COMAL IH0035 (6477-32-001)

Items: 155

County: COMAL
Length: 0.0100 MILES
Highway: IH0035
District: SAN ANTONIO
Control Number: 6477-32-001
DBE Goal: N/A
Project: RMC - 647732001
Guaranty: $100,000.00
Time: 1095 CALENDAR DAYS
Engineer's Estimate: $8,636,622.50
Date: 01/08/2025 (1 year ago)
Contract Number: 1254203
Type: BUNDLED BID
Project ID: A00212994
Project Description: ROUTINE MAINTENANCE
Mail/Deliver Bids To: N/A
HENRY FOJTIK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$8,636,622.50
$6,284,856.50
Over/Under Est: -27.23% -$2,351,766.00
Over/Under Est: -20.85% -$1,801,009.50
Amt Left: 8.76% $550,756.50
Subcontractor Percentage Amount
AIMS COMPANIES 0.00% $0.00
ALAMO1 0.00% $0.00
BK FIELD OPERATIONS LLC 0.00% $0.00
DIAMOND R CONTRACTING, LLC 0.00% $0.00
DT CONSTRUCTION SERVICES 0.00% $0.00
SWEEPING CORPORATION OF AMERICA, LLC 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

155 Total 0 of 155
COMAL  |  IH0035  |  SAN ANTONIO  |  6477-32-001  |  01/08/2025  |  $8,636,622.50  |  RMC - 647732001  |  BUNDLED BID  |  1095 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
ROY JORGENSEN ASSOCIATES, INC.
REMOV CONC (MEDIANS)
SY 100.000 $30.000 $30.000 $1.000
REMOV CONC (CURB)
LF 100.000 $17.000 $5.500 $1.000
REMOV CONC (FOUNDATIONS)
CY 20.000 $357.000 $275.000 $1.000
REMOV CONC (MISC)
SY 225.000 $60.000 $100.000 $50.000
FLOWABLE BACKFILL
CY 100.000 $350.000 $110.000 $62.500
CLASS K CONCRETE (MISC)
CY 100.000 $500.000 $110.000 $140.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 100.000 $245.000 $330.000 $290.000
RIPRAP (CONC)(CL B)
CY 50.000 $425.000 $380.000 $290.000
RIPRAP (MOW STRIP)(4 IN)
CY 50.000 $500.000 $550.000 $420.000
MOBILIZATION (CALLOUT)
EA 275.000 $1,500.000 $1.000 $2,000.000
MOBILIZATION (EMERGENCY)
EA 50.000 $500.000 $1.000 $500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 75.000 $200.000 $1.000 $1.000
TMA (STATIONARY)
DAY 2,000.000 $150.000 $1.000 $0.010
TMA (MOBILE OPERATION)
HR 3,500.000 $25.000 $1.000 $80.000
CONC CURB (TY II)
LF 50.000 $45.000 $55.000 $6.000
CONC SIDEWALKS (4")
SY 100.000 $60.000 $55.000 $47.500
MTL W-BEAM GD FEN (TIM POST)
LF 6,500.000 $32.000 $33.000 $13.000
MTL W-BEAM GD FEN (STEEL POST)
LF 100.000 $35.000 $1.000 $17.000
MTL THRIE-BEAM GD FEN (TIM POST)
LF 180.000 $70.000 $55.000 $55.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 25.000 $1,500.000 $1,560.000 $750.000
MTL BM GD FEN TRANS (NON - SYM)
EA 10.000 $1,100.000 $1.000 $1,100.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 10.000 $550.000 $1.000 $1,275.000
REMOVE METAL BEAM GUARD FENCE
LF 6,600.000 $6.000 $5.500 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $550.000 $555.000 $145.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 5.000 $450.000 $555.000 $150.000
GUARDRAIL END TREATMENT (INSTALL)
EA 15.000 $3,000.000 $4,500.000 $2,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 18.000 $400.000 $225.000 $1.000
