PREPARING ROW
|
STA
|
46.260
|
$2,500.000
|
$15,000.000
|
$28,100.000
|
$16,000.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
113.000
|
$10.000
|
$25.000
|
$23.940
|
$16.000
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
40.000
|
$10.000
|
$25.000
|
$13.870
|
$1.000
|
|
|
REMOVING CONC (FLUME)
|
SY
|
52.000
|
$15.000
|
$25.000
|
$11.040
|
$40.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
6,547.000
|
$8.000
|
$8.000
|
$10.000
|
$20.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
22,168.000
|
$14.000
|
$25.000
|
$16.000
|
$26.000
|
|
|
BLADING
|
HR
|
100.000
|
$80.000
|
$85.000
|
$146.330
|
$60.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
66,387.000
|
$1.000
|
$1.500
|
$1.020
|
$3.400
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
66,387.000
|
$0.500
|
$0.280
|
$0.250
|
$0.400
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
16,597.000
|
$0.500
|
$0.280
|
$0.250
|
$0.350
|
|
|
CELL FBR MLCH SEED(TEMP)(COOL)
|
SY
|
16,597.000
|
$0.500
|
$0.280
|
$0.250
|
$0.350
|
|
|
VEGETATIVE WATERING
|
MG
|
1,394.000
|
$15.000
|
$30.000
|
$21.820
|
$14.000
|
|
|
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
|
CY
|
3,709.000
|
$70.000
|
$75.000
|
$90.000
|
$70.000
|
|
|
FL BS (CMP IN PLC)(RAP) (6")
|
SY
|
2,284.000
|
$10.000
|
$25.000
|
$9.440
|
$10.000
|
|
|
LIME TRT (EXST MATL) (6")
|
SY
|
14,484.000
|
$2.500
|
$5.000
|
$5.100
|
$4.000
|
|
|
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
|
TON
|
174.000
|
$150.000
|
$180.000
|
$203.020
|
$190.000
|
|
|
SALV, HAUL & STKPL RCL APH PV (4 TO 6")
|
SY
|
2,692.000
|
$3.500
|
$5.500
|
$4.110
|
$4.000
|
|
|
SLV,HAUL & STKPL RCL APH PV (10 TO 12")
|
SY
|
8,614.000
|
$6.000
|
$8.000
|
$5.480
|
$4.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
3,865.000
|
$3.500
|
$6.000
|
$8.180
|
$5.900
|
|
|
AGGR(TY-PE GR-3 SAC-B)
|
CY
|
196.000
|
$150.000
|
$200.000
|
$278.150
|
$197.000
|
|
|
AGGR(TY-PE GR-4 SAC-B)
|
CY
|
16.000
|
$150.000
|
$200.000
|
$278.150
|
$197.000
|
|
|
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
|
GAL
|
7,382.000
|
$3.250
|
$5.000
|
$6.140
|
$4.400
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
2,771.000
|
$75.000
|
$100.000
|
$147.250
|
$105.000
|
|
|
D-GR HMA TY-D SAC-B PG70-22
|
TON
|
2,517.000
|
$75.000
|
$100.000
|
$147.250
|
$105.000
|
|
|
PLANE ASPH CONC PAV(0" TO 4")
|
SY
|
1,026.000
|
$4.000
|
$12.000
|
$7.220
|
$17.000
|
|
|
CEM STABIL BKFL
|
CY
|
113.000
|
$150.000
|
$125.000
|
$181.190
|
$95.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,630.000
|
$16.000
|
$24.000
|
$21.660
|
$40.000
|
|
|
TEMPORARY SPL SHORING (COFFERDAM)
|
SF
|
6,768.000
|
$35.000
|
$55.000
|
$125.000
|
$315.000
|
|
|
PRESTR CONC PIL (18 IN SQ)
|
LF
|
12,644.000
|
$80.000
|
$90.000
|
$130.000
|
$150.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
624.000
|
$140.000
|
$250.000
|
$366.500
|
$260.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
190.000
|
$170.000
|
$300.000
|
$428.210
|
$525.000
|
|
|
CL C CONC (ABUT)
|
CY
|
59.000
|
$850.000
|
$1,000.000
|
$1,500.000
|
$950.000
|
|
|
CL C CONC (BENT)
|
CY
|
1,172.900
|
$700.000
|
$950.000
|
$1,500.000
|
$800.000
|
|
|
CL C CONC (BENT)(MASS)
|
CY
|
81.600
|
$1,000.000
|
$1,100.000
|
$1,500.000
|
$900.000
|
|
|
CL C CONC (MISC)
|
CY
|
73.000
|
$800.000
|
$950.000
|
$1,500.000
|
$470.000
|
|
|
REINF CONC SLAB
|
SF
|
62,040.000
|
$15.500
|
$18.000
|
$20.470
|
$20.000
|
|
|
PRESTR CONC GIRDER (TX40)
|
LF
|
5,460.000
|
$130.000
|
$150.000
|
$170.060
|
$165.000
|
|
|
PRESTR CONC GIRDER (TX70)
|
LF
|
2,601.120
|
$150.000
|
$250.000
|
$165.790
|
$260.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
2.400
|
$500.000
|
$800.000
|
$695.880
|
$500.000
|
|
|
RIPRAP (CONC)(CL B)(5 IN)
|
CY
|
111.000
|
$450.000
|
$500.000
|
$428.480
|
$550.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
38.000
|
$400.000
|
$500.000
|
$452.110
|
$730.000
|
|
|
RAIL (TY SSTR)
|
LF
|
2,740.000
|
$55.000
|
$80.000
|
$76.420
|
$90.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
|
LF
|
407.000
|
$80.000
|
$100.000
|
$91.480
|
$70.000
|
|
|
CONC BOX CULV (3 FT X 3 FT)
|
LF
|
20.000
|
$500.000
|
$300.000
|
$700.000
|
$680.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
72.000
|
$65.000
|
$65.000
|
$135.050
|
$85.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
192.000
|
$125.000
|
$130.000
|
$156.810
|
$93.000
|
|
|
WINGWALL (FW - S) (HW=6 FT)
|
EA
|
1.000
|
$10,000.000
|
$5,000.000
|
$13,435.010
|
$10,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
6.000
|
$1,200.000
|
$1,500.000
|
$1,485.060
|
