COOKE US 82 (0045-01-061)

Items: 41

County: COOKE
Length: N/A
Highway: US 82
District: WICHITA FALLS
Control Number: 0045-01-061
DBE Goal: N/A
Project: NH 2018(556)
Guaranty: N/A
Time: 50 WORKING DAYS
Engineer's Estimate: $2,159,327.02
Date: 02/01/2018 (8 years ago)
Contract Number: N/A
Type: PAVEMENT REPAIR, SEAL AND PFC OVERLAY (EB ONLY)
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$2,159,327.02
$2,124,211.95
Over/Under Est: -1.63% -$35,115.07
Over/Under Est: -1.24% -$26,795.07
Amt Left: 0.39% $8,320.00
$2,147,125.80
Over/Under Est: -0.57% -$12,201.22
Amt Left: 1.08% $22,913.85
Delta: -0.68% -$14,593.85
Over/Under Est: 7.57% $163,524.13
Amt Left: 9.35% $198,639.20
Delta: -8.18% -$175,725.35
Over/Under Est: 9.22% $199,108.08
Amt Left: 11.03% $234,223.15
Delta: -1.53% -$35,583.95
$2,382,174.06
Over/Under Est: 10.32% $222,847.04
Amt Left: 12.14% $257,962.11
Delta: -1.01% -$23,738.96
$2,588,982.45
Over/Under Est: 19.9% $429,655.43
Amt Left: 21.88% $464,770.50
Delta: -8.68% -$206,808.39