CHAIN LINK FENCE (INSTALL) (6')
LF 200.000 $24.000 $1.000 $24.000
CHAIN LINK FENCE (REPAIR) (6')
LF 100.000 $16.000 $1.000 $16.000
CHAIN LINK FENCE (INSTALL) (4')
LF 425.000 $30.000 $1.000 $20.000
CHAIN LINK FENCE (REPAIR) (4')
LF 200.000 $20.000 $1.000 $13.500
CHAIN LINK FENCE (REMOVE)
LF 450.000 $6.500 $1.000 $1.000
GATE (INSTALL)(6'X4')
EA 4.000 $750.000 $1.000 $1.000
INSTL DEL ASSM (D-DW)SZ 1(BRF)GF2
EA 50.000 $35.000 $28.000 $35.000
INSTL DEL ASSM (D-DY)SZ 1(BRF)GF2
EA 55.000 $35.000 $28.000 $35.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 20.000 $35.000 $1.000 $35.000
POTHOLE REPAIR(STANDARD)(0"-5" DEEP)
SY 100.000 $150.000 $110.000 $300.000
POTHOLE REPAIR(STANDARD)(5"-10" DEEP)
SY 100.000 $160.000 $110.000 $1.000
POTHOLE REPAIR (SAW - CUT)
TON 50.000 $175.000 $550.000 $200.000
EMERGENCY MOBILIZATION
EA 50.000 $250.000 $100.000 $1.000
SPOT MOWING
AC 250.000 $65.000 $55.000 $55.000
FULL - WIDTH MOWING
AC 19,134.000 $57.000 $55.000 $55.500
LITTER REMOVAL
AC 42,624.000 $13.000 $10.000 $13.000
LITTER REMOVAL (SPOT)
AC 200.000 $70.000 $100.000 $13.000
DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES)
MI 2,203.000 $65.000 $180.000 $150.000
DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS)
MI 896.000 $65.000 $180.000 $150.000
DRIFTWOOD REMOVAL
CY 270.000 $50.000 $110.000 $80.500
DEBRIS REMOVAL (SPOT DEBRIS)
MI 300.000 $200.000 $200.000 $50.000
CLEANING / SWEEPING (CENTER MEDIAN)
MI 735.000 $200.000 $200.000 $210.000
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
MI 735.000 $200.000 $200.000 $210.000
CLEANING / SWEEPING (FRONTAGE ROAD)
MI 735.000 $200.000 $200.000 $210.000
CLEANING / SWEEPING(ENTRANCE/EXIT RAMP)
MI 299.000 $200.000 $200.000 $210.000
CLEANING / SWEEPING (AGGREGATE REMOVAL)
MI 100.000 $175.000 $150.000 $75.000
CLEANING / SWEEPING (SPOT)
MI 50.000 $200.000 $210.000 $310.000
CLEANING / SWEEPING (HANDWORK)
SY 10,000.000 $5.000 $5.500 $3.000
GRAFFITI REMOVAL (PAINTING)
SF 385.000 $2.500 $3.500 $3.000
SPOT TREE TRIMMING / BRUSH REMOVAL
LF 5,000.000 $25.000 $15.000 $13.000
DRAIN INLET CLEANING
EA 125.000 $220.000 $200.000 $180.000
STORM SEWER CLEANING (PIPE)(12"-18"DIA)
LF 500.000 $9.000 $6.000 $9.000
STORM SEWER CLEANING (PIPE)(19"-24"DIA)
LF 500.000 $8.000 $10.000 $12.000
SLOTTED DRAIN CLEANING
LF 1,000.000 $14.000 $20.000 $30.000
REPLACE RAIL ELEMENT (W-BEAM)
LF 2,000.000 $25.000 $45.000 $34.000
REPLACE RAIL ELEMENT (THRIE-BEAM)
LF 40.000 $50.000 $112.000 $20.000
REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM)
EA 10.000 $42.000 $560.000 $40.000
REPLACE TIMBER POST W/O CONC FND
EA 50.000 $65.000 $330.000 $250.000
REPLACE STEEL POST W/O CONC FND
EA 75.000 $75.000 $110.000 $1.000
REPLACE TIMBER POST W/ CONC FND
EA 50.000 $82.000 $330.000 $1.000
REPLACE STEEL POST W/ CONC FND
EA 75.000 $92.000 $110.000 $1.000
REALIGN POSTS
EA 500.000 $30.000 $11.000 $5.000
REPAIR OF TERMINAL ANCHORS POSTS
EA 5.000 $80.000 $1.000 $250.000
