Show Job Controls
Bid Cobra

COMANCHE SH 16 (0288-01-040)

Items: 44

County: COMANCHE
Length: N/A
Highway: SH 16
District: BROWNWOOD
Control Number: 0288-01-040
DBE Goal: N/A
Project: BR 2023(159)
Guaranty: N/A
Time: 234 WORKING DAYS
Engineer's Estimate: $2,493,956.50
Date: 11/02/2022 (3 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$2,493,956.50
$2,724,265.00
Over/Under Est: 9.23% $230,308.50
Over/Under Est: 16.05% $400,245.43
Amt Left: 6.24% $169,936.93
Over/Under Est: 27.46% $684,858.50
Amt Left: 16.69% $454,550.00
Delta: -9.83% -$284,613.07
Over/Under Est: 36.11% $900,573.50
Amt Left: 24.6% $670,265.00
Delta: -6.79% -$215,715.00
Over/Under Est: 40.03% $998,423.50
Amt Left: 28.2% $768,115.00
Delta: -2.88% -$97,850.00
Over/Under Est: 41.09% $1,024,843.50
Amt Left: 29.17% $794,535.00
Delta: -0.76% -$26,420.00
$4,199,462.50
Over/Under Est: 68.39% $1,705,506.00
Amt Left: 54.15% $1,475,197.50
Delta: -19.34% -$680,662.50
Subcontractor Percentage Amount
S&S BRIDGE PAINTING 15.71% $561,652.33
CHEROKEE SERVICES 4.64% $165,885.86
Total: 20.35% $727,538.19

