Show Job Controls
Bid Cobra

CONCHO FM 765 (0870-04-040)

Items: 51

County: CONCHO
Length: N/A
Highway: FM 765
District: SAN ANGELO
Control Number: 0870-04-040
DBE Goal: N/A
Project: STP 1702(552)
Guaranty: N/A
Time: 165 WORKING DAYS
Engineer's Estimate: $3,072,000.00
Date: 07/11/2017 (8 years ago)
Contract Number: N/A
Type: RESTORATION OF EXISTING ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$3,072,000.00
$2,792,437.52
Over/Under Est: -9.1% -$279,562.48
$2,818,926.83
Over/Under Est: -8.24% -$253,073.17
Amt Left: 0.95% $26,489.31
$3,027,294.99
Over/Under Est: -1.46% -$44,705.01
Amt Left: 8.41% $234,857.47
Delta: -7.39% -$208,368.16
Over/Under Est: 19.51% $599,498.14
Amt Left: 31.48% $879,060.62
Delta: -21.28% -$644,203.15
Over/Under Est: 20.78% $638,261.99
Amt Left: 32.87% $917,824.47
Delta: -1.06% -$38,763.85
$3,798,279.50
Over/Under Est: 23.64% $726,279.50
Amt Left: 36.02% $1,005,841.98
Delta: -2.37% -$88,017.51

