COOKE FM 51 (0312-01-083)

Items: 31

County: COOKE
Length: 0.0000 MILES
Highway: FM 51
District: WICHITA FALLS
Control Number: 0312-01-083
DBE Goal: 0.0%
Project: F 2025(626)
Guaranty: $100,000.00
Time: 95 WORKING DAYS
Engineer's Estimate: $7,537,592.50
Date: 04/04/2025 (1 year ago)
Contract Number: 4253210
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00194685
Contract Type: Federal
Project Description: PAVEMENT REPAIR AND OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
COLBY SHELTON
MADISON HAVERKAMP
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$7,537,592.50
$6,010,839.85
Over/Under Est: -20.26% -$1,526,752.65
$6,376,539.56
Over/Under Est: -15.4% -$1,161,052.94
Amt Left: 6.08% $365,699.71
$6,497,015.68
Over/Under Est: -13.81% -$1,040,576.82
Amt Left: 8.09% $486,175.83
Delta: -1.89% -$120,476.12
$7,096,877.92
Over/Under Est: -5.85% -$440,714.58
Amt Left: 18.07% $1,086,038.07
Delta: -9.23% -$599,862.24
$7,537,955.15
Over/Under Est: 0% $362.65
Amt Left: 25.41% $1,527,115.30
Delta: -6.22% -$441,077.23
Over/Under Est: 4.15% $313,077.69
Amt Left: 30.61% $1,839,830.34
Delta: -4.15% -$312,715.04
Subcontractor Percentage Amount
TRAFFIC HIGHWAY MAINTENANCE, LLC 2.93% $183,279.50
WEST TEXAS RUMBLE STRIP LLC 0.49% $30,650.84
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.26% $16,263.71
TEXAS TRAFFIC AND BARRICADE, LLC 0.25% $15,638.18
Total: 3.93% $245,832.23

Bid Items & Bid Tabulations

31 Total 0 of 31
COOKE  |  FM 51  |  WICHITA FALLS  |  0312-01-083  |  04/04/2025  |  $7,537,592.50  |  F 2025(626)  |  SURF/ROADWAY RESTOR  |  95 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EUROVIA ATLANTIC COAST LLC
JAGOE-PUBLIC COMPANY
OVERLAND CORPORATION
ZACK BURKETT CO.
A. L. HELMCAMP, INC.
AUSTIN BRIDGE & ROAD SERVICES, LP
BACKFILL (TY A OR B)
STA 880.000 $234.000 $143.000 $75.000 $225.000 $267.000 $190.000 $157.720
BROADCAST SEED (PERM_RURAL_SAND)
SY 78,205.000 $0.450 $0.100 $0.100 $0.100 $0.120 $0.100 $0.260
BROADCAST SEED (TEMP_WARM)
SY 39,102.000 $0.500 $0.080 $0.050 $0.080 $0.100 $0.060 $0.260
BROADCAST SEED (TEMP_COOL)
SY 39,102.000 $0.500 $0.130 $0.050 $0.130 $0.150 $0.060 $0.260
VEGETATIVE WATERING
TGL 657.000 $75.000 $52.000 $45.000 $40.000 $25.000 $20.000 $56.000
EMULS ASPH (EROSN CONT)(SS-1)
GAL 19,551.000 $4.250 $3.250 $1.500 $3.250 $3.100 $4.000 $3.810
SP MIXES SP-C SAC-B PG70-28
TON 47,662.000 $115.000 $98.000 $99.250 $97.750 $115.000 $123.000 $122.600
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 6,000.000 $55.700 $44.500 $48.000 $60.000 $50.000 $85.000 $55.680
PLANE ASPH CONC PAV(0" TO 2")
SY 28,450.000 $7.000 $1.900 $1.750 $1.300 $2.960 $3.560 $1.740
MOBILIZATION
LS 1.000 $682,780.940 $349,000.000 $701,000.000 $605,000.000 $464,000.000 $374,000.000 $863,573.720
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $4,500.000 $10,000.000 $18,000.000 $30,000.000 $3,000.000 $10,400.000 $29,120.770
TMA (STATIONARY)
DAY 60.000 $330.000 $345.000 $150.000 $250.000 $275.000 $300.000 $324.750
TMA (MOBILE OPERATION)
DAY 61.000 $200.000 $675.000 $150.000 $900.000 $0.010 $80.000 $10.830
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 176,892.000 $0.220 $0.210 $0.130 $0.050 $0.240 $0.180 $0.050
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 87,980.000 $0.220 $0.230 $0.130 $0.060 $0.240 $0.190 $0.060
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 6,052.000 $2.000 $1.050 $2.000 $1.400 $1.200 $1.000 $0.500
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 670.000 $1.300 $1.000 $1.050 $1.100 $1.190 $1.040 $1.100
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 180,587.000 $0.720 $0.550 $0.600 $0.540 $0.750 $0.570 $0.540
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 14,539.000 $0.720 $0.640 $0.700 $0.570 $0.750 $0.660 $0.570
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 102,200.000 $0.720 $0.550 $0.600 $0.540 $0.750 $0.570 $0.540
PREFAB PM TY C (W)(24")(SLD)
LF 24.000 $13.000 $14.000 $15.000 $15.000 $18.450 $14.490 $15.000
PREFAB PM TY C (W)(ARROW)
EA 2.000 $250.000 $225.000 $240.000 $300.000 $297.500 $232.880 $300.000
PREFAB PM TY C (W)(WORD)
EA 2.000 $315.000 $345.000 $360.000 $350.000 $416.500 $357.080 $350.000
PREFAB PM TY C (Y)(24")(SLD)
LF 114.000 $13.000 $15.000 $5.000 $15.000 $19.040 $15.530 $15.000
REFL PAV MRKR TY II-A-A
EA 2,662.000 $4.000 $4.500 $5.000 $3.800 $5.360 $4.660 $3.800
ELIM EXT PM & MRKS (6")
LF 3,953.000 $1.340 $2.000 $2.000 $1.000 $0.500 $1.000 $2.690
ELIM EXT PM & MRKS (8")
LF 661.000 $1.210 $3.050 $5.000 $1.000 $0.700 $1.500 $2.690
ELIM EXT PM & MRKS (24")
LF 138.000 $4.410 $10.000 $20.000 $15.000 $2.500 $6.000 $4.040
ELIM EXT PM & MRKS (ARROW)
EA 2.000 $83.500 $300.000 $500.000 $100.000 $250.000 $80.000 $108.950
ELIM EXT PM & MRKS (WORD)
EA 2.000 $93.170 $265.000 $500.000 $100.000 $250.000 $80.000 $84.740
BONDING COURSE
GAL 17,205.000 $3.650 $3.000 $5.000 $4.500 $4.950 $5.000 $4.000
Totals: $7,537,592.500 $6,010,839.850 $6,376,539.560 $6,497,015.680 $7,096,877.920 $7,537,955.150 $7,850,670.190
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
Total: $4,000.00