Bid Cobra

COLLINGSWORTH US 83 (0031-03-048)

Items: 50

County: COLLINGSWORTH
Length: 0.0000 MILES
Highway: US 83
District: CHILDRESS
Control Number: 0031-03-048
DBE Goal: 0.0%
Project: BR 2026(558)
Guaranty: $50,000.00
Time: 100 WORKING DAYS
Engineer's Estimate: $2,507,551.66
Date: 05/06/2026 (5 weeks ago)
Contract Number: 5263025
Type: BRIDGE MAINTENANCE
Project ID: A00211596
Contract Type: Federal
Project Description: BRIDGE MAINTENANCE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
LOUIS MCDOW III
JORDAN BAKER
JARED GROVES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (13)
E
Engineer's Estimate
$2,507,551.66
Over/Under Est: -4.43% -$111,026.11
Over/Under Est: 13.54% $339,621.88
Amt Left: 18.8% $450,647.99
Over/Under Est: 14.37% $360,315.34
Amt Left: 19.67% $471,341.45
Delta: -0.73% -$20,693.46
$2,888,242.20
Over/Under Est: 15.18% $380,690.54
Amt Left: 20.52% $491,716.65
Delta: -0.71% -$20,375.20
Over/Under Est: 15.44% $387,193.29
Amt Left: 20.79% $498,219.40
Delta: -0.23% -$6,502.75
Over/Under Est: 15.52% $389,139.18
Amt Left: 20.87% $500,165.29
Delta: -0.07% -$1,945.89
$2,994,452.36
Over/Under Est: 19.42% $486,900.70
Amt Left: 24.95% $597,926.81
Delta: -3.37% -$97,761.52
$2,999,453.12
Over/Under Est: 19.62% $491,901.46
Amt Left: 25.16% $602,927.57
Delta: -0.17% -$5,000.76
$3,165,946.95
Over/Under Est: 26.26% $658,395.29
Amt Left: 32.11% $769,421.40
Delta: -5.55% -$166,493.83
Over/Under Est: 29.35% $735,931.29
Amt Left: 35.34% $846,957.40
Delta: -2.45% -$77,536.00
Over/Under Est: 35.37% $886,954.64
Amt Left: 41.64% $997,980.75
Delta: -4.66% -$151,023.35
Over/Under Est: 35.73% $895,850.34
Amt Left: 42.01% $1,006,876.45
Delta: -0.26% -$8,895.70
$4,486,085.80
Over/Under Est: 78.9% $1,978,534.14
Amt Left: 87.19% $2,089,560.25
Delta: -31.81% -$1,082,683.80