Bid Items & Bid Tabulations

51 Total 0 of 51
CONCHO  |  FM 765  |  SAN ANGELO  |  0870-04-040  |  07/11/2017  |  $3,072,000.00  |  STP 1702(552)  |  RESTOR OF EXIST ROAD  |  165 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. H. STRAIN & SONS, INC.
REECE ALBERT, INC.
ALLEN KELLER COMPANY
PRICE CONSTRUCTION, LTD.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
RAY FARIS, INC.
EXCAVATION (ROADWAY)
CY 623.000 $20.000 $30.000 $32.550 $22.000 $22.730 $25.330 $15.820
SUBGRADE WIDENING (ORD COMP)
STA 368.220 $300.000 $300.000 $75.440 $290.000 $100.470 $474.470 $482.130
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 20.000 $100.000 $50.000 $32.680 $29.000 $136.100 $24.530 $71.980
BLADING
HR 61.000 $100.000 $100.000 $86.220 $125.000 $183.230 $174.560 $79.100
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 49,113.000 $0.150 $0.130 $0.140 $0.120 $0.120 $0.170 $0.120
BROADCAST SEED (TEMP) (WARM)
SY 24,557.000 $0.150 $0.130 $0.140 $0.120 $0.120 $0.150 $0.120
BROADCAST SEED (TEMP) (COOL)
SY 24,557.000 $0.150 $0.130 $0.140 $0.120 $0.120 $0.150 $0.120
PROOF ROLLING
HR 44.000 $75.000 $75.000 $64.730 $110.000 $108.180 $70.870 $63.280
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 108,388.000 $7.250 $5.750 $6.760 $7.800 $8.800 $8.380 $11.810
LIME (QUICKLIME (DRY))
TON 2,543.000 $165.500 $175.000 $170.190 $175.000 $160.850 $170.100 $155.170
LIME TRT (EXST MATL) (12")
SY 131,498.000 $2.850 $2.850 $2.600 $2.300 $3.510 $2.330 $2.890
PRIME COAT(MC-30 OR AE-P)
GAL 22,910.000 $3.500 $3.600 $2.730 $4.200 $3.760 $4.540 $3.860
EMULS ASPH (EROSN CONT)(MS-2)
GAL 4,100.000 $4.000 $4.000 $2.960 $3.630 $2.700 $4.140 $3.130
ASPH (MULTI OPTION)
GAL 83,570.000 $3.500 $3.150 $2.410 $3.170 $2.840 $3.660 $2.970
AGGR(TY-PB GR-3 SAC-B)
CY 1,150.000 $95.000 $85.000 $92.620 $80.000 $142.720 $136.390 $86.390
AGGR(TY-PB GR-4 SAC-B)
CY 1,061.000 $95.000 $85.000 $94.790 $75.000 $93.480 $141.140 $81.690
D-GR HMA TY-B PG70-22
TON 1,027.000 $80.000 $115.000 $86.600 $120.000 $109.070 $124.100 $98.260
SUPERPAVE MIXTURES SP-C SAC-B PG70-22
TON 206.000 $85.000 $150.000 $143.770 $165.000 $171.230 $178.990 $122.600
FLEXIBLE PAVEMENT STRUCTURE REPAIR(24")
SY 133.000 $75.000 $75.000 $54.560 $60.000 $96.770 $309.400 $63.900
PLANE ASPH CONC PAV (1.5")
SY 653.000 $4.000 $20.000 $10.610 $8.400 $14.880 $14.130 $13.560
FLOWABLE BACKFILL
CY 10.000 $200.000 $200.000 $322.310 $175.000 $295.480 $244.290 $265.000
CONC STR REPAIR (STANDARD)
SF 8.000 $500.000 $1,100.000 $47.760 $250.000 $322.750 $1,157.160 $300.000
CLEANING AND SEALING EXISTING JOINTS
LF 122.800 $25.000 $80.000 $66.090 $90.000 $86.070 $159.900 $80.000
RETROFIT RAIL (TY T131RC)
LF 466.660 $175.000 $175.000 $195.380 $157.000 $177.510 $258.420 $165.000
MOBILIZATION
LS 1.000 $270,703.410 $160,000.000 $228,693.960 $161,000.000 $413,041.000 $493,001.620 $417,811.050
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $10,000.000 $3,000.000 $9,291.160 $14,900.000 $33,278.700 $2,978.110 $16,260.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 78.000 $25.000 $20.000 $16.520 $30.000 $17.810 $23.460 $28.000
CONSTRUCTION EXITS (REMOVE)
SY 78.000 $10.000 $5.000 $3.750 $10.000 $14.190 $10.260 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 810.000 $5.000 $4.000 $2.710 $4.500 $5.200 $2.890 $5.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 810.000 $2.000 $2.000 $1.390 $1.500 $1.390 $0.970 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 720.000 $5.000 $5.000 $4.700 $9.000 $5.490 $11.710 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 720.000 $2.000 $2.000 $1.300 $2.000 $3.210 $2.910 $2.000
MTL W-BEAM GD FEN (STEEL POST)
LF 1,150.000 $25.000 $28.000 $31.750 $25.000 $20.980 $29.250 $26.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,800.000 $2,450.000 $2,564.430 $1,900.000 $1,527.660 $2,448.510 $2,200.000
REMOVE METAL BEAM GUARD FENCE
LF 350.000 $3.000 $3.500 $3.660 $5.600 $1.610 $3.960 $3.300
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $200.000 $325.000 $366.350 $255.000 $129.100 $391.510 $330.000
GDRAIL END TRT(INSTALL)(HBA POST)
EA 12.000 $2,500.000 $3,000.000 $3,175.010 $2,810.000 $2,130.110 $3,063.020 $2,750.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 26.000 $750.000 $500.000 $506.780 $580.000 $268.950 $865.660 $775.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 10.000 $20.000 $22.000 $24.420 $20.000 $19.370 $35.610 $22.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 72.000 $20.000 $22.000 $24.420 $20.000 $16.140 $36.870 $22.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 12.000 $120.000 $100.000 $152.640 $76.000 $59.170 $160.750 $137.500
INSTL DEL ASSN (OM-2Z)(FLX)(WAP)
EA 10.000 $100.000 $100.000 $610.580 $76.000 $69.930 $616.410 $550.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,740.000 $2.000 $1.750 $2.190 $1.500 $2.140 $1.150 $1.130
REFL PAV MRK TY II (W) 4" (SLD)
LF 74,842.000 $0.070 $0.120 $0.130 $0.110 $0.120 $0.170 $0.110
REFL PAV MRK TY II (Y) 4" (BRK)
LF 17,380.000 $0.190 $0.230 $0.260 $0.210 $0.230 $0.300 $0.210
REFL PAV MRK TY II (Y) 4" (SLD)
LF 49,062.000 $0.160 $0.230 $0.260 $0.210 $0.230 $0.180 $0.210
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 74,842.000 $0.320 $0.330 $0.350 $0.290 $0.310 $0.450 $0.290
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 8,690.000 $0.340 $0.350 $0.390 $0.320 $0.340 $0.530 $0.320
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 24,531.000 $0.340 $0.350 $0.380 $0.310 $0.330 $0.460 $0.310
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 124.000 $12.000 $15.000 $15.880 $13.100 $13.990 $20.170 $13.000
REFL PAV MRKR TY II-A-A
EA 773.000 $4.200 $5.600 $5.860 $5.000 $5.160 $4.550 $4.800
Totals: $3,072,000.000 $2,792,437.520 $2,818,926.840 $3,027,294.990 $3,671,498.156 $3,710,262.001 $3,798,279.509