Bid Items & Bid Tabulations

41 Total 0 of 41
COOKE  |  US 82  |  WICHITA FALLS  |  0045-01-061  |  02/01/2018  |  $2,159,327.02  |  NH 2018(556)  |  PAVMT REPAIR, SEAL AND PFC OVERLAY (...  |  50 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAGOE-PUBLIC COMPANY
THE LANE CONSTRUCTION CORPORATION
OVERLAND CORPORATION
AUSTIN BRIDGE & ROAD SERVICES, LP
FOUTSCO PAVING COMPANY, LLC
RK HALL, LLC
A. L. HELMCAMP, INC.
ASPH (AC-20-5TR)
GAL 87,435.000 $2.400 $3.110 $3.210 $3.150 $2.960 $4.000 $3.000 $2.700
AGGR(TY-PE GR-4 SAC-B)
CY 2,143.000 $54.200 $136.000 $99.500 $98.000 $128.650 $160.000 $140.000 $94.000
PFC (ASPHALT) PG76-22
TON 601.000 $880.000 $565.000 $600.000 $630.000 $105.000 $110.000 $125.000 $165.000
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
TON 9,400.000 $75.000 $70.000 $82.000 $64.350 $105.000 $110.000 $125.000 $165.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 511.000 $40.000 $55.000 $45.000 $49.500 $73.000 $34.000 $45.700 $64.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 6,854.000 $22.000 $25.000 $27.500 $37.050 $36.000 $23.500 $29.650 $27.000
PLANE ASPH CONC PAV (0" TO 3 1/2")
SY 5,384.000 $4.000 $4.450 $3.500 $5.350 $5.500 $2.500 $4.390 $5.000
RIPRAP (MOW STRIP)(4 IN)
CY 51.300 $540.000 $345.000 $625.000 $712.500 $410.000 $300.000 $588.500 $660.000
MOBILIZATION
LS 1.000 $180,121.000 $165,000.000 $45,000.000 $185,235.000 $225,000.000 $200,000.000 $108,000.000 $66,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $8,000.000 $8,500.000 $19,000.000 $1,565.000 $6,500.000 $10,000.000 $3,100.000 $2,500.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 77,940.000 $0.200 $0.130 $0.120 $0.180 $0.130 $0.090 $0.150 $0.140
MTL W-BEAM GD FEN (TIM POST)
LF 750.000 $20.200 $18.500 $17.650 $23.000 $17.500 $17.500 $18.190 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $2,000.000 $1,850.000 $1,430.000 $2,030.000 $1,750.000 $1,750.000 $1,471.250 $2,200.000
REMOVE METAL BEAM GUARD FENCE
LF 900.000 $4.000 $3.150 $3.250 $3.200 $3.000 $3.000 $3.210 $3.500
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,400.000 $2,325.000 $2,365.000 $2,675.000 $2,200.000 $2,200.000 $2,434.250 $2,800.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $350.000 $263.000 $315.000 $320.000 $250.000 $250.000 $321.000 $340.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $850.000 $615.000 $535.000 $975.000 $560.000 $100.000 $975.050 $960.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $650.000 $440.000 $250.000 $795.000 $400.000 $500.000 $794.030 $780.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 9.000 $23.000 $44.000 $24.000 $53.500 $40.000 $30.000 $25.680 $55.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 9.000 $23.000 $44.000 $25.000 $53.500 $40.000 $30.000 $26.750 $55.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 9.000 $35.000 $28.000 $34.000 $53.500 $25.000 $30.000 $36.380 $45.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 12.000 $35.000 $28.000 $35.000 $53.500 $25.000 $30.000 $37.450 $45.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 11,464.000 $1.000 $0.500 $2.000 $0.450 $1.250 $1.000 $1.250 $0.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 94.000 $1.000 $0.500 $1.500 $0.450 $1.600 $1.000 $2.000 $0.500
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 51.000 $6.500 $1.050 $1.000 $1.050 $3.000 $1.000 $1.070 $1.100
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,835.000 $7.700 $0.950 $0.900 $0.950 $0.790 $0.900 $0.960 $0.950
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 14,000.000 $0.610 $0.420 $0.400 $0.450 $0.390 $0.400 $0.430 $0.420
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 58,021.000 $0.280 $0.360 $0.350 $0.350 $0.340 $0.350 $0.370 $0.370
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 59,279.000 $0.260 $0.360 $0.350 $0.350 $0.350 $0.350 $0.370 $0.370
PREFAB PAV MRK TY B (W)(24")(SLD)
LF 312.000 $18.000 $14.300 $14.000 $15.000 $14.000 $14.000 $14.980 $15.000
PREFAB PAV MRK TY B (W)(ARROW)
EA 12.000 $350.000 $190.000 $185.000 $198.000 $340.000 $185.000 $197.950 $195.000
PREFAB PAV MRK TY B (W)(WORD)
EA 10.000 $505.000 $240.000 $235.000 $255.000 $410.000 $235.000 $251.450 $245.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 7.000 $54.000 $42.000 $40.000 $45.000 $81.000 $40.000 $43.340 $45.000
REFL PAV MRKR TY I-C
EA 52.000 $5.000 $4.000 $3.800 $4.100 $7.000 $4.000 $4.070 $4.000
REFL PAV MRKR TY II-A-A
EA 24.000 $4.000 $4.000 $3.800 $4.100 $8.000 $4.000 $4.070 $4.000
REFL PAV MRKR TY II-C-R
EA 1,125.000 $2.900 $4.000 $3.800 $4.100 $3.500 $4.000 $4.070 $4.000
ELIM EXT PAV MRK & MRKS (24")
LF 270.000 $5.350 $1.560 $1.500 $1.600 $0.250 $1.500 $1.610 $1.600
ELIM EXT PAV MRK & MRKS (ARROW)
EA 12.000 $54.500 $32.000 $30.000 $35.000 $8.630 $30.000 $32.100 $32.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 10.000 $50.000 $52.000 $50.000 $55.000 $10.000 $50.000 $53.500 $52.000
TMA (STATIONARY)
EA 1.000 $10,000.000 $1,000.000 $350.000 $535.000 $22,000.000 $500.000 $25,000.000 $3,000.000
TMA (MOBILE OPERATION)
HR 40.000 $100.000 $64.000 $75.000 $85.000 $75.000 $50.000 $190.000 $100.000
Totals: $2,159,327.020 $2,124,211.950 $2,132,531.950 $2,147,125.800 $2,322,851.150 $2,358,435.100 $2,382,174.060 $2,588,982.450