Bid Items & Bid Tabulations

50 Total 0 of 50
COLLINGSWORTH  |  US 83  |  CHILDRESS  |  0031-03-048  |  05/06/2026  |  $2,507,551.66  |  BR 2026(558)  |  BRIDGE MAINT  |  100 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
GIBSON & ASSOCIATES, INC.
THE TRUESDELL CORPORATION
ICOS MANAGEMENT, LLC
BLACKSMITH VENTURES LLC
MYERS & SONS CONSTRUCTION LLC
TI-ZACK CONCRETE, LLC
MPB, INC.
GILVIN-TERRILL, LTD.
RAGLE CONSTRUCTION, INC.
PATHFIELD INVESTMENTS LLC
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
EARTH BUILDERS, L.P.
REMOV CONC (MOWSTRIP)
SY 2,067.000 $13.790 $5.000 $24.200 $25.000 $11.000 $2.000 $15.000 $11.900 $6.000 $20.000 $13.000 $18.000 $8.000 $40.000
EMBANK (FNL)(OC)(TY B)
CY 522.000 $34.420 $40.000 $85.800 $35.000 $43.000 $28.000 $130.000 $41.650 $90.000 $60.000 $70.000 $80.000 $86.000 $55.000
PLANE & TEXT ASPH CONC PAV(2")
SY 3,920.000 $2.030 $18.000 $9.780 $7.000 $9.000 $10.000 $6.490 $10.710 $6.000 $10.000 $20.000 $9.700 $12.000 $30.000
FLOWABLE BACKFILL
CY 160.000 $650.000 $300.000 $324.500 $437.000 $294.000 $375.000 $400.000 $416.500 $385.000 $500.000 $380.000 $490.000 $434.000 $500.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 767.000 $18.250 $10.000 $22.770 $29.000 $27.000 $8.000 $23.000 $101.150 $38.000 $25.000 $21.000 $28.000 $37.000 $20.000
CONC STR REPAIR (EPOXY MORTAR)
SF 250.000 $200.000 $100.000 $150.000 $155.000 $128.000 $75.000 $70.000 $101.150 $65.000 $220.000 $100.000 $205.000 $254.000 $350.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 425.000 $150.000 $325.000 $75.000 $220.000 $190.000 $225.000 $111.130 $113.050 $130.000 $220.000 $125.000 $255.000 $188.000 $600.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 680.000 $138.000 $225.000 $255.000 $155.000 $107.000 $109.000 $102.460 $101.150 $80.000 $220.000 $150.000 $230.000 $184.000 $350.000
RIPRAP (MOW STRIP)(4 IN)
CY 92.000 $870.000 $400.000 $770.000 $750.000 $642.000 $429.000 $805.000 $535.500 $1,100.000 $850.000 $676.000 $1,200.000 $1,186.000 $850.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 204.000 $370.000 $200.000 $330.000 $210.000 $204.000 $258.000 $649.000 $184.450 $300.000 $500.000 $241.000 $210.000 $241.000 $360.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 1,177.000 $58.000 $30.000 $50.000 $65.000 $54.000 $42.000 $80.000 $29.750 $35.000 $30.000 $39.000 $75.000 $33.000 $90.000
MULTI-LAYER POLYMER OVERLAY
SY 4,620.000 $47.000 $37.000 $33.000 $28.500 $54.000 $60.000 $60.000 $53.550 $47.000 $34.000 $40.000 $108.000 $47.000 $60.000
POLYESTER POLYMER CONC OVERLAY (2")
SY 3,920.000 $140.000 $160.000 $204.000 $225.000 $224.000 $237.750 $270.000 $267.750 $236.000 $217.950 $200.000 $255.000 $282.000 $330.000
RETROFIT RAIL (TY SSTR)
LF 1,906.000 $190.000 $115.000 $174.900 $150.000 $235.000 $226.000 $180.500 $152.320 $130.000 $175.000 $131.000 $190.000 $195.000 $300.000
SHOT BLASTING
SY 4,620.000 $6.000 $2.000 $3.000 $4.000 $16.000 $15.850 $9.000 $14.280 $9.500 $5.500 $5.000 $10.700 $5.000 $8.000
MOBILIZATION
LS 1.000 $200,000.000 $75,000.000 $310,000.000 $355,272.250 $94,000.000 $250,000.000 $200,000.000 $41,650.000 $197,000.000 $318,000.000 $300,000.000 $200,000.000 $340,000.000 $450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $2,000.000 $2,200.000 $15,500.000 $2,000.000 $1.000 $3,000.000 $7,625.000 $7,140.000 $3,000.000 $27,000.000 $80,750.000 $10,000.000 $8,780.000 $6,500.000
TMA (STATIONARY)
DAY 4.000 $235.000 $300.000 $900.000 $750.000 $535.000 $5,000.000 $216.150 $3,570.000 $150.000 $1,500.000 $1,000.000 $150.000 $528.000 $300.000
TMA (MOBILE OPERATION)
DAY 1.000 $60.000 $300.000 $900.000 $550.000 $856.000 $10,000.000 $6,495.000 $4,165.000 $150.000 $1,500.000 $1,000.000 $1,000.000 $578.000 $650.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 1.000 $11,000.000 $8,500.000 $8,900.000 $7,500.000 $16,050.000 $8,500.000 $7,780.470 $20,230.000 $8,850.000 $6,000.000 $15,000.000 $8,000.000 $6,791.000 $8,000.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 2,970.000 $63.000 $100.000 $50.000 $63.000 $86.000 $51.000 $25.000 $65.450 $125.000 $70.000 $80.000 $40.000 $63.000 $70.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 2,970.000 $9.000 $15.000 $5.000 $10.500 $16.000 $5.000 $5.000 $23.800 $10.000 $15.000 $15.000 $7.000 $13.000 $20.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 2,970.000 $14.000 $30.000 $15.000 $26.000 $16.000 $8.400 $2.800 $41.650 $50.000 $35.000 $32.000 $11.000 $28.000 $20.000
MTL W-BEAM GD FEN (STEEL POST)
