Show Job Controls
Bid Cobra

COMAL FM0306 (6411-85-001)

Items: 21

County: COMAL
Length: 0.0100 MILES
Highway: FM0306
District: SAN ANTONIO
Control Number: 6411-85-001
DBE Goal: N/A
Project: BPM - A00189581
Guaranty: $4,000.00
Time: 25 WORKING DAYS
Engineer's Estimate: $190,731.48
Date: 02/20/2025 (1 year ago)
Contract Number: 2251510
Type: EROSION REPAIR
Project ID: A00189581
Project Description: SCOUR REPAIR
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
4615 NW LOOP 410, SAN ANTONIO, TX 78229
HENRY FOJTIK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (13)
E
Engineer's Estimate
$190,731.48
$135,300.00
Over/Under Est: -29.06% -$55,431.48
Over/Under Est: -4.52% -$8,621.82
Amt Left: 34.6% $46,809.66
Over/Under Est: -0.27% -$508.48
Amt Left: 40.59% $54,923.00
Delta: -4.46% -$8,113.34
Over/Under Est: 1.27% $2,427.02
Amt Left: 42.76% $57,858.50
Delta: -1.54% -$2,935.50
Over/Under Est: 2.9% $5,527.52
Amt Left: 45.05% $60,959.00
Delta: -1.61% -$3,100.50
Over/Under Est: 3.85% $7,352.52
Amt Left: 46.4% $62,784.00
Delta: -0.93% -$1,825.00
Over/Under Est: 9.79% $18,670.52
Amt Left: 54.77% $74,102.00
Delta: -5.71% -$11,318.00
$226,613.25
Over/Under Est: 18.81% $35,881.77
Amt Left: 67.49% $91,313.25
Delta: -8.22% -$17,211.25
Over/Under Est: 19.83% $37,823.52
Amt Left: 68.92% $93,255.00
Delta: -0.86% -$1,941.75
Over/Under Est: 20.68% $39,445.52
Amt Left: 70.12% $94,877.00
Delta: -0.71% -$1,622.00
$232,778.00
Over/Under Est: 22.04% $42,046.52
Amt Left: 72.05% $97,478.00
Delta: -1.13% -$2,601.00
Over/Under Est: 22.55% $43,018.52
Amt Left: 72.76% $98,450.00
Delta: -0.42% -$972.00
Over/Under Est: 49.78% $94,955.52
Amt Left: 111.15% $150,387.00
Delta: -22.22% -$51,937.00

