Show Job Controls
Bid Cobra

COOKE FM 373 (0823-01-039)

Items: 83

County: COOKE
Length: 0.0000 MILES
Highway: FM 373
District: WICHITA FALLS
Control Number: 0823-01-039
DBE Goal: 0.0%
Project: F 2025(816)
Guaranty: $100,000.00
Time: 374 WORKING DAYS
Engineer's Estimate: $7,545,119.80
Date: 06/04/2025 (1 year ago)
Contract Number: 6253007
Type: WIDEN ROAD - ADD SHOULDERS
Project ID: A00194689
Contract Type: Federal
Project Description: PROVIDE ADDITIONAL PAVED SURFACE WIDTH
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
COLBY SHELTON
MADISON HAVERKAMP
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$7,545,119.80
$7,282,548.10
Over/Under Est: -3.48% -$262,571.70
Over/Under Est: -1.43% -$108,229.05
Amt Left: 2.12% $154,342.65
Over/Under Est: 2.56% $192,948.63
Amt Left: 6.25% $455,520.33
Delta: -4.05% -$301,177.68
$8,117,649.31
Over/Under Est: 7.59% $572,529.51
Amt Left: 11.47% $835,101.21
Delta: -4.91% -$379,580.88
$9,194,051.91
Over/Under Est: 21.85% $1,648,932.11
Amt Left: 26.25% $1,911,503.81
Delta: -13.26% -$1,076,402.60
Over/Under Est: 22.13% $1,669,519.66
Amt Left: 26.53% $1,932,091.36
Delta: -0.22% -$20,587.55
Subcontractor Percentage Amount
TEXOP CONSTRUCTION 2.40% $175,823.87
TRAFFIC HIGHWAY MAINTENANCE, LLC 1.51% $110,622.52
DUSTIN ALLEN, INC. 1.14% $83,516.34
BARRICADES UNLIMITED 1.06% $77,655.54
JOE'S TREE SERVICE 0.87% $63,736.15
J. H. ODEN CONTRACTING COMPANY 0.87% $63,736.15
MARCOMS CONSTRUCTION LLC 0.44% $32,234.38
SURFACE PREPARATION TECHNOLOGIES, LLC 0.40% $29,303.98
MOBILE ENTERPRISES, INC. 0.13% $9,523.79
Total: 8.82% $646,152.72