LF 650.000 $37.000 $35.000 $49.500 $38.000 $35.000 $35.000 $36.500 $65.450 $35.000 $33.000 $29.500 $35.000 $39.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,500.000 $2,500.000 $3,300.000 $2,800.000 $2,675.000 $2,100.000 $2,705.000 $4,165.000 $2,775.000 $2,400.000 $2,125.000 $2,000.000 $3,277.000 $2,500.000
REMOVE METAL BEAM GUARD FENCE
LF 670.000 $3.000 $3.000 $5.500 $3.200 $4.000 $0.250 $3.000 $24.990 $2.500 $4.000 $2.000 $3.000 $6.000 $6.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $290.000 $300.000 $550.000 $500.000 $428.000 $0.250 $220.000 $2,975.000 $250.000 $400.000 $200.000 $250.000 $400.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,480.000 $3,500.000 $4,070.000 $3,800.000 $3,500.000 $3,250.000 $3,550.000 $6,545.000 $3,600.000 $3,250.000 $3,300.000 $3,000.000 $3,733.000 $3,700.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $330.000 $300.000 $550.000 $400.000 $428.000 $0.250 $330.000 $1,428.000 $500.000 $400.000 $200.000 $300.000 $529.000 $300.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 3.000 $2,200.000 $3,000.000 $2,200.000 $1,800.000 $4,280.000 $3,000.000 $1,665.000 $5,950.000 $700.000 $2,000.000 $1,100.000 $1,400.000 $2,458.000 $3,000.000
CRASH CUSH ATTEN (REMOVE)
EA 3.000 $2,200.000 $1,300.000 $1,650.000 $900.000 $2,140.000 $1,000.000 $810.000 $3,570.000 $350.000 $2,000.000 $1,100.000 $900.000 $1,958.000 $1,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 3.000 $11,000.000 $11,000.000 $10,450.000 $9,800.000 $8,560.000 $9,000.000 $9,200.000 $5,355.000 $11,750.000 $5,500.000 $25,000.000 $7,200.000 $10,988.000 $14,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 29.000 $36.000 $25.000 $33.000 $25.000 $32.000 $7.000 $24.000 $53.550 $30.000 $24.000 $18.000 $50.000 $24.000 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 14.000 $40.000 $35.000 $38.500 $32.000 $32.000 $7.000 $30.000 $26.180 $30.000 $29.000 $25.000 $38.000 $29.000 $35.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BI)
EA 24.000 $25.000 $35.000 $33.000 $26.000 $32.000 $7.000 $24.000 $27.370 $30.000 $24.000 $25.000 $30.000 $24.000 $35.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2(BI)
EA 3.000 $30.800 $35.000 $38.500 $32.000 $32.000 $100.000 $30.000 $29.750 $30.000 $29.000 $25.000 $450.000 $29.000 $35.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 70.000 $56.000 $25.000 $5.500 $20.000 $22.000 $0.250 $18.500 $22.610 $5.000 $18.000 $20.000 $23.000 $5.000 $25.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 6,798.000 $1.200 $2.250 $1.930 $2.350 $2.000 $1.750 $0.390 $2.082 $0.850 $1.750 $1.750 $1.800 $1.500 $2.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 84.000 $4.080 $17.000 $16.500 $16.000 $16.000 $15.000 $5.500 $17.850 $13.000 $15.000 $15.000 $15.000 $25.000 $25.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 7,517.000 $1.200 $2.000 $1.930 $2.300 $2.000 $1.750 $0.390 $2.082 $0.850 $1.750 $1.750 $2.000 $1.500 $2.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 1,374.000 $0.600 $2.250 $2.310 $2.300 $2.500 $2.100 $0.750 $2.499 $1.900 $2.100 $2.100 $2.600 $3.000 $2.500
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 5,073.000 $0.540 $2.250 $2.310 $2.300 $2.500 $2.100 $0.750 $2.499 $1.900 $2.100 $2.100 $2.600 $3.000 $2.500
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 240.000 $0.540 $2.250 $2.310 $2.300 $2.500 $2.100 $0.750 $2.499 $2.500 $2.100 $2.100 $3.000 $3.000 $2.500
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 10,729.000 $4.080 $2.250 $2.310 $2.300 $2.500 $2.100 $0.750 $2.499 $3.000 $2.100 $2.100 $3.000 $3.000 $2.500
REFL PAV MRKR TY II-A-A
EA 14.000 $4.300 $12.000 $11.000 $11.000 $12.000 $10.000 $3.950 $11.900 $13.000 $10.000 $10.000 $12.000 $50.000 $12.000
ELIM EXT PM & MRKS (4")
LF 14,315.000 $1.000 $1.150 $1.100 $1.050 $1.200 $1.000 $0.550 $1.190 $2.250 $1.000 $1.000 $1.300 $1.500 $1.200
ELIM EXT PM & MRKS (6")
LF 13,396.000 $0.410 $1.250 $1.210 $1.200 $1.200 $1.100 $0.550 $1.309 $3.000 $1.100 $1.100 $2.000 $1.500 $1.300
ELIM EXT PM & MRKS (24")
LF 84.000 $7.180 $3.250 $2.750 $1.200 $3.000 $2.500 $0.550 $2.975 $6.750 $2.500 $2.500 $2.900 $10.000 $14.000
PAV SURF PREP FOR MRK (6")
LF 8,126.000 $3.600 $1.300 $1.380 $1.300 $1.500 $1.250 $0.070 $1.487 $0.820 $1.250 $1.250 $1.600 $1.500 $1.500
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 290.000 $86.000 $50.000 $81.000 $69.000 $107.000 $75.000 $85.830 $8.330 $105.000 $50.000 $40.000 $103.000 $118.000 $200.000
Totals: $2,507,551.660 $2,396,525.550 $2,847,173.540 $2,867,867.000 $2,888,242.200 $2,894,744.950 $2,896,690.840 $2,994,452.360 $2,999,453.120 $3,165,946.950 $3,243,482.950 $3,394,506.300 $3,403,402.000 $4,486,085.800
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $373,000.00
Total: $374,000.00