COMAL FM 482 (0016-19-025)

Items: 29

County: COMAL
Length: N/A
Highway: FM 482
District: SAN ANTONIO
Control Number: 0016-19-025
DBE Goal: N/A
Project: C 16-19-25
Guaranty: N/A
Time: 91 WORKING DAYS
Engineer's Estimate: $10,333,036.38
Date: 10/06/2022 (3 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
CHRISTEN LONGORIA
FRANCES MERECKA
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$10,333,036.38
$9,397,889.26
Over/Under Est: -9.05% -$935,147.12
Over/Under Est: -4.44% -$458,797.15
Amt Left: 5.07% $476,349.97
Over/Under Est: -3.95% -$408,593.19
Amt Left: 5.6% $526,553.93
Delta: -0.51% -$50,203.96

Bid Items & Bid Tabulations

29 Total 0 of 29
COMAL  |  FM 482  |  SAN ANTONIO  |  0016-19-025  |  10/06/2022  |  $10,333,036.38  |  C 16-19-25  |  RESURF ROADWAY  |  91 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RONALD R. WAGNER & CO., LP
CLARK CONSTRUCTION OF TEXAS, INC.
BRANNAN PAVING CO., LTD.
ASPH (A-R TYPE II)
GAL 418,593.000 $3.600 $3.200 $3.200 $3.740
AGGR(TY-PD GR-3 SAC-B)
CY 5,461.000 $85.000 $85.000 $85.000 $83.140
AGGR(TY-PD GR-5 SAC-B)
CY 776.000 $130.000 $85.190 $70.000 $82.380
AGGR (TY-PD GR-4 OR GR-4S SAC-B)
CY 23,825.000 $75.000 $86.170 $75.000 $84.720
ASPH (AC-20-5TR OR AC-20XP)
TON 4,377.000 $850.000 $743.080 $850.000 $798.000
MOBILIZATION
LS 1.000 $929,555.980 $1,238,590.000 $1,399,000.000 $1,404,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $8,000.000 $20,000.000 $15,000.000 $10,000.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 7,424.000 $2.000 $0.010 $0.010 $0.010
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 23,089.000 $1.500 $0.010 $0.010 $0.010
REFL PAV MRK TY II (W) 4" (BRK)
LF 73,840.000 $0.150 $0.100 $0.130 $0.100
REFL PAV MRK TY II (W) 4" (DOT)
LF 1,046.000 $1.000 $0.500 $0.130 $0.500
REFL PAV MRK TY II (W) 6" (SLD)
LF 1,724,740.000 $0.400 $0.130 $0.190 $0.125
REFL PAV MRK TY II (W) 8" (SLD)
LF 48,888.000 $0.250 $0.200 $0.260 $0.200
REFL PAV MRK TY II (Y) 4" (BRK)
LF 139,889.000 $0.150 $0.100 $0.130 $0.100
REFL PAV MRK TY II (Y) 4" (SLD)
LF 1,234,061.000 $0.150 $0.100 $0.130 $0.100
PREFAB PAV MRK TY C (W) (18") (SLD)
LF 245.000 $9.000 $12.000 $7.000 $12.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 4,090.000 $14.000 $12.000 $9.000 $12.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 135.000 $200.000 $220.000 $200.000 $210.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 7.000 $400.000 $400.000 $315.000 $400.000
PREFAB PAV MRK TY C (W) (WORD)
EA 118.000 $250.000 $250.000 $240.000 $250.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 10.000 $550.000 $650.000 $450.000 $650.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 408.000 $30.000 $32.000 $25.000 $32.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 2,214.000 $13.000 $12.000 $9.000 $12.000
PREFAB PAV MRK TY C (Y) (MED NOSE)
EA 26.000 $350.000 $350.000 $400.000 $350.000
REFL PAV MRKR TY I-C
EA 2,683.000 $4.000 $3.500 $2.900 $3.500
REFL PAV MRKR TY II-A-A
EA 22,795.000 $4.000 $3.500 $2.900 $3.500
REFL PAV MRKR TY II-C-R
EA 420.000 $4.000 $5.000 $2.900 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 1,524,542.000 $0.300 $0.160 $0.190 $0.160
TMA (MOBILE OPERATION)
DAY 316.000 $250.000 $0.010 $0.010 $5.000
Totals: $10,333,036.380 $9,397,889.260 $9,874,239.230 $9,924,443.190