COLORADO FM 109 (0716-02-045)
Items: 83
County: COLORADO
Length: N/A
Highway: FM 109
District: YOAKUM
Control Number: 0716-02-045
DBE Goal: N/A
Project: BR 2022(323)
Guaranty: N/A
Time: 246 WORKING DAYS
Engineer's Estimate: $6,400,527.75
Date: 02/04/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,400,527.75 | |||
| $6,985,517.21 |
9.14%
$584,989.46
|
|||
| $7,350,499.87 |
14.84%
$949,972.12
|
5.22%
$364,982.66
|
||
| $7,906,192.53 |
23.52%
$1,505,664.78
|
13.18%
$920,675.32
|
-7.56%
-$555,692.66
|
E
Engineer's Estimate
$6,400,527.75
1
Awarded
$6,985,517.21
Over/Under Est:
9.14%
$584,989.46
$7,350,499.87
Over/Under Est:
14.84%
$949,972.12
Amt Left:
5.22%
$364,982.66
$7,906,192.53
Over/Under Est:
23.52%
$1,505,664.78
Amt Left:
13.18%
$920,675.32
Delta:
-7.56%
-$555,692.66
| Subcontractor | Percentage | Amount |
|---|---|---|
| CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | 10.30% | $719,508.27 |
| M & D FOUNDATION DRILLING INDUSTRIES, INC. | 9.56% | $667,815.45 |
| HUNTER DEMOLITION & WRECKING CORPORATION | 2.75% | $192,101.72 |
| SIREN STEEL, INC. | 1.26% | $88,017.52 |
| FARR FOUNDATION, INC. | 1.06% | $74,046.48 |
| DIIBS SPECIALISTS, LLC | 0.94% | $65,663.86 |
| QUALITY TURF FARMS, L.C. | 0.81% | $56,582.69 |
| HIGHWAY 1 LLC | 0.61% | $42,611.65 |
| COLD CREEK CONSTRUCTION, LTD | 0.53% | $37,023.24 |
| J.KRU LAND SERVICES, LLC | 0.28% | $19,559.45 |
| HOUSTON SAWING & DRILLING | 0.18% | $12,573.93 |
| A. L. HELMCAMP, INC. | 0.16% | $11,176.83 |
| LONESTAR TRAFFIC SAFETY, LLC | 0.13% | $9,081.17 |
| MTAM CORPORATION | 0.06% | $4,191.31 |
| Total: | 28.63% | $1,999,953.57 |