COOKE FM 1306 (0195-05-013)
Items: 90
County: COOKE
Length: 0.0000 MILES
Highway: FM 1306
District: WICHITA FALLS
Control Number: 0195-05-013
DBE Goal: 0.0%
Project: STP 2025(223)TAPS
Guaranty: $62,000.00
Time: 192 WORKING DAYS
Engineer's Estimate: $2,835,173.67
Date: 03/04/2026 (3 months ago)
Contract Number: 3263023
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00207039
Contract Type: Federal
Project Description: THE PROJECT WILL INSTALL A 6-FOOT-WIDE SIDEWALK TO CONNECT THE CITY CENTER TO GAINESVILLE HIGH SCHOOL, NORTH CENTRAL TEXAS COLLEGE, MOFFET PARK AND LEONARD PARK.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
COOKE FM 1306 (0195-05-013)
Project Name: N/A
Project: STP 2025(223)TAPS
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: FM 51
Limits To: GAINESVILLE HIGH SCHOOL
Project Description: THE PROJECT WILL INSTALL A 6-FOOT-WIDE SIDEWALK TO CONNECT THE CITY CENTER TO GAINESVILLE HIGH SCHOOL, NORTH CENTRAL TEXAS COLLEGE, MOFFET PARK AND LEONARD PARK.
COOKE FM 51 (0312-01-084)
Project Name: TASA GAINESVILLE FM 51 SIDEWALK IMPROV
Project: STP 2025(223)TAPS
Length: 0.0000 MILES
Project Type: PEDESTRIAN, SIDEWALKS & CURB RAMPS
Limits From: IH 35 SOUTHBOUND FRONTAGE ROAD
Limits To: FM 1306
Project Description: THE PROJECT WILL INSTALL A 6-FOOT-WIDE SIDEWALK TO CONNECT THE CITY CENTER TO GAINESVILLE HIGH SCHOOL, NORTH CENTRAL TEXAS COLLEGE, MOFFET PARK AND LEONARD PARK.
Bidders (12)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,835,173.67 | |||
| $2,192,971.75 |
-22.65%
-$642,201.92
|
|||
| $2,231,704.00 |
-21.29%
-$603,469.67
|
1.77%
$38,732.25
|
||
| $2,296,745.50 |
-18.99%
-$538,428.17
|
4.73%
$103,773.75
|
-2.91%
-$65,041.50
|
|
| $2,365,287.80 |
-16.57%
-$469,885.87
|
7.86%
$172,316.05
|
-2.98%
-$68,542.30
|
|
| $2,470,594.75 |
-12.86%
-$364,578.92
|
12.66%
$277,623.00
|
-4.45%
-$105,306.95
|
|
| $2,518,586.87 |
-11.17%
-$316,586.80
|
14.85%
$325,615.12
|
-1.94%
-$47,992.12
|
|
| $2,677,525.15 |
-5.56%
-$157,648.52
|
22.1%
$484,553.40
|
-6.31%
-$158,938.28
|
|
| $2,791,150.74 |
-1.55%
-$44,022.93
|
27.28%
$598,178.99
|
-4.24%
-$113,625.59
|
|
| $2,828,006.45 |
-0.25%
-$7,167.22
|
28.96%
$635,034.70
|
-1.32%
-$36,855.71
|
|
| $3,268,724.85 |
15.29%
$433,551.18
|
49.05%
$1,075,753.10
|
-15.58%
-$440,718.40
|
|
| $3,496,935.05 |
23.34%
$661,761.38
|
59.46%
$1,303,963.30
|
-6.98%
-$228,210.20
|
|
| $3,699,479.80 |
30.49%
$864,306.13
|
68.7%
$1,506,508.05
|
-5.79%
-$202,544.75
|
E
Engineer's Estimate
$2,835,173.67
1
$2,192,971.75
Over/Under Est:
-22.65%
-$642,201.92
$2,231,704.00
Over/Under Est:
-21.29%
-$603,469.67
Amt Left:
1.77%
$38,732.25
$2,296,745.50
Over/Under Est:
-18.99%
-$538,428.17
Amt Left:
4.73%
$103,773.75
Delta:
-2.91%
-$65,041.50
$2,365,287.80
Over/Under Est:
-16.57%
-$469,885.87
Amt Left:
7.86%
$172,316.05
Delta:
-2.98%
-$68,542.30
$2,470,594.75
Over/Under Est:
-12.86%
-$364,578.92
Amt Left:
12.66%
$277,623.00
Delta:
-4.45%
-$105,306.95
$2,518,586.87
Over/Under Est:
-11.17%
-$316,586.80
Amt Left:
14.85%
$325,615.12
Delta:
-1.94%
-$47,992.12
$2,677,525.15
Over/Under Est:
-5.56%
-$157,648.52
Amt Left:
22.1%
$484,553.40
Delta:
-6.31%
-$158,938.28
$2,791,150.74
Over/Under Est:
-1.55%
-$44,022.93
Amt Left:
27.28%
$598,178.99
Delta:
-4.24%
-$113,625.59
$2,828,006.45
Over/Under Est:
-0.25%
-$7,167.22
Amt Left:
28.96%
$635,034.70
Delta:
-1.32%
-$36,855.71
$3,268,724.85
Over/Under Est:
15.29%
$433,551.18
Amt Left:
49.05%
$1,075,753.10
Delta:
-15.58%
-$440,718.40
$3,496,935.05
Over/Under Est:
23.34%
$661,761.38
Amt Left:
59.46%
$1,303,963.30
Delta:
-6.98%
-$228,210.20
$3,699,479.80
Over/Under Est:
30.49%
$864,306.13
Amt Left:
68.7%
$1,506,508.05
Delta:
-5.79%
-$202,544.75
Bid Items & Bid Tabulations
90
Total
0 of 90
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $4,200.00 |
| Total: | $5,200.00 |