Show Job Controls
Bid Cobra

COMAL SH0046 (6457-89-001)

Items: 75

County: COMAL
Length: N/A
Highway: SH0046
District: SAN ANTONIO
Control Number: 6457-89-001
DBE Goal: 0.0%
Project: RMC - 645789001
Guaranty: N/A
Time: 730 CALENDAR DAYS
Engineer's Estimate: $2,947,812.25
Date: 01/04/2024 (2 years ago) Changed
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To: N/A
HENRY FOJTIK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$2,947,812.25
$1,996,311.00
Over/Under Est: -32.28% -$951,501.25
$2,271,540.36
Over/Under Est: -22.94% -$676,271.89
Amt Left: 13.79% $275,229.36
Over/Under Est: -6.97% -$205,556.25
Amt Left: 37.37% $745,945.00
Delta: -20.72% -$470,715.64
$2,794,530.00
Over/Under Est: -5.2% -$153,282.25
Amt Left: 39.98% $798,219.00
Delta: -1.91% -$52,274.00
$3,078,400.00
Over/Under Est: 4.43% $130,587.75
Amt Left: 54.2% $1,082,089.00
Delta: -10.16% -$283,870.00
Over/Under Est: 6.06% $178,662.75
Amt Left: 56.61% $1,130,164.00
Delta: -1.56% -$48,075.00
Over/Under Est: 45.85% $1,351,648.75
Amt Left: 115.37% $2,303,150.00
Delta: -37.52% -$1,172,986.00