Bid Items & Bid Tabulations

21 Total 0 of 21
COMAL  |  FM0306  |  SAN ANTONIO  |  6411-85-001  |  02/20/2025  |  $190,731.48  |  BPM - A00189581  |  EROSION REPAIR  |  25 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BK FIELD OPERATIONS LLC
USA DT SERVICES, INC.
DIAMOND R CONTRACTING, LLC
AAD CONTRACTING INC.
BECK-REIT & SONS, LTD.
DELGADO'S CONTRACTORS, LLC
TEXAS ROAD CONSTRUCTION, LLC
LAKEY, INC.
ICOS MANAGEMENT, LLC
TAYLOR CONTRACTING LLC
RHINO EQUITY, LLC
CRACKSEAL OF TEXAS, LLC
STRUCTURAL INTEGRITY GROUP LLC
EXCAV (CHANNEL)
CY 30.000 $94.330 $30.000 $50.000 $100.000 $20.000 $100.000 $40.000 $200.000 $75.000 $110.000 $250.000 $16.000 $50.000 $90.000
EMBANK (FNL)(OC)(TY B)
CY 240.000 $61.500 $1.000 $50.000 $65.000 $55.000 $50.000 $55.000 $100.000 $45.580 $55.000 $100.000 $30.000 $50.000 $85.000
COMPOST MANUF TOPSOIL (4")
SY 500.000 $1.500 $10.000 $20.000 $5.000 $8.000 $5.000 $15.000 $2.000 $6.000 $11.000 $5.000 $6.000 $50.000 $21.500
BROADCAST SEED (PERM_URBAN_CLAY)
SY 500.000 $0.240 $1.000 $1.000 $1.000 $2.000 $1.000 $3.500 $3.000 $1.000 $1.000 $1.000 $2.000 $50.000 $7.500
SOIL RET BLKT(SL_MOD_CLAY_LONG)
SY 500.000 $4.790 $2.000 $2.000 $1.000 $6.000 $5.000 $5.000 $10.000 $4.390 $11.000 $2.000 $6.000 $50.000 $9.500
FLOWABLE BACKFILL
CY 35.000 $323.910 $50.000 $300.000 $100.000 $275.000 $288.000 $325.000 $250.000 $450.000 $440.000 $500.000 $400.000 $300.000 $675.000
RIPRAP (CONC)(5 IN)
CY 120.000 $650.000 $515.000 $300.000 $650.000 $300.000 $711.000 $630.000 $400.000 $702.560 $660.000 $650.000 $700.000 $190.000 $680.000
RIPRAP (MOW STRIP)(4 IN)
CY 7.000 $755.250 $475.000 $300.000 $1,000.000 $400.000 $800.000 $725.000 $600.000 $700.000 $770.000 $750.000 $800.000 $10.000 $2,100.000
RIPRAP (STONE COMMON)(DRY)(6 IN)
CY 89.000 $238.750 $30.000 $138.000 $100.000 $140.000 $165.000 $120.000 $100.000 $115.000 $275.000 $150.000 $280.000 $190.000 $240.000
GABION MATTRESSES (GALV)(12 IN)
SY 118.000 $103.260 $100.000 $139.420 $100.000 $200.000 $150.000 $105.000 $225.000 $156.000 $165.000 $125.000 $110.000 $50.000 $250.000
GABION (1.5' X 3')(GALV)
CY 33.000 $210.000 $230.000 $200.000 $100.000 $200.000 $255.000 $365.000 $200.000 $200.000 $495.000 $400.000 $330.000 $50.000 $535.000
MOBILIZATION
LS 1.000 $12,000.000 $25,000.000 $63,700.000 $10,000.000 $25,000.000 $10,000.000 $15,500.000 $50,000.000 $25,000.000 $13,000.000 $25,000.000 $30,000.000 $35,000.000 $18,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,500.000 $1.000 $2,000.000 $10,000.000 $10,000.000 $2,500.000 $2,750.000 $2,500.000 $5,000.000 $1.000 $7,500.000 $6,000.000 $10.000 $13,000.000
TMA (STATIONARY)
DAY 25.000 $196.610 $1.000 $100.000 $1.000 $350.000 $1.000 $225.000 $100.000 $205.000 $275.000 $1.000 $100.000 $10.000 $1.000
ROCK FILTER DAMS (REMOVE)
CY 4.000 $14.200 $100.000 $1.000 $1,000.000 $12.000 $1.000 $50.000 $1,000.000 $100.000 $550.000 $1.000 $6.000 $250.000 $135.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 224.000 $22.800 $1.000 $0.100 $1.000 $8.000 $15.000 $24.000 $20.000 $34.000 $11.000 $1.000 $10.000 $50.000 $12.000
CONSTRUCTION EXITS (REMOVE)
SY 224.000 $7.450 $1.000 $0.100 $1.000 $4.000 $5.000 $7.000 $10.000 $12.655 $11.000 $1.000 $6.000 $50.000 $6.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 325.000 $6.310 $4.000 $7.000 $1.000 $4.500 $5.000 $7.000 $1.000 $6.625 $5.000 $1.000 $6.000 $5.000 $3.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 325.000 $1.510 $2.000 $2.000 $1.000 $1.000 $1.000 $1.000 $1.000 $2.000 $1.000 $1.000 $2.000 $5.000 $1.000
DRIFTWOOD REMOVAL
LS 2.000 $500.000 $200.000 $1.000 $5,000.000 $8,000.000 $2,500.000 $3,000.000 $1.000 $5,000.000 $5,500.000 $2,000.000 $6,000.000 $9,000.000 $1,000.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 0.300 $2,000.000 $35,000.000 $1.000 $35,000.000 $20,000.000 $25,000.000 $8,000.000 $100.000 $12,500.000 $1,100.000 $25,000.000 $10,000.000 $25,000.000 $10,000.000
Totals: $190,731.480 $135,300.000 $182,109.660 $190,223.000 $193,158.500 $196,259.000 $198,084.000 $209,402.000 $226,613.245 $228,555.000 $230,177.000 $232,778.000 $233,750.000 $285,687.000