Bid Items & Bid Tabulations

83 Total 0 of 83
COOKE  |  FM 373  |  WICHITA FALLS  |  0823-01-039  |  06/04/2025  |  $7,545,119.80  |  F 2025(816)  |  WIDEN ROAD - ADD SHOULDERS  |  374 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAGOE-PUBLIC COMPANY
EUROVIA ATLANTIC COAST LLC
FOUTSCO PAVING COMPANY, LLC
A. L. HELMCAMP, INC.
OVERLAND CORPORATION
AUSTIN BRIDGE & ROAD SERVICES, LP
EXCAV (ROADWAY)
CY 8,000.000 $28.000 $40.000 $30.000 $8.000 $55.000 $57.250 $29.890
EMBANK (FNL)(DC)(TY B)
CY 7,754.000 $65.000 $30.000 $41.000 $15.000 $65.000 $45.000 $40.000
DRILL SEED (PERM_RURAL_CLAY)
SY 88,571.000 $0.120 $0.250 $0.140 $0.140 $0.140 $0.140 $0.200
DRILL SEED (TEMP_WARM)
SY 44,286.000 $0.200 $0.150 $0.140 $0.010 $0.140 $0.140 $0.160
DRILL SEED (TEMP_COOL)
SY 44,286.000 $0.200 $0.150 $0.140 $0.010 $0.140 $0.140 $0.160
VEGETATIVE WATERING
TGL 740.000 $25.000 $55.000 $55.000 $0.010 $20.000 $74.340 $51.000
CEMENT
TON 580.000 $280.000 $350.000 $250.000 $235.000 $240.000 $300.000 $220.000
CEMENT TRT (EXIST MATL)(8")
SY 40,226.000 $6.700 $3.750 $4.400 $4.500 $6.000 $12.000 $9.980
EMULS ASPH (EROSN CONT)(MS-2)
GAL 11,088.000 $3.500 $2.000 $4.000 $0.010 $5.000 $3.240 $5.190
D-GR HMA TY-B SAC-B PG64-22
TON 7,925.000 $112.000 $100.000 $113.000 $145.000 $123.000 $133.000 $145.260
D-GR HMA TY-C SAC-B PG70-28
TON 15,898.000 $125.000 $120.000 $131.000 $150.000 $125.000 $143.500 $152.490
D-GR HMA TY-C PG70-28 (LEVEL-UP)
TON 3,478.000 $125.000 $125.000 $132.500 $140.000 $141.000 $205.000 $168.700
TACK COAT
GAL 10,431.000 $4.900 $3.000 $3.000 $6.500 $5.500 $3.660 $4.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 13,574.000 $60.000 $60.000 $61.000 $71.900 $83.000 $82.750 $90.650
PLANE & TEXT ASPH CONC PAV(0" TO 2")
SY 6,468.000 $10.000 $3.250 $4.250 $4.000 $3.000 $4.990 $6.490
CUT & RESTORING PAV
SY 220.000 $78.000 $60.000 $124.000 $80.000 $70.000 $194.940 $112.530
CEM STABIL BKFL
CY 136.000 $270.000 $450.000 $325.000 $250.000 $260.000 $445.160 $325.000
FLOWABLE BACKFILL
CY 20.000 $350.000 $200.000 $450.000 $420.000 $260.000 $445.160 $450.000
TRENCH EXCAVATION PROTECTION
LF 95.000 $30.200 $30.000 $1.000 $10.000 $16.000 $20.000 $1.000
TEMPORARY SPL SHORING
SF 2,473.000 $24.000 $5.000 $40.000 $29.000 $36.000 $39.450 $45.000
CL A CONC (PLUG)
EA 2.000 $1,800.000 $2,500.000 $2,000.000 $2,000.000 $2,100.000 $2,000.000 $2,000.000
RIPRAP (MOW STRIP)(4 IN)
CY 72.000 $715.000 $900.000 $815.000 $700.000 $700.000 $650.000 $700.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 19.000 $300.000 $500.000 $700.000 $400.000 $250.000 $246.870 $400.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 168.000 $76.000 $50.000 $45.000 $55.000 $85.000 $75.000 $45.000
RETROFIT RAIL (TY T131RC)
LF 240.000 $245.000 $275.000 $265.000 $210.000 $220.000 $240.000 $200.000
CMP (GAL STL 18 IN)
LF 321.000 $84.000 $100.000 $59.000 $85.000 $110.000 $213.630 $59.000
CONC BOX CULV (8 FT X 5 FT)
LF 16.000 $900.000 $1,500.000 $1,725.000 $1,150.000 $1,700.000 $1,150.000 $1,725.000
RC PIPE (CL III)(18 IN)
LF 51.000 $90.000 $135.000 $90.000 $90.000 $74.000 $94.870 $90.000
RC PIPE (CL III)(24 IN)
LF 50.000 $100.000 $150.000 $100.000 $100.000 $108.000 $131.290 $100.000
RC PIPE (CL III)(42 IN)
LF 6.000 $240.000 $275.000 $500.000 $500.000 $190.000 $241.000 $500.000
RC PIPE (CL III)(48 IN)
LF 130.000 $360.000 $300.000 $425.000 $283.000 $365.000 $293.560 $425.000
HEADWALL (CH - FW - 45) (DIA= 48 IN)
EA 1.000 $7,100.000 $25,000.000 $19,000.000 $20,000.000 $15,000.000 $7,150.000 $19,000.000
HEADWALL (CH - PW - 0) (DIA= 42 IN)
EA 2.000 $13,750.000 $21,000.000 $20,000.000 $15,000.000 $15,500.000 $12,200.000 $20,000.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 1.000 $9,000.000 $25,000.000 $25,000.000 $17,000.000 $18,500.000 $16,090.000 $25,000.000
WINGWALL (PW - 2) (HW=6 FT)
EA 2.000 $44,000.000 $30,000.000 $19,800.000 $25,000.000 $26,000.000 $21,600.000 $19,800.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 22.000 $1,400.000 $1,700.000 $1,100.000 $1,800.000 $1,400.000 $1,722.000 $1,100.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $1,600.000 $1,600.000 $1,100.000 $1,800.000 $1,400.000 $1,500.000 $1,100.000
SET (TY II) (24 IN) (CMP) (4: 1) (C)
EA 1.000 $3,000.000 $2,000.000 $1,150.000 $2,000.000 $1,400.000 $2,250.000 $1,150.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $2,500.000 $2,200.000 $1,340.000 $2,500.000 $1,700.000 $2,250.000 $1,340.000
REMOV STR (SET)
EA 4.000 $400.000 $750.000 $300.000 $750.000 $1,100.000 $852.680 $300.000
REMOV STR (WINGWALL)
EA 2.000 $1,000.000 $3,400.000 $1,500.000 $1,500.000 $16,000.000 $2,187.370 $1,500.000
REMOV STR (HEADWALL)