Bid Items & Bid Tabulations

75 Total 0 of 75
COMAL  |  SH0046  |  SAN ANTONIO  |  6457-89-001  |  01/04/2024  |  $2,947,812.25  |  RMC - 645789001  |  METAL BEAM GUARD FENCE REPAIR  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SHORT-LINE CORPORATION
ROSS SA ENTERPRISE LLC
DIAMOND R CONTRACTING, LLC
DIGG COMMERCIAL, LLC
ABOVE ALL CONSTRUCTION
HAZMAT INTERNATIONAL, INC.
ROY JORGENSEN ASSOCIATES, INC.
REMOVING CONC (MISC)
SY 100.000 $42.260 $100.000 $39.100 $50.000 $30.000 $100.000 $2.000 $50.000
RIPRAP (CONC)(CL B)
CY 50.000 $1,065.500 $100.000 $100.250 $50.000 $200.000 $100.000 $200.000 $225.000
RIPRAP (MOW STRIP)(4 IN)
CY 50.000 $100.000 $100.000 $202.500 $100.000 $300.000 $400.000 $400.000 $500.000
RETROFIT RAIL (TY T631)
LF 500.000 $75.000 $30.000 $10.250 $15.000 $35.000 $30.000 $10.000 $105.000
MOBILIZATION (CALLOUT)
EA 500.000 $100.000 $1.000 $1.100 $1.000 $1.000 $1.000 $5.000 $1.000
MOBILIZATION (EMERGENCY)
EA 100.000 $200.000 $1.000 $1.080 $1.000 $1.000 $1.000 $5.000 $750.000
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $25.000 $100.000 $30.450 $20.000 $16.000 $25.000 $21.000 $40.000
MTL W-BEAM GD FEN (STEEL POST)
LF 500.000 $25.000 $1.000 $21.400 $20.000 $22.000 $40.000 $25.000 $30.000
MTL THRIE-BEAM GD FEN (TIM POST)
LF 150.000 $30.000 $1.000 $1.065 $30.000 $40.000 $100.000 $35.000 $40.000
MTL THRIE-BEAM GD FEN (STEEL POST)
LF 150.000 $40.000 $1.000 $1.470 $30.000 $47.000 $100.000 $40.000 $35.000
TERMINAL ANCHOR SECTION
EA 5.000 $300.000 $100.000 $1.500 $500.000 $500.000 $500.000 $900.000 $1.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 10.000 $1,800.000 $1,500.000 $909.800 $1,500.000 $700.000 $1,500.000 $800.000 $1,850.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 1,000.000 $15.000 $1.000 $1.200 $2.000 $1.000 $5.000 $2.000 $5.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 20.000 $1,200.000 $1,200.000 $509.450 $1,200.000 $800.000 $1,200.000 $500.000 $1,600.000
DOWNSTREAM ANCHOR TERMINAL ADJUSTMENT
EA 15.000 $400.000 $1.000 $1.050 $100.000 $1.000 $100.000 $50.000 $150.000
REMOVE METAL BEAM GUARD FENCE
LF 2,000.000 $2.000 $2.000 $9.030 $1.000 $1.000 $2.000 $0.600 $10.000
REMOVE TERMINAL ANCHOR SECTION
EA 5.000 $400.000 $500.000 $501.480 $100.000 $1.000 $500.000 $100.000 $250.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 15.000 $400.000 $100.000 $1.000 $100.000 $1.000 $100.000 $100.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,500.000 $1.000 $3,202.210 $3,000.000 $2,000.000 $3,000.000 $2,800.000 $4,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 5.000 $500.000 $3,000.000 $802.350 $500.000 $1.000 $300.000 $500.000 $500.000
GDRAIL END TRT(INST)(WOOD POST)(TY III)
EA 10.000 $2,000.000 $1.000 $1.000 $3,000.000 $1,000.000 $2,000.000 $2,000.000 $4,100.000
CRASH CUSH ATTEN (INSTL) (S) (TL3)
EA 3.000 $5,500.000 $100.000 $2,560.330 $8,000.000 $5,000.000 $10,000.000 $7,800.000 $6,700.000
CHAIN LINK FENCE (REPAIR) (6')
LF 500.000 $10.000 $10.000 $10.340 $10.000 $6.000 $10.000 $5.000 $10.000
CHAIN LINK FENCE (REMOVE)
LF 500.000 $5.000 $5.000 $5.080 $5.000 $1.000 $5.000 $2.000 $2.000
INSTL DEL ASSM (D-DW)SZ 1(BRF)GF2
EA 1,000.000 $25.000 $9.000 $1.010 $2.500 $20.000 $15.000 $13.000 $15.000
INSTL DEL ASSM (D-DY)SZ 1(BRF)GF2
EA 1,000.000 $30.000 $1.000 $1.050 $2.500 $20.000 $15.000 $13.000 $15.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 25,000.000 $20.000 $1.000 $15.450 $16.000 $14.000 $18.000 $11.000 $22.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 100.000 $20.000 $50.000 $25.360 $50.000 $35.000 $50.000 $5.000 $25.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 50.000 $25.000 $50.000 $35.650 $50.000 $50.000 $50.000 $10.000 $25.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 1,000.000 $30.000 $15.000 $1.200 $20.000 $1.000 $30.000 $20.000 $32.000
REALIGN EXISTING RAIL
LF 500.000 $10.000 $1.000 $1.040 $5.000 $1.000 $5.000 $5.000 $10.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 2,500.000 $40.000 $100.000 $1.680 $40.000 $22.000 $20.000 $55.000 $30.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 200.000 $45.000 $1.000 $1.470 $30.000 $90.000 $50.000 $70.000 $40.000
REALIGN POSTS
EA 300.000 $5.000 $100.000 $308.450 $10.000 $100.000 $20.000 $10.000 $5.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 6,000.000 $25.000 $20.000 $1.050 $20.000 $19.000 $20.000 $16.000 $27.000
REPAIR OF TERMINAL ANCHORS POSTS
EA 20.000 $25.000 $1.000 $1.420 $50.000 $200.000 $50.000 $25.000 $150.000
REPLACE TERMINAL ANCHOR POSTS
