2,751,439.30
Date: 07/01/2025 (11 months ago)
Contract Number: 7253013
Type: BRIDGE REPLACEMENT
Project ID: A00183418
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
COLBY SHELTON
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$2,751,439.30
$2,437,820.96
Over/Under Est: -11.4% -$313,618.34
Over/Under Est: -8.61% -$236,870.30
Amt Left: 3.15% $76,748.04
$2,657,248.50
Over/Under Est: -3.42% -$94,190.80
Amt Left: 9% $219,427.54
Delta: -5.67% -$142,679.50
Over/Under Est: -2.23% -$61,382.00
Amt Left: 10.35% $252,236.34
Delta: -1.23% -$32,808.80
$2,757,154.20
Over/Under Est: 0.21% $5,714.90
Amt Left: 13.1% $319,333.24
Delta: -2.49% -$67,096.90
Over/Under Est: 14.36% $395,233.70
Amt Left: 29.08% $708,852.04
Delta: -14.13% -$389,518.80
$3,237,266.00
Over/Under Est: 17.66% $485,826.70
Amt Left: 32.79% $799,445.04
Delta: -2.88% -$90,593.00
$4,013,933.25
Over/Under Est: 45.88% $1,262,493.95
Amt Left: 64.65% $1,576,112.29
Delta: -23.99% -$776,667.25
Subcontractor Percentage Amount
HODGES AND SON CONSTRUCTION COMPANY, INC. 9.01% $219,647.67
MORRIS COUNTY CONTRACTORS, L.L.C. 5.47% $133,348.81
PEACHTREE CONSTRUCTION, LTD. 1.99% $48,512.64
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.93% $22,671.73
DALLAS LITE AND BARRICADE, INC. 0.78% $19,015.00
TORO BRAVO CONSTRUCTION, LLC 0.06% $1,462.69
Total: 18.24% $444,658.54

Bid Items & Bid Tabulations

39 Total 0 of 39
COOKE  |  COUNTY ROAD 341  |  WICHITA FALLS  |  0903-15-106  |  07/01/2025  |  $2,751,439.30  |  BR 2024(312)  |  BRIDGE REPL  |  221 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
SKYLINE BRIDGE LLC
COPPELL CONSTRUCTION CO., INC.
TALBERT COMPANIES LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
IBCTX, LLC
EARTH BUILDERS, L.P.
PREPARING ROW
STA 20.000 $3,500.000 $1,800.000 $5,600.000 $3,500.000 $3,500.000 $4,950.000 $3,000.000 $3,000.000 $25,000.000
EXCAV (ROADWAY)
CY 865.000 $40.000 $20.000 $25.000 $16.000 $38.000 $22.000 $25.000 $40.000 $30.000
EXCAV (CHANNEL)
CY 828.000 $44.000 $20.000 $25.000 $18.000 $36.000 $60.500 $25.000 $50.000 $30.000
EMBANK (FNL)(OC)(TY B)
CY 545.000 $42.000 $20.000 $30.000 $50.000 $55.000 $85.800 $40.000 $55.000 $40.000
BROADCAST SEED (PERM_RURAL_SAND)
SY 3,460.000 $10.000 $0.770 $1.500 $1.250 $0.700 $0.770 $1.000 $6.000 $8.000
FERTILIZER
AC 0.720 $560.000 $550.000 $500.000 $500.000 $500.000 $550.000 $650.000 $1,500.000 $2,500.000
VEGETATIVE WATERING
TGL 31.000 $90.000 $10.000 $1.000 $1.000 $50.000 $66.000 $250.000 $1.000 $375.000
FL BS (CMP IN PLC)(TY B GR 5) (6")
SY 2,840.000 $45.000 $54.000 $40.000 $55.000 $38.000 $60.500 $20.000 $30.000 $45.000
FL BS (CMP IN PLC)(TY B GR 5) (10")
SY 832.000 $45.000 $54.000 $45.000 $78.000 $41.000 $60.500 $20.000 $45.000 $75.000
D-GR HMA TY-D PG64-22
TON 220.000 $200.000 $242.350 $250.000 $250.000 $213.500 $234.850 $400.000 $250.000 $350.000
TACK COAT
GAL 27.000 $10.500 $2.750 $8.000 $100.000 $2.500 $2.750 $30.000 $3.000 $80.000
CEM STABIL BKFL
CY 287.000 $180.000 $340.000 $250.000 $325.000 $335.000 $275.000 $500.000 $350.000 $450.000
DRILL SHAFT (36 IN)
LF 1,046.000 $305.000 $257.300 $210.000 $360.000 $275.000 $242.000 $500.000 $350.000 $450.000
CL C CONC (ABUT)
CY 145.000 $1,720.000 $1,100.000 $1,600.000 $1,600.000 $1,200.000 $1,320.000 $1,200.000 $2,000.000 $2,500.000
CL C CONC (CAP)