REPLACE TERMINAL ANCHOR POSTS
EA 5.000 $100.000 $1.000 $200.000
REM OBSOLETE GET & REPL W/ SGT
EA 20.000 $4,000.000 $3,800.000 $4,000.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 10.000 $1,100.000 $1,300.000 $1,150.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 1,050.000 $30.000 $35.000 $80.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 500.000 $85.000 $1.000 $1.000
REPAIR STEEL POST WITH BASE PLATE
EA 10.000 $125.000 $280.000 $440.000
RESET SGT IMPACT HEAD
EA 10.000 $250.000 $550.000 $205.000
REPLACE DOWNSTREAM ANCHOR TERMINAL
EA 20.000 $1,100.000 $1,300.000 $100.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 800.000 $38.000 $28.000 $35.000
REALIGN EXISTING RAIL
LF 200.000 $9.000 $11.000 $7.000
REPLACE CRT POST (WOOD)
EA 200.000 $70.000 $1.000 $1.000
REPLACE SINGLE GDRAIL TERM POST (WOOD)
EA 10.000 $55.000 $350.000 $150.000
REPLACE SINGLE GDRAIL TERM POST (STEEL)
EA 60.000 $85.000 $350.000 $200.000
POST AND CABLE FENCE (REMOVAL)
LF 400.000 $5.000 $11.000 $1.000
POST AND CABLE FENCE (REMV CONC ANCHOR)
EA 5.000 $140.000 $1.000 $1.000
POST AND CABLE FENCE (NEW INSTALLATION)
LF 500.000 $28.000 $28.000 $1.000
POST AND CABLE FENCE (NEW CONC ANCHOR)
EA 15.000 $300.000 $1.000 $1.000
POST AND CABLE FENCE(REMV / REPL POSTS)
EA 100.000 $70.000 $112.000 $1.000
POST AND CABLE FENCE(RMV/REPL CNC ANCH)
EA 10.000 $120.000 $1.000 $1.000
POST AND CABLE FENCE (REMV/ REPL CABLE)
LF 150.000 $10.000 $28.000 $1.000
POST AND CABLE FENCE (REPAIR)
LF 3,000.000 $10.000 $12.000 $1.000
REPLACE (SMTC) WIDE
EA 3.000 $30,000.000 $20,000.000 $18,000.000
REPAIR (SMTC) WIDE
LF 130.000 $300.000 $330.000 $450.000
REPAIR (REACT)(M)
LF 50.000 $100.000 $445.000 $162.500
REPLACE (REACT) WIDE
EA 2.000 $30,000.000 $1.000 $1.000
REPAIR (NARROW QUAD)
LF 150.000 $450.000 $1.000 $120.000
REPAIR (WIDE QUAD)
LF 100.000 $500.000 $450.000 $500.000
REPLACE (TAU-M) NARROW
EA 4.000 $35,000.000 $30,000.000 $21,000.000
REPAIR (TAU-M) NARROW
LF 150.000 $400.000 $550.000 $500.000
REPLACE (TAU II) WIDE
EA 2.000 $35,000.000 $1.000 $1.000
REPAIR (TAU II) WIDE
LF 100.000 $400.000 $550.000 $1.000
REPLACE (INDIVIDUAL SAND BARREL)
EA 225.000 $525.000 $1.000 $300.000
REPAIR (REACT)(N)
LF 100.000 $300.000 $1.000 $50.000
REPAIR (REACT)(N)(CYLINDER ONLY)
EA 6.000 $5,000.000 $1.000 $100.000
REPAIR (REACT)(W)(CYLINDER ONLY)
EA 5.000 $5,000.000 $1.000 $1.000
REPAIR (REACT)(M)(CYLINDER ONLY)
EA 5.000 $5,000.000 $5,000.000 $1.000
REPAIR (QUAD)(N)(M)
LF 50.000 $400.000 $400.000 $225.000
REPLACE (QUAD)(N)(M)
EA 2.000 $30,000.000 $25,000.000 $12,500.000
REPLACE CRASH CUSH ATTEN (L)(N)(TL3)
EA 2.000 $28,000.000 $40,000.000 $27,000.000
REPLACE CRASH CUSH ATTEN (R)(N)(TL3)
EA 3.000 $35,000.000 $25,000.000 $22,500.000
REPLACE CRASH CUSH ATTEN (R)(W)(TL3)
EA 3.000 $38,000.000 $1.000 $1.000
REPLACE CRASH CUSH ATTEN (R)(N)(TL2)
EA 2.000 $26,000.000 $1.000 $22,000.000
REPAIR (STEEL PED. RAIL)
LF 200.000 $100.000 $1.000 $420.000
