Show Job Controls
Bid Cobra

COLLIN SH0078 (6486-31-001)

Items: 23

County: COLLIN
Length: 0.0100 MILES
Highway: SH0078
District: DALLAS
Control Number: 6486-31-001
DBE Goal: 0.0%
Project: RMC - A00216248
Guaranty: $6,000.00
Time: 34 WORKING DAYS
Engineer's Estimate: $640,676.08
Date: 10/15/2025 (7 months ago)
Contract Number: 10251801
Type: CULVERT EXTENSION & CROSS DRAINAGE
Project ID: A00216248
Project Description: CULVERT REPAIR
Mail/Deliver Bids To: N/A
JENNIFER VORSTER
DERICK DAVIS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$640,676.08
$444,180.20
Over/Under Est: -30.67% -$196,495.88
Over/Under Est: -30.63% -$196,231.91
Amt Left: 0.06% $263.97
Over/Under Est: -25.25% -$161,780.08
Amt Left: 7.82% $34,715.80
Delta: -7.75% -$34,451.83
Over/Under Est: -19.8% -$126,829.08
Amt Left: 15.68% $69,666.80
Delta: -7.30% -$34,951.00

Bid Items & Bid Tabulations

23 Total 0 of 23
COLLIN  |  SH0078  |  DALLAS  |  6486-31-001  |  10/15/2025  |  $640,676.08  |  RMC - A00216248  |  CULVERT EXTENSION & CROSS DRAINAGE  |  34 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
RISE UP CONSTRUCTION LLC
ED BELL CONSTRUCTION COMPANY
HIGHWAY 19 CONSTRUCTION LLC
PREPARING ROW
STA 1.780 $7,573.990 $10,000.000 $5,000.000 $16,000.000 $5,000.000
DRILL SEED (PERM_RURAL_CLAY)
SY 2,001.000 $2.000 $0.200 $15.000 $12.000 $5.000
VEGETATIVE WATERING
TGL 303.000 $10.000 $10.000 $100.000 $1.000 $10.000
CUT & RESTORING PAV
SY 21.000 $245.000 $200.000 $200.000 $400.000 $350.000
CEM STABIL BKFL
CY 39.000 $250.000 $300.000 $450.000 $350.000 $350.000
TEMPORARY SPL SHORING
SF 496.000 $22.500 $80.000 $39.000 $1.000 $55.000
RC PIPE (CL III)(30 IN)
LF 88.000 $138.900 $300.000 $175.000 $333.000 $1,600.000
HEADWALL (CH - PW - S) (DIA= 30 IN)
EA 1.000 $11,000.000 $25,000.000 $15,000.000 $25,000.000 $9,000.000
REMOV STR (PIPE)
LF 88.000 $53.130 $50.000 $75.000 $60.000 $50.000
MOBILIZATION
LS 1.000 $54,011.300 $40,000.000 $45,500.000 $45,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $2,500.000 $10,000.000 $1,959.000 $31,500.000 $10,000.000
TMA (STATIONARY)
DAY 68.000 $400.000 $300.000 $400.000 $100.000 $250.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 20.000 $84.330 $20.000 $44.000 $100.000 $85.000
ROCK FILTER DAMS (REMOVE)
LF 20.000 $34.000 $10.000 $1.000 $50.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 520.000 $7.500 $5.000 $7.000 $6.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 520.000 $4.500 $1.000 $1.000 $3.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 250.000 $4.630 $8.000 $9.000 $10.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 250.000 $1.600 $1.000 $1.000 $5.000 $1.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 4)
LF 380.000 $40.000 $80.000 $300.000 $40.000 $100.000
PORT CTB (REMOVE)(F-SHAPE)(TY 4)
LF 380.000 $20.000 $20.000 $75.000 $20.000 $25.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $2,566.670 $500.000 $1.000 $800.000 $2,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $13,200.000 $10,000.000 $9,022.000 $9,000.000 $9,500.000
SLIP LINING CULVERT PIPE 30"
LF 277.000 $1,500.000 $600.000 $189.210 $633.000 $266.000
Totals: $640,676.082 $444,180.200 $444,444.170 $478,896.000 $513,847.000