COOKE CR (0903-15-085)

Items: 45

County: COOKE
Length: N/A
Highway: CR
District: WICHITA FALLS
Control Number: 0903-15-085
DBE Goal: N/A
Project: BR 2006(656)
Guaranty: N/A
Time: 168 WORKING DAYS
Engineer's Estimate: $1,043,507.40
Date: 03/06/2019 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (9)
E
Engineer's Estimate
$1,043,507.40
Over/Under Est: 4.46% $46,532.40
$1,147,700.70
Over/Under Est: 9.98% $104,193.30
Amt Left: 5.29% $57,660.90
Over/Under Est: 17.64% $184,107.00
Amt Left: 12.62% $137,574.60
Delta: -6.96% -$79,913.70
Over/Under Est: 19.73% $205,848.60
Amt Left: 14.62% $159,316.20
Delta: -1.77% -$21,741.60
Over/Under Est: 22.95% $239,433.86
Amt Left: 17.7% $192,901.46
Delta: -2.69% -$33,585.26
$1,441,583.20
Over/Under Est: 38.15% $398,075.80
Amt Left: 32.25% $351,543.40
Delta: -12.37% -$158,641.94
$1,455,760.08
Over/Under Est: 39.51% $412,252.68
Amt Left: 33.55% $365,720.28
Delta: -0.98% -$14,176.88
$1,517,905.70
Over/Under Est: 45.46% $474,398.30
Amt Left: 39.25% $427,865.90
Delta: -4.27% -$62,145.62
$1,576,031.50
Over/Under Est: 51.03% $532,524.10
Amt Left: 44.58% $485,991.70
Delta: -3.83% -$58,125.80

