COLLIN US0075 (6478-72-001)

Items: 28

County: COLLIN
Length: 0.0000 MILES
Highway: US0075
District: DALLAS
Control Number: 6478-72-001
DBE Goal: N/A
Project: RMC - A00213486
Guaranty: $26,000.00
Time: 180 CALENDAR DAYS
Engineer's Estimate: $986,583.33
Date: 05/07/2025 (1 year ago)
Contract Number: 5251804
Type: METAL BEAM GUARD FENCE REPAIR
Project ID: A00213486
Project Description: GUARD FENCE REPAIR
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
4777 E HWY 80, MESQUITE, TX 75150
JENNIFER VORSTER
DERICK DAVIS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$986,583.33
$596,312.00
Over/Under Est: -39.56% -$390,271.33
Over/Under Est: -38.04% -$375,265.33
Amt Left: 2.52% $15,006.00
Over/Under Est: -22.74% -$224,338.33
Amt Left: 27.83% $165,933.00
Delta: -24.69% -$150,927.00
Over/Under Est: 19.45% $191,878.67
Amt Left: 97.63% $582,150.00
Delta: -54.60% -$416,217.00

Bid Items & Bid Tabulations

28 Total 0 of 28
COLLIN  |  US0075  |  DALLAS  |  6478-72-001  |  05/07/2025  |  $986,583.33  |  RMC - A00213486  |  METAL BEAM GUARD FENCE REPAIR  |  180 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FIREMAN EXCAVATING, INC.
BK FIELD OPERATIONS LLC
MARCOM'S MOWING SERVICE, LLC
SOUTHERN CROSS CONTRACTORS, LLC
MOBILIZATION (CALLOUT)
EA 200.000 $1,000.000 $500.000 $1.000 $1.000 $800.000
MOBILIZATION (EMERGENCY)
EA 1.000 $2,000.000 $5,000.000 $500.000 $4,000.000 $3,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 6.000 $185.000 $1.000 $1.000 $200.000 $495.000
TMA (STATIONARY)
DAY 200.000 $400.000 $1.000 $1.000 $1.000 $200.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $1,000.000 $2,000.000 $1,400.000 $900.000 $975.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 38.000 $38.320 $50.000 $10.000 $60.000 $90.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 38.000 $44.090 $1.000 $10.000 $30.000 $90.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 19.000 $32.640 $50.000 $1.000 $30.000 $90.000
REPLACE RAIL ELEMENT (W-BEAM)
LF 3,500.000 $20.350 $115.000 $65.000 $32.840 $69.000
REPLACE RAIL ELEMENT (THRIE-BEAM)
LF 8.000 $37.780 $500.000 $100.000 $60.000 $60.000
REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM)
EA 8.000 $43.580 $500.000 $100.000 $600.000 $400.000
REPLACE SHORT RADIUS SYS (TL-3)
EA 9.000 $45.000 $200.000 $100.000 $20,000.000 $20,000.000
REPLACE TIMBER POST W/O CONC FND
EA 320.000 $43.600 $1.000 $1.000 $25.000 $45.000
REPLACE STEEL POST W/O CONC FND
EA 100.000 $53.730 $50.000 $30.000 $90.000 $155.000
REALIGN POSTS
EA 600.000 $62.740 $1.000 $10.000 $15.000 $45.000
REM OBSOLETE GET & REPL W/ SGT
EA 113.000 $4,041.260 $400.000 $3,000.000 $3,280.000 $3,750.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 8.000 $1,000.000 $200.000 $500.000 $600.000 $1,295.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 12.000 $40.000 $50.000 $100.000 $100.000 $100.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 12.000 $101.240 $20.000 $200.000 $200.000 $100.000
REPLACE BLOCKOUT
EA 788.000 $100.000 $1.000 $1.000 $20.000 $24.000
REPAIR STEEL POST WITH BASE PLATE
EA 5.000 $100.000 $20.000 $1.000 $500.000 $350.000
RESET SGT IMPACT HEAD
EA 5.000 $249.950 $20.000 $250.000 $1.000 $300.000
REPLACE SGT OBJECT MARKER
EA 35.000 $43.490 $10.000 $1.000 $20.000 $40.000
REPLACE SGT CABLE ANCHOR
EA 5.000 $72.810 $100.000 $1.000 $150.000 $78.000
REPLACE SGT CABLE ASSEMBLY
EA 5.000 $132.500 $100.000 $1.000 $150.000 $99.000
REPLACE SGT STRUT
EA 5.000 $300.000 $100.000 $1.000 $150.000 $70.000
REPLACE DOWNSTREAM ANCHOR TERMINAL
EA 10.000 $1,250.000 $1,000.000 $800.000 $1,400.000 $1,250.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 188.000 $32.000 $40.000 $65.000 $60.000 $35.000
Totals: $986,583.330 $596,312.000 $611,318.000 $762,245.000 $1,178,462.000