$2,500.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$2,500.000
|
$2,500.000
|
$3,319.630
|
$3,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
130.000
|
$10.000
|
$25.000
|
$29.340
|
$100.000
|
|
|
REMOV STR (BRIDGE 1000 FT OR GREATER)
|
EA
|
1.000
|
$500,000.000
|
$590,000.000
|
$750,000.000
|
$475,000.000
|
|
|
REMOV STR (RET WALL)
|
LF
|
45.000
|
$100.000
|
$250.000
|
$80.420
|
$95.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$700,000.000
|
$1,000,000.000
|
$1,350,000.000
|
$1,400,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
26.000
|
$2,500.000
|
$2,000.000
|
$5,000.000
|
$2,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
267.000
|
$30.000
|
$32.000
|
$30.100
|
$35.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
267.000
|
$8.000
|
$12.000
|
$10.640
|
$12.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
8,575.000
|
$2.000
|
$2.000
|
$1.820
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
8,575.000
|
$0.500
|
$0.500
|
$0.380
|
$2.000
|
|
|
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
|
LF
|
3,450.000
|
$50.000
|
$65.000
|
$50.000
|
$91.000
|
|
|
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
|
LF
|
810.000
|
$10.000
|
$10.000
|
$12.590
|
$15.000
|
|
|
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
|
LF
|
3,450.000
|
$20.000
|
$10.000
|
$11.830
|
$14.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
634.000
|
$30.000
|
$35.000
|
$31.140
|
$30.000
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
665.000
|
$12.000
|
$45.000
|
$27.810
|
$30.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
6,300.000
|
$0.500
|
$1.000
|
$0.620
|
$1.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
325.000
|
$25.000
|
$25.000
|
$21.100
|
$24.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
6.000
|
$1,400.000
|
$1,600.000
|
$1,448.000
|
$2,400.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
722.000
|
$1.000
|
$2.000
|
$1.500
|
$1.750
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
2.000
|
$200.000
|
$200.000
|
$125.000
|
$225.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$2,200.000
|
$3,000.000
|
$2,745.000
|
$3,100.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$250.000
|
$150.000
|
$125.000
|
$225.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
6.000
|
$1,200.000
|
$1,500.000
|
$1,200.000
|
$1,300.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
6.000
|
$800.000
|
$800.000
|
$650.000
|
$900.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
6.000
|
$8,500.000
|
$9,000.000
|
$7,000.000
|
$10,000.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
4.000
|
$500.000
|
$800.000
|
$689.520
|
$800.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
4.000
|
$250.000
|
$120.000
|
$100.000
|
$110.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
54.000
|
$15.000
|
$12.000
|
$10.000
|
$25.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
2.000
|
$85.000
|
$55.000
|
$43.950
|
$75.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
4.000
|
$20.000
|
$30.000
|
$25.000
|
$30.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
14.000
|
$25.000
|
$15.000
|
$13.950
|
$34.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
84.000
|
$8.000
|
$3.500
|
$5.000
|
$5.500
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
6,552.000
|
$1.000
|
$0.900
|
$0.700
|
$1.400
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
6,552.000
|
$1.000
|
$0.900
|
$0.700
|
$1.400
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
655.000
|
$2.000
|
$2.200
|
$2.000
|
$1.200
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
655.000
|
$2.000
|
$2.200
|
$2.000
|
$1.200
|
|
|
PAVEMENT SEALER 4"
|
LF
|
3,038.000
|
$0.500
|
$2.000
|
$0.350
|
$0.600
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
9,252.000
|
$0.750
|
$1.200
|
$0.800
|
$0.650
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
1,160.000
|
$0.750
|
$1.500
|
$0.800
|
$0.650
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
526.000
|
$0.750
|
$2.000
|
$0.800
|
$0.650
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
59.000
|
$15.000
|
$8.000
|
$6.000
|
$5.600
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
7,902.000
|
$0.100
|
$0.400
|
$0.200
|
$0.250
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$8,000.000
|
$25,000.000
|
$14,056.500
|
$20,000.000
|
|
|
TMA (STATIONARY)
|
EA
|
2.000
|
$10,000.000
|
$20,000.000
|
$35,141.250
|
$6,000.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
4.000
|
$500.000
|
$500.000
|
$773.540
|
$275.000
|
|
Totals: |
$8,043,816.700
|
$10,990,759.480
|
$14,017,708.377
|
$14,184,244.500
|