Bid Items & Bid Tabulations

45 Total 0 of 45
COOKE  |  CR  |  WICHITA FALLS  |  0903-15-085  |  03/06/2019  |  $1,043,507.40  |  BR 2006(656)  |  REPLACE BRIDGE AND APPROACHES  |  168 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HODGES AND SON CONSTRUCTION COMPANY, INC.
PIERCE R & B LLC
STATELINE CONSTRUCTION, LLC
ASHLAR CONTRACTING COMPANY
COPPELL CONSTRUCTION CO., INC.
CDM HOLDINGS, LLC
JAGOE-PUBLIC COMPANY
EARTH BUILDERS LP
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 12.000 $1,200.000 $3,000.000 $2,000.000 $2,260.000 $3,500.000 $910.000 $800.000 $8,000.000 $8,000.000 $10,000.000
EXCAVATION (ROADWAY AND CHANNEL)
CY 961.000 $20.000 $10.000 $12.000 $17.000 $15.000 $16.000 $20.000 $16.000 $30.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 631.000 $25.000 $20.000 $21.000 $22.000 $15.000 $16.500 $22.000 $23.000 $30.000 $30.000
FURNISHING AND PLACING TOPSOIL (4")
SY 3,772.000 $1.000 $2.500 $3.000 $5.250 $8.000 $2.000 $2.650 $4.000 $2.000 $6.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 3,772.000 $0.250 $1.000 $0.950 $1.000 $2.000 $0.900 $1.250 $0.950 $2.600 $1.000
DRILL SEEDING (TEMP) (WARM)
SY 1,886.000 $0.250 $0.500 $0.740 $1.000 $1.000 $0.680 $1.000 $0.720 $5.000 $1.000
DRILL SEEDING (TEMP) (COOL)
SY 1,886.000 $0.250 $0.500 $0.740 $0.500 $1.000 $0.680 $1.000 $0.720 $5.000 $1.000
VEGETATIVE WATERING
MG 121.600 $25.000 $1.000 $25.000 $10.000 $170.000 $20.000 $21.000 $76.220 $50.000 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 3,772.000 $2.000 $1.500 $1.060 $2.250 $2.000 $1.000 $1.500 $1.050 $4.000 $6.500
PROOF ROLLING
HR 3.000 $100.000 $10.000 $75.000 $50.000 $550.000 $40.000 $85.000 $82.690 $100.000 $150.000
FL BS (CMP IN PLC)(TYA GR1-2) (6")
SY 2,578.000 $18.000 $28.000 $13.500 $31.000 $17.000 $18.000 $18.000 $29.000 $20.000 $25.000
PRIME COAT (MC-30)
GAL 214.000 $4.250 $12.000 $13.500 $12.000 $33.000 $20.000 $10.000 $14.210 $35.000 $10.000
ASPH (AC-20-5TR)
GAL 616.000 $4.000 $10.000 $16.550 $15.000 $16.000 $10.000 $10.000 $17.420 $25.000 $10.000
AGGR(TY-B GR-4 SAC-B)
CY 18.000 $80.000 $400.000 $860.000 $900.000 $800.000 $625.000 $225.000 $905.370 $1,000.000 $300.000
CEM STABIL BKFL
CY 186.000 $150.000 $200.000 $200.000 $225.000 $170.000 $265.000 $220.000 $207.420 $250.000 $250.000
DRILL SHAFT (18 IN)
LF 236.000 $75.000 $90.000 $120.000 $140.000 $110.000 $116.000 $144.000 $95.060 $110.000 $150.000
DRILL SHAFT (36 IN)
LF 996.000 $150.000 $160.000 $210.000 $175.000 $220.000 $230.000 $381.000 $198.320 $200.000 $350.000
CL C CONC (ABUT)(HPC)
CY 105.400 $900.000 $900.000 $900.000 $990.000 $900.000 $1,045.000 $850.000 $1,095.550 $1,500.000 $850.000
CL C CONC (MISC)
CY 8.800 $800.000 $600.000 $925.000 $1,000.000 $900.000 $1,313.000 $1,325.000 $1,162.890 $500.000 $1,000.000
REINF CONC SLAB (HPC)
SF 4,940.000 $16.000 $20.000 $22.000 $22.000 $27.000 $35.500 $22.000 $32.000 $30.000 $15.000
PRESTR CONC GIRDER (TX28)
LF 416.000 $130.000 $165.000 $185.000 $210.000 $180.000 $230.000 $260.000 $178.100 $170.000 $140.000
PRESTR CONC GIRDER (TX34)
LF 338.000 $150.000 $180.000 $197.000 $210.000 $180.000 $240.000 $260.000 $196.440 $170.000 $140.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 506.700 $12.000 $6.000 $20.000 $22.000 $20.000 $13.000 $14.000 $6.320 $25.000 $25.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 445.000 $80.000 $110.000 $120.000 $125.000 $125.000 $110.000 $150.000 $161.180 $130.000 $85.000
RIPRAP (STONE PROTECTION)(21 IN)
CY 179.000 $200.000 $110.000 $109.000 $135.000 $125.000 $121.000 $150.000 $149.720 $130.000 $190.000
RAIL (TY T223)(HPC)
LF 496.000 $115.000 $105.000 $110.000 $115.000 $125.000 $160.000 $125.000 $137.910 $100.000 $135.000
ARMOR JOINT
LF 104.000 $75.000 $60.000 $90.000 $95.000 $50.000 $79.500 $70.000 $62.240 $120.000 $20.000
ARMOR JOINT (SEALED)
LF 52.000 $75.000 $75.000 $100.000 $105.000 $90.000 $100.000 $100.000 $83.900 $120.000 $20.000
GABIONS (GALV)
CY 102.000 $200.000 $220.000 $235.000 $202.000 $225.000 $315.000 $365.000 $278.280 $220.000 $300.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $20,000.000 $8,000.000 $8,700.000 $8,000.000 $9,000.000 $17,000.000 $10,000.000 $20,000.000 $25,000.000 $30,000.000
MOBILIZATION
LS 1.000 $88,400.000 $90,000.000 $100,000.000 $100,000.000 $102,000.000 $61,000.000 $120,000.000 $140,000.000 $150,000.000 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $6,500.000 $5,400.000 $1,800.000 $2,200.000 $1,600.000 $1,450.000 $2,500.000 $3,000.000 $2,500.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 110.000 $50.000 $10.000 $45.000 $40.000 $25.000 $20.000 $60.000 $45.270 $110.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 110.000 $8.000 $1.000 $8.990 $10.000 $20.000 $16.000 $5.500 $21.060 $25.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,950.000 $3.000 $1.000 $3.100 $3.000 $2.000 $1.300 $4.150 $3.110 $5.400 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,950.000 $1.000 $1.000 $1.100 $1.000 $1.000 $0.750 $1.500 $1.050 $1.600 $2.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 490.000 $8.000 $5.000 $4.650 $5.000 $10.000 $4.300 $6.000 $4.530 $8.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 490.000 $1.000 $1.000 $1.150 $1.000 $5.000 $1.000 $1.500 $1.050 $2.000 $12.000
MTL W-BEAM GD FEN (TIM POST)
LF 225.000 $22.500 $22.000 $23.000 $23.000 $22.000 $22.000 $22.500 $23.160 $25.000 $25.000
MTL BEAM GD FEN TRANS (TL2)
EA 12.000 $1,050.000 $1,000.000 $1,050.000 $1,500.000 $800.000 $975.000 $1,050.000 $1,595.160 $1,200.000 $1,850.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 6.000 $1,150.000 $1,000.000 $1,200.000 $1,500.000 $1,100.000 $975.000 $1,175.000 $1,026.430 $1,200.000 $1,850.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,500.000 $2,500.000 $2,650.000 $2,600.000 $2,800.000 $2,450.000 $2,600.000 $2,579.240 $2,500.000 $2,850.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $30.000 $25.000 $25.000 $25.000 $125.000 $25.000 $21.000 $26.320 $10.000 $100.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 6.000 $70.000 $65.000 $50.000 $25.000 $170.000 $65.000 $46.000 $68.430 $100.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $30.000 $25.000 $30.000 $25.000 $80.000 $25.000 $26.000 $26.320 $12.000 $100.000
Totals: $1,043,507.400 $1,090,039.800 $1,147,700.700 $1,227,614.400 $1,249,356.000 $1,282,941.260 $1,441,583.200 $1,455,760.088 $1,517,905.700 $1,576,031.500