EA 50.000 $35.000 $1.000 $1.260 $50.000 $200.000 $50.000 $200.000 $150.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 225.000 $2,500.000 $1.000 $1,754.150 $2,500.000 $1,700.000 $2,800.000 $3,400.000 $3,200.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 150.000 $750.000 $1.000 $105.000 $1,000.000 $600.000 $800.000 $1,000.000 $1,000.000
REM & RESET SGT IMPACT HEAD
EA 100.000 $100.000 $1,000.000 $201.000 $100.000 $1.000 $100.000 $25.000 $250.000
REPAIR STEEL POST WITH BASE PLATE
EA 20.000 $200.000 $50.000 $50.500 $50.000 $100.000 $200.000 $50.000 $350.000
REMOVE AND REPLACE LONG SPAN CRT POST
EA 50.000 $50.000 $1.000 $1.200 $50.000 $100.000 $100.000 $10.000 $125.000
REMOVE AND REPLACE DAT
EA 250.000 $350.000 $1.000 $1.210 $100.000 $500.000 $100.000 $900.000 $1,800.000
REPAIR MTL BM GD FEN(LONG SPAN SYS)
LF 2,500.000 $30.000 $1.000 $0.980 $20.000 $1.000 $17.000 $5.000 $18.000
REPLACE SINGLE GDRAIL TERM POST(WOOD)
EA 750.000 $60.000 $100.000 $20.140 $50.000 $20.000 $50.000 $60.000 $70.000
REPLACE SINGLE GDRAIL TERM POST(STEEL)
EA 750.000 $65.000 $1.000 $26.250 $50.000 $80.000 $80.000 $200.000 $200.000
REPLACE POSTS (TL-3)
EA 3,000.000 $100.000 $150.000 $30.000 $150.000 $100.000 $130.000 $165.000 $200.000
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 50.000 $150.000 $50.000 $50.510 $1.000 $1.000 $200.000 $330.000 $250.000
REPAIR CONCRETE FOUNDATION (TL-3)
EA 40.000 $200.000 $10.000 $25.020 $10.000 $1.000 $10.000 $25.000 $350.000
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 75.000 $750.000 $1,500.000 $815.410 $2,000.000 $700.000 $1,200.000 $800.000 $950.000
REPLACE CABLE (TL-3)
LF 10,000.000 $2.000 $0.010 $1.100 $1.000 $0.010 $5.000 $5.000 $2.000
POST AND CABLE FENCE (REMOVAL)
LF 100.000 $4.000 $10.000 $1.080 $5.000 $1.000 $10.000 $6.000 $1.000
POST AND CABLE FENCE (REMV CONC ANCHOR)
EA 5.000 $200.000 $50.000 $105.000 $50.000 $200.000 $50.000 $100.000 $200.000
POST AND CABLE FENCE(REMV / REPL POSTS)
EA 30.000 $45.000 $100.000 $624.350 $40.000 $100.000 $30.000 $30.000 $500.000
POST AND CABLE FENCE(RMV/REPL CNC ANCH)
EA 5.000 $200.000 $100.000 $984.670 $50.000 $200.000 $100.000 $100.000 $500.000
POST AND CABLE FENCE (REMV/ REPL CABLE)
LF 1,000.000 $5.000 $75.000 $52.470 $5.000 $5.000 $5.000 $2.000 $5.000
REPAIR (REACT)
EA 5.000 $15,625.250 $1,000.000 $299.870 $5,000.000 $4,000.000 $4,000.000 $500.000 $1,000.000
REPAIR REACT (N) (CYLINDERS)
EA 5.000 $6,225.000 $3,000.000 $289.780 $5,000.000 $3,500.000 $3,000.000 $500.000 $3,250.000
REPAIR (VIA -SAND FILL PLASTIC BARRELS)
EA 100.000 $350.000 $400.000 $254.640 $300.000 $250.000 $400.000 $500.000 $600.000
REMOVE AND REPLACE (SHORTRACC)
EA 6.000 $15,000.000 $1.000 $507.450 $1.000 $4,500.000 $18,000.000 $18,500.000 $1.000
REPAIR (QUADGUARD)(MASH)(N)
EA 3.000 $29.000 $1,000.000 $5,008.470 $5,000.000 $500.000 $5,000.000 $2,000.000 $1,500.000
REPAIR (QUADGUARD)(MASH)(N)(BAY)
EA 3.000 $151.000 $1,000.000 $1,507.870 $5,000.000 $500.000 $1,500.000 $1,500.000 $2,500.000
REMOVE AND REPLACE (REACT)(M)(NARROW)
EA 5.000 $100.000 $20,000.000 $1,062.140 $5,000.000 $4,500.000 $30,000.000 $30,000.000 $28,000.000
REPAIR (STL POST W/ DOUBLED W-BEAMS-T6)
LF 1,000.000 $45.000 $25.000 $10.240 $20.000 $1.000 $27.000 $10.000 $150.000
REPAIR (STL PIPE PEDESTRIAN RAIL - PR1)
LF 100.000 $200.000 $100.000 $81.650 $50.000 $1.000 $150.000 $5.000 $200.000
REPAIR (W-BEAM - T101 RAIL)
LF 500.000 $42.500 $50.000 $9.870 $20.000 $1.000 $30.000 $30.000 $25.000
REPAIR (EXISTING METAL PED. RAIL)
LF 100.000 $200.000 $200.000 $124.220 $50.000 $1.000 $50.000 $10.000 $225.000
REP METAL PST W/ BASE PLATE (TY T631)
EA 20.000 $150.000 $200.000 $49.880 $50.000 $150.000 $150.000 $250.000 $150.000
REP W BEAM (TY T631)
LF 125.000 $20.000 $25.000 $23.120 $20.000 $10.000 $50.000 $30.000 $15.000
REM/REPLACE CURB GUIDANCE SYSTEM
EA 5.000 $150.330 $100.000 $498.520 $400.000 $200.000 $200.000 $200.000 $150.000
REM/REPLACE CURB
EA 5.000 $165.000 $100.000 $478.450 $400.000 $200.000 $200.000 $200.000 $100.000
REM/REPLACE VISION STRIP
EA 5.000 $80.000 $100.000 $492.000 $400.000 $200.000 $200.000 $5.000 $50.000
REM/REPLACE CURB TRANS END SECTION
EA 5.000 $125.000 $50.000 $465.250 $400.000 $200.000 $200.000 $5.000 $150.000
REM/REPLACE DELINEATOR POST ASSEMBLY
EA 5.000 $83.670 $50.000 $305.440 $400.000 $200.000 $200.000 $75.000 $75.000
TMA (STATIONARY)
DAY 200.000 $200.000 $1,500.000 $4,056.780 $1,000.000 $4,200.000 $1,000.000 $100.000 $1,100.000
Totals: $2,947,812.250 $1,996,311.000 $2,271,540.360 $2,742,256.000 $2,794,530.000 $3,078,400.000 $3,126,475.000 $4,299,461.000