CY 22.000 $1,950.000 $1,500.000 $2,000.000 $2,000.000 $1,200.000 $3,540.000 $1,500.000 $2,000.000 $2,500.000
CL C CONC (COLUMN)
CY 18.000 $1,680.000 $2,500.000 $2,200.000 $2,100.000 $1,000.000 $1,430.000 $1,300.000 $2,000.000 $2,500.000
CL C CONC (MISC)
CY 18.000 $2,000.000 $1,100.000 $2,000.000 $1,000.000 $2,100.000 $1,540.000 $1,000.000 $2,000.000 $2,000.000
REINF CONC SLAB
SF 8,335.000 $45.000 $34.500 $35.000 $35.000 $35.000 $33.000 $50.000 $50.000 $45.000
APPROACH SLAB
CY 42.000 $1,040.000 $1,000.000 $900.000 $900.000 $1,000.000 $1,045.000 $1,500.000 $1,300.000 $1,400.000
PRESTR CONC GIRDER (TX28)
LF 1,236.000 $235.000 $246.860 $265.000 $275.000 $295.000 $210.122 $325.000 $350.000 $350.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 437.000 $250.000 $200.000 $220.000 $225.000 $230.000 $308.000 $300.000 $180.000 $240.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 382.000 $180.000 $200.000 $230.000 $250.000 $230.000 $308.000 $300.000 $185.000 $240.000
MISC NON-BRIDGE (NBIS)
LB 112.000 $18.000 $10.000 $12.000 $60.000 $15.000 $82.500 $50.000 $80.000 $25.000
RAIL (TY T631)
LF 772.000 $160.000 $100.710 $90.000 $100.000 $90.000 $110.000 $140.000 $110.000 $180.000
SEALED EXPANSION JOINT (4 IN) (SEJ - B)
LF 224.000 $150.000 $150.000 $250.000 $175.000 $165.000 $242.000 $500.000 $250.000 $160.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $15,000.000 $44,250.000 $25,000.000 $15,000.000 $40,000.000 $16,500.000 $25,000.000 $40,000.000 $45,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $121,000.000 $44,250.000 $40,000.000 $38,000.000 $70,000.000 $38,500.000 $30,000.000 $60,000.000 $65,000.000
MOBILIZATION
LS 1.000 $185,215.600 $240,000.000 $200,000.000 $225,000.000 $215,000.000 $369,000.000 $300,000.000 $323,000.000 $390,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $5,000.000 $2,651.850 $8,700.000 $2,500.000 $15,000.000 $3,850.000 $3,500.000 $8,000.000 $3,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 282.000 $55.000 $28.600 $1.000 $35.000 $26.000 $28.600 $33.000 $90.000 $75.000
ROCK FILTER DAMS (REMOVE)
LF 282.000 $20.000 $10.000 $1.000 $10.000 $15.000 $16.500 $6.000 $60.000 $53.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,197.000 $6.000 $3.190 $1.000 $4.000 $2.900 $3.190 $4.000 $10.000 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,197.000 $2.000 $1.100 $1.000 $1.500 $1.000 $1.100 $2.000 $7.000 $3.250
MTL W-BEAM GD FEN (TIM POST)
LF 1,225.000 $40.000 $24.750 $24.000 $28.000 $22.500 $30.305 $30.000 $28.000 $32.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,600.000 $1,430.000 $1,400.000 $1,750.000 $1,300.000 $1,705.000 $1,700.000 $1,600.000 $1,800.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $3,300.000 $3,000.000 $3,400.000 $3,000.000 $3,223.000 $3,900.000 $3,600.000 $3,200.000
CHAIN LINK FENCE (INSTALL) (6')
LF 208.000 $38.000 $96.000 $80.000 $50.000 $50.000 $55.000 $75.000 $55.000 $30.000
CHAIN LINK FENCE (REMOVE)
LF 208.000 $13.000 $10.000 $20.000 $8.000 $10.000 $27.500 $10.000 $20.000 $6.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 28.000 $45.000 $27.500 $25.000 $50.000 $25.000 $71.500 $35.000 $30.000 $30.000
Totals: $2,751,439.300 $2,437,820.960 $2,514,569.000 $2,657,248.500 $2,690,057.300 $2,757,154.197 $3,146,673.000 $3,237,266.000 $4,013,933.250
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $10,000.00