COLLIN US0075 (6460-92-001)

Items: 12

County: COLLIN
Length: N/A
Highway: US0075
District: DALLAS
Control Number: 6460-92-001
DBE Goal: 0.0%
Project: RMC - 646092001
Guaranty: N/A
Time: 70 W
Engineer's Estimate: $818,082.61
Date: 06/06/2024 (2 years ago) Changed
Contract Number: N/A
Type: FULL DEPTH CONCRETE REPAIR
Mail/Deliver Bids To: N/A
JENNIFER VORSTER
DERICK DAVIS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$818,082.61
$650,985.00
Over/Under Est: -20.43% -$167,097.61
Over/Under Est: -18.9% -$154,582.61
Amt Left: 1.92% $12,515.00
Over/Under Est: -3.22% -$26,327.61
Amt Left: 21.62% $140,770.00
Delta: -19.33% -$128,255.00
$849,450.00
Over/Under Est: 3.83% $31,367.39
Amt Left: 30.49% $198,465.00
Delta: -7.29% -$57,695.00
$1,068,750.00
Over/Under Est: 30.64% $250,667.39
Amt Left: 64.17% $417,765.00
Delta: -25.82% -$219,300.00
Over/Under Est: 51.55% $421,737.39
Amt Left: 90.45% $588,835.00
Delta: -16.01% -$171,070.00

Bid Items & Bid Tabulations

12 Total 0 of 12
COLLIN  |  US0075  |  DALLAS  |  6460-92-001  |  06/06/2024  |  $818,082.61  |  RMC - 646092001  |  FULL DEPTH CONC REPAIR  |  70 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
O. TREVINO CONSTRUCTION, LLC
GARRET SHIELDS INFRASTRUCTURE
ICOS MANAGEMENT, LLC
STX CIVIL
FNH CONSTRUCTION, LLC
ROY JORGENSEN ASSOCIATES, INC.
REMOVING CONC (CURB)
LF 300.000 $20.000 $13.000 $30.000 $32.000 $30.000 $30.000 $15.000
REMOVING CONC (CURB AND GUTTER)
LF 150.000 $25.000 $18.000 $30.000 $43.000 $30.000 $30.000 $25.000
FULL-DEPTH REPAIR CPCD (11"-13")
SY 100.000 $432.000 $486.500 $350.000 $428.000 $410.000 $650.000 $650.000
FULL DEPTH REPAIR CPCD (8"-10"
SY 1,600.000 $330.000 $275.000 $300.000 $334.000 $395.000 $450.000 $625.000
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 50.000 $148.000 $200.000 $200.000 $428.000 $230.000 $500.000 $180.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 50.000 $277.000 $225.000 $300.000 $535.000 $320.000 $400.000 $250.000
MOBILIZATION
LS 1.000 $67,548.110 $62,000.000 $40,000.000 $65,000.000 $67,000.000 $100,000.000 $70,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $4,000.000 $3,677.000 $5,000.000 $1.000 $3,500.000 $15,000.000 $8,000.000
CONC CURB (TY II)
LF 300.000 $253.670 $65.000 $40.000 $54.000 $45.000 $55.000 $50.000
CONC CURB & GUTTER (TY II)
LF 150.000 $92.670 $80.000 $40.000 $86.000 $60.000 $75.000 $80.000
SPALLING REPAIR (POLYMERIC) (SEMIRIGID)
GAL 100.000 $103.330 $100.000 $60.000 $370.000 $85.000 $50.000 $80.000
TMA (STATIONARY)
DAY 70.000 $400.000 $180.000 $300.000 $275.000 $285.000 $250.000 $1.000
Totals: $818,082.610 $650,985.000 $663,500.000 $791,755.000 $849,450.000 $1,068,750.000 $1,239,820.000