EA 1.000 $1,100.000 $2,000.000 $1,500.000 $1,500.000 $1,100.000 $2,582.060 $1,500.000
REMOV STR (PIPE)
LF 718.000 $15.000 $24.000 $12.000 $22.000 $21.000 $48.910 $12.000
MOBILIZATION
LS 1.000 $665,920.010 $815,000.000 $480,000.000 $600,000.000 $515,000.000 $945,510.000 $1,013,610.340
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 22.000 $10,000.000 $12,500.000 $16,000.000 $20,000.000 $10,000.000 $4,000.000 $17,391.220
TMA (STATIONARY)
DAY 290.000 $260.000 $100.000 $375.000 $150.000 $260.000 $205.000 $4.000
TMA (MOBILE OPERATION)
DAY 40.000 $260.000 $100.000 $975.000 $50.000 $130.000 $275.000 $25.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 80.000 $60.000 $60.000 $29.000 $30.000 $31.000 $29.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 80.000 $15.000 $20.000 $22.000 $10.000 $16.000 $93.210 $18.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $2.000 $5.000 $3.000 $3.000 $3.200 $3.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,000.000 $0.500 $1.000 $1.000 $1.000 $1.000 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,910.000 $4.000 $6.000 $2.950 $3.000 $3.200 $2.950 $5.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,910.000 $1.000 $1.000 $1.000 $1.000 $1.000 $1.000 $1.500
DRIVEWAYS (CONC)
SY 217.000 $98.000 $130.000 $146.000 $95.000 $145.000 $120.000 $152.320
DRIVEWAYS (ACP)
SY 2,063.000 $45.000 $45.000 $43.000 $50.000 $65.000 $66.220 $59.230
DRIVEWAYS (BASE)
SY 4,005.000 $30.000 $18.000 $25.000 $40.000 $40.000 $28.160 $24.950
TURNOUTS (ACP)
SY 66.000 $90.000 $45.000 $105.000 $100.000 $65.000 $544.460 $149.920
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 91,640.000 $0.140 $0.150 $0.250 $0.150 $0.230 $0.170 $0.060
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 45,820.000 $0.240 $0.200 $0.290 $0.150 $0.230 $0.170 $0.060
MTL W-BEAM GD FEN (TIM POST)
LF 275.000 $30.000 $35.000 $34.200 $28.000 $24.000 $28.220 $23.250
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,100.000 $3,500.000 $2,210.000 $1,800.000 $1,800.000 $1,981.000 $1,750.000
REMOVE METAL BEAM GUARD FENCE
LF 275.000 $4.000 $3.000 $8.000 $8.000 $3.200 $8.000 $2.500
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $3,500.000 $3,340.000 $3,000.000 $3,400.000 $3,010.000 $3,025.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $250.000 $325.000 $600.000 $300.000 $320.000 $300.000 $200.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 2.000 $330.000 $225.000 $200.000 $200.000 $220.000 $325.000 $200.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 1.000 $600.000 $650.000 $550.000 $550.000 $580.000 $798.000 $550.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 10.000 $765.000 $625.000 $515.000 $500.000 $540.000 $705.000 $515.000
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
EA 1.000 $1,300.000 $800.000 $655.000 $650.000 $690.000 $828.000 $655.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 51.000 $520.000 $450.000 $380.000 $350.000 $400.000 $432.000 $380.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 2.000 $605.000 $225.000 $200.000 $200.000 $220.000 $550.000 $200.000
REMOVE SM RD SN SUP&AM
EA 53.000 $110.000 $120.000 $100.000 $100.000 $110.000 $105.000 $100.000
RELOCATE SM RD SN SUP & AM TY TEMP
EA 2.000 $150.000 $230.000 $1,000.000 $200.000 $250.000 $370.000 $400.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 11.000 $120.000 $60.000 $50.000 $50.000 $55.000 $100.000 $50.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 3.000 $20.000 $18.000 $15.000 $15.000 $16.000 $65.000 $15.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 5,562.000 $1.500 $2.250 $1.750 $0.010 $0.750 $2.860 $2.140
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 91,861.000 $0.570 $0.750 $0.630 $0.550 $0.590 $0.570 $0.570
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 5,573.000 $0.650 $0.850 $0.700 $0.590 $0.610 $0.590 $0.590
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 66,953.000 $0.700 $0.750 $0.630 $0.550 $0.590 $0.570 $0.570
REFL PAV MRKR TY II-A-A
EA 1,137.000 $4.650 $5.000 $4.450 $4.000 $4.100 $3.880 $3.880
SPOT TREE TRIMMING / BRUSH REMOVAL
LF 8,344.000 $3.000 $6.000 $3.840 $0.500 $5.000 $6.500 $5.720
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 0.070 $40,000.000 $200,000.000 $172,000.000 $15,000.000 $116,000.000 $5,000.000 $2,500.000
TREE REMOVAL (12" - 18" DIA)
EA 7.000 $1,000.000 $1,500.000 $860.000 $750.000 $1,200.000 $300.000 $900.000
TREE REMOVAL (18" - 24" DIA)
EA 7.000 $3,500.000 $2,300.000 $1,075.000 $1,500.000 $1,800.000 $600.000 $1,868.000
Totals: $7,545,119.800 $7,282,548.100 $7,436,890.750 $7,738,068.430 $8,117,649.310 $9,194,051.910 $9,214,639.460
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $2,000.00