Show Job Controls
Bid Cobra

COMAL FM 1101 (1272-01-019)

Items: 12

County: COMAL
Length: N/A
Highway: FM 1101
District: SAN ANTONIO
Control Number: 1272-01-019
DBE Goal: N/A
Project: STP 2019(046)HES
Guaranty: N/A
Time: 119 WORKING DAYS
Engineer's Estimate: $259,933.16
Date: 09/07/2018 (7 years ago)
Contract Number: N/A
Type: PROFILE EDGELINE & CENTERLINE MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$259,933.16
$195,334.08
Over/Under Est: -24.85% -$64,599.08
Over/Under Est: -23.14% -$60,138.18
Amt Left: 2.28% $4,460.90
Over/Under Est: -22.39% -$58,197.78
Amt Left: 3.28% $6,401.30
Delta: -0.97% -$1,940.40
$219,535.07
Over/Under Est: -15.54% -$40,398.09
Amt Left: 12.39% $24,200.99
Delta: -8.82% -$17,799.69

Bid Items & Bid Tabulations

12 Total 0 of 12
COMAL  |  FM 1101  |  SAN ANTONIO  |  1272-01-019  |  09/07/2018  |  $259,933.16  |  STP 2019(046)HES  |  PROFILE EDGELINE & CENTERLINE MRK  |  119 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRP CONSTRUCTION GROUP, LLC
INTERSTATE BARRICADES & MARKINGS, INC.
D. I. J. CONSTRUCTION, INC.
STRIPE-A-ZONE, INC.
MOBILIZATION
LS 1.000 $19,393.570 $14,000.000 $7,500.000 $20,000.000 $30,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $3,500.000 $500.000 $1.000 $1.000 $1,500.000
RUMBLE STRIPS (SHOULDER)
LF 53,272.000 $0.270 $0.170 $0.300 $0.230 $0.200
RUMBLE STRIPS (CENTERLINE)
LF 25,936.000 $0.210 $0.240 $0.300 $0.320 $0.270
PAVEMENT SEALER 4"
LF 35,586.000 $0.110 $0.160 $0.250 $0.100 $0.100
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 3,880.000 $0.560 $0.500 $0.650 $0.330 $0.850
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 31,706.000 $0.350 $0.400 $0.400 $0.310 $0.370
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 140,534.000 $0.580 $0.520 $0.530 $0.540 $0.505
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 3,337.000 $0.690 $0.600 $1.000 $0.600 $0.550
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 112,922.000 $0.590 $0.530 $0.530 $0.540 $0.505
REFL PAV MRKR TY II-A-A
EA 2,210.000 $3.700 $3.250 $3.000 $3.400 $5.750
TMA (STATIONARY)
DAY 126.000 $162.000 $1.000 $1.000 $1.000 $2.000
Totals: $259,933.160 $195,334.080 $199,794.980 $201,735.380 $219,535.070