Bid Items & Bid Tabulations

44 Total 0 of 44
COMANCHE  |  SH 16  |  BROWNWOOD  |  0288-01-040  |  11/02/2022  |  $2,493,956.50  |  BR 2023(159)  |  BRIDGE MAINT  |  234 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRUCTURAL INTEGRITY GROUP LLC
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
TALBRAN ENTERPRISES LLC
RAGLE CONSTRUCTION, INC.
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
FNH CONSTRUCTION, LLC
EXCAVATION (CHANNEL)
CY 75.500 $30.000 $80.000 $164.520 $150.000 $250.000 $100.000 $50.000 $50.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 86.000 $7.000 $105.000 $178.990 $80.000 $200.000 $50.000 $60.000 $50.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 15,000.000 $1.000 $0.400 $0.320 $0.500 $0.280 $1.200 $1.250 $1.500
BROADCAST SEED (TEMP) (WARM)
SY 7,500.000 $1.000 $0.400 $0.370 $0.500 $0.280 $1.200 $1.000 $1.500
BROADCAST SEED (TEMP) (COOL)
SY 7,500.000 $1.000 $0.400 $0.370 $0.500 $0.280 $1.200 $1.000 $1.500
FLOWABLE BACKFILL
CY 293.000 $350.000 $500.000 $466.170 $200.000 $350.000 $400.000 $300.000 $350.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 270.000 $70.000 $82.000 $53.390 $1.000 $60.000 $200.000 $150.000 $125.000
CL C CONC(PILE ENCASEMENT)
LF 60.000 $2,000.000 $745.000 $1,020.280 $650.000 $1,500.000 $2,500.000 $3,000.000 $1,500.000
CL C CONC(PILE ENCASEMENT)(UNDERWATER)
LF 60.000 $2,000.000 $1,070.000 $2,145.300 $950.000 $2,200.000 $3,000.000 $3,000.000 $2,000.000
EPOXY WATERPROOF FINISH
SF 3,860.000 $10.000 $70.000 $28.130 $95.000 $25.000 $30.000 $15.000 $17.000
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 214.500 $200.000 $100.000 $299.760 $260.000 $150.000 $150.000 $200.000 $500.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 7.000 $300.000 $400.000 $556.010 $300.000 $1,000.000 $500.000 $200.000 $1,000.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 4,224.000 $200.000 $155.000 $141.600 $180.000 $175.000 $265.000 $300.000 $300.000
CONC STR REPAIR (PAN GIRDER HOLE REPR)
EA 663.000 $250.000 $80.000 $100.010 $300.000 $100.000 $100.000 $75.000 $850.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 110.500 $155.000 $320.000 $383.330 $210.000 $425.000 $300.000 $250.000 $185.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 321.000 $162.000 $270.000 $343.490 $260.000 $450.000 $300.000 $250.000 $250.000
RIPRAP (STONE PROTECTION) (36 IN)
CY 618.500 $200.000 $250.000 $350.040 $340.000 $515.000 $300.000 $300.000 $350.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 4,432.000 $30.000 $45.000 $30.980 $55.000 $25.000 $35.000 $25.000 $50.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 120.000 $30.000 $37.000 $52.160 $65.000 $40.000 $65.000 $30.000 $70.000
GABION MATTRESSES (GALV)(12 IN)
SY 28.000 $250.000 $470.000 $782.330 $300.000 $200.000 $1,000.000 $200.000 $350.000
GAL PIPE (4" X 6")
LF 50.000 $300.000 $275.000 $456.940 $200.000 $150.000 $125.000 $50.000 $150.000
MOBILIZATION
LS 1.000 $214,000.000 $130,000.000 $289,418.250 $280,000.000 $330,000.000 $366,000.000 $300,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $10,000.000 $10,000.000 $6,487.730 $5,000.000 $26,000.000 $11,000.000 $20,000.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,000.000 $5.000 $1.500 $2.810 $0.010 $2.000 $3.650 $0.500 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 10,000.000 $0.500 $1.000 $1.220 $0.010 $0.500 $1.500 $0.500 $2.000
ONE-WAY TRAFFIC CONTROL (PORT TRAF SIG)
DAY 10.000 $320.000 $1,050.000 $1,181.400 $1.000 $1,100.000 $350.000 $600.000 $850.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 165.000 $100.000 $80.000 $166.750 $145.000 $101.000 $75.000 $80.000 $300.000
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 25.000 $100.000 $50.000 $67.770 $300.000 $25.000 $100.000 $125.000 $500.000
STEEL BRIDGE ZONE PAINTING REF STR #1
EA 1.000 $5,000.000 $32,600.000 $32,613.970 $16,000.000 $30,000.000 $30,000.000 $30,000.000 $50,000.000
STEEL BRIDGE ZONE PAINTING REF STR #2
EA 1.000 $5,250.000 $32,400.000 $32,613.970 $16,800.000 $30,000.000 $30,000.000 $33,000.000 $40,000.000
STEEL BRIDGE ZONE PAINTING REF STR #3
EA 1.000 $12,500.000 $35,000.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $40,000.000
STEEL BRIDGE ZONE PAINTING REF STR #4
EA 1.000 $12,500.000 $34,000.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $40,000.000
STEEL BRIDGE ZONE PAINTING REF STR #5
EA 1.000 $12,500.000 $33,500.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $30,000.000
STEEL BRIDGE ZONE PAINTING REF STR #6
EA 1.000 $20,000.000 $50,000.000 $45,013.970 $64,000.000 $50,000.000 $43,000.000 $33,000.000 $60,000.000
STEEL BRIDGE ZONE PAINTING REF STR #7
EA 1.000 $12,500.000 $32,500.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $30,000.000
STEEL BRIDGE ZONE PAINTING REF STR #8
EA 1.000 $12,500.000 $34,100.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $30,000.000
STEEL BRIDGE ZONE PAINTING REF STR #9
EA 1.000 $12,500.000 $33,100.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $30,000.000
STEEL BRIDGE ZONE PAINTING REF STR #10
EA 1.000 $12,500.000 $33,600.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $30,000.000
STEEL BRIDGE ZONE PAINTING REF STR #11
EA 1.000 $12,500.000 $35,500.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $30,000.000
STEEL BRIDGE ZONE PAINTING REF STR #12
EA 1.000 $12,500.000 $34,900.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $30,000.000
STEEL BRIDGE ZONE PAINTING REF STR #13
EA 1.000 $12,500.000 $34,200.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $30,000.000
STEEL BRIDGE ZONE PAINTING REF STR #14
EA 1.000 $12,500.000 $34,000.000 $32,613.970 $40,000.000 $40,000.000 $30,000.000 $33,000.000 $30,000.000
TMA (STATIONARY)
DAY 174.000 $225.000 $275.000 $482.840 $400.000 $300.000 $225.000 $210.000 $250.000
REML & DISPL DRIFTWOOD & DEBRIS
CY 320.000 $50.000 $165.000 $318.410 $100.000 $250.000 $100.000 $140.000 $100.000
Totals: $2,493,956.500 $2,724,265.000 $2,894,201.935 $3,178,815.000 $3,394,530.000 $3,492,380.000 $3,518,800.000 $4,199,462.500