REPAIR (STL PIPE PED RAIL)(PR1)
LF 200.000 $104.000 $1.000 $345.000
REPLACE(STEEL RAIL)
LF 100.000 $75.000 $1.000 $1.000
PERM CONC TRF BARRIER REPAIR (F SHAPE)
LF 100.000 $150.000 $100.000 $400.000
PERM CONC TRF BARRIER REPLACE (F SHAPE)
LF 100.000 $225.000 $200.000 $1.000
PERM CONC TRF BARR REPAIR(SINGLE SLOPE)
LF 100.000 $150.000 $100.000 $195.000
PERM CONC TRF BARR REPL(SINGLE SLOPE)
LF 100.000 $225.000 $200.000 $1.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 150.000 $200.000 $200.000 $300.000
CONCRETE RAIL REPLACEMENT (IN-KIND)
LF 150.000 $250.000 $1.000 $1.000
REM/REPLACE CURB GUIDANCE SYSTEM
EA 50.000 $250.000 $165.000 $200.000
REM REPLACE CURB
EA 50.000 $175.000 $1.000 $1.000
REM/REPLACE VISION STRIP
EA 50.000 $100.000 $1.000 $1.000
REM/REPLACE CURB TRANS END SECTION
EA 10.000 $140.000 $60.000 $1.000
REM/REPLACE DELINEATOR POST ASSEMBLY
EA 700.000 $55.000 $160.000 $40.000
INCIDENT MANAGEMENT (TYPE A)
HR 100.000 $150.000 $10.000 $1.000
INCIDENT MANAGEMENT (TYPE B)
HR 100.000 $150.000 $10.000 $1.000
INCIDENT MANAGEMENT (TYPE C)
HR 100.000 $1,150.000 $10.000 $1.000
INCIDENT MANAGEMENT (TYPE D)
HR 100.000 $175.000 $10.000 $1.000
INCIDENT MANAGEMENT (TYPE E)
HR 100.000 $250.000 $10.000 $1.000
INCIDENT MANAGEMENT (TYPE F)
HR 50.000 $150.000 $100.000 $1.000
INCIDENT MANAGEMENT (TYPE G)
HR 50.000 $100.000 $10.000 $1.000
INCIDENT MANAGEMENT (TYPE H)
HR 50.000 $100.000 $100.000 $1.000
INCIDENT MANAGEMENT (TYPE I)
HR 50.000 $175.000 $10.000 $1.000
INCIDENT MANAGMENT (TYPE J)
HR 50.000 $50.000 $10.000 $1.000
REPAIR LARGE RDSD SIGN SUPT & ASSEM
EA 25.000 $800.000 $1,700.000 $1,000.000
RELOCATE LARGE RDSD SIGN SUPT & ASSEM
EA 20.000 $100.000 $1.000 $1.000
REPLACE LARGE RDSD SIGN SUPT & ASSEM
EA 100.000 $1,100.000 $550.000 $1,200.000
REMOVE LARGE RDSD SIGN SUPT & ASSEM
EA 100.000 $65.000 $1.000 $1.000
REPAIR SMALL RDSD SIGN SUPT & ASSEM
EA 275.000 $350.000 $380.000 $500.000
RELOCATE SMALL RDSD SIGN SUPT & ASSEM
EA 25.000 $150.000 $1.000 $1.000
REPLACE SMALL RDSD SIGN SUPT & ASSEM
EA 150.000 $425.000 $600.000 $500.000
REMOVE SMALL RDSD SIGN SUPT & ASSEM
EA 25.000 $125.000 $1.000 $1.000
SNOW AND ICE CONTROL (TRUCK)
HR 500.000 $95.000 $80.000 $1.000
SNOW AND ICE CONTROL (SHADOW VEHICLE)
HR 500.000 $75.000 $80.000 $50.000
SNOW AND ICE CONTROL (SPRAY RIG)
HR 500.000 $85.000 $80.000 $125.000
SNOW AND ICE CONTROL SEASON
MO 15.000 $100,000.000 $50,000.000 $50,000.000
SITE INSPECTION AND CLEANING
EA 210.000 $140.000 $250.000 $250.000
TRASH, DEBRIS, ADN SEDIMENT REMOVAL
CYC 29.000 $260.000 $1,650.000 $1,650.000
REPLACING FILTER CARTRIDGES
EA 4,950.000 $65.000 $40.000 $37.000
ROTATION OF FILTER CARTRIDGES
EA 685.000 $15.000 $18.000 $25.000
MOWING AND TRIMMING
CYC 65.000 $190.000 $180.000 $315.000
REPLACE BLADDER VALVE
EA 15.000 $165.000 $150.000 $160.000
REPLACE BATTERY
EA 50.000 $75.000 $60.000 $140.000
Totals: $8,636,622.500 $6,284,856.500 $6,835,613.000