COLLIN US0380 (6433-60-001)

Items: 32

County: COLLIN
Length: N/A
Highway: US0380
District: DALLAS
Control Number: 6433-60-001
DBE Goal: N/A
Project: RMC - 643360001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $463,794.52
Date: 05/05/2023 (3 years ago)
Contract Number: N/A
Type: SPECIALTY MARKINGS
Mail/Deliver Bids To: N/A
JENNIFER VORSTER
DERICK DAVIS
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$463,794.52
$329,329.29
Over/Under Est: -28.99% -$134,465.23
Over/Under Est: 6.56% $30,416.43
Amt Left: 50.07% $164,881.66
Over/Under Est: 38.22% $177,259.78
Amt Left: 94.65% $311,725.01
Delta: -29.71% -$146,843.35

Bid Items & Bid Tabulations

32 Total 0 of 32
COLLIN  |  US0380  |  DALLAS  |  6433-60-001  |  05/05/2023  |  $463,794.52  |  RMC - 643360001  |  SPECIALTY MRK  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPE-A-ZONE, LLC
TRAFFIC HIGHWAY MAINTENANCE, LLC
TRP CONSTRUCTION GROUP, LLC
MOBILIZATION
LS 1.000 $38,295.000 $5,102.540 $40,000.000 $10,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,200.000 $1,500.000 $15,000.000 $500.000
REFL PAV MRK TY I (W)4"(DOT)(060MIL)
LF 1,910.000 $3.790 $2.500 $2.430 $3.050
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 8,945.000 $4.160 $4.550 $4.770 $8.700
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 3,245.000 $20.000 $7.350 $8.970 $15.500
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 272.000 $185.350 $120.000 $187.000 $306.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 16.000 $116.120 $210.000 $327.000 $436.000
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 22.000 $115.420 $320.000 $397.000 $446.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 275.000 $200.000 $135.000 $211.000 $368.000
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 86.000 $10.910 $45.000 $71.000 $131.000
PAVEMENT SEALER 12"
LF 8,945.000 $1.320 $2.000 $1.530 $1.800
PAVEMENT SEALER 24"
LF 3,245.000 $2.320 $3.000 $3.430 $3.250
PAVEMENT SEALER (ARROW)
EA 272.000 $64.530 $60.000 $63.000 $62.000
PAVEMENT SEALER (WORD)
EA 275.000 $85.720 $60.000 $67.000 $75.000
PAVEMENT SEALER (DBL ARROW)
EA 16.000 $41.470 $60.000 $93.000 $89.000
PAVEMENT SEALER (UTURN ARROW)
EA 22.000 $41.510 $60.000 $111.000 $91.000
PAVEMENT SEALER (YLD TRI)
EA 86.000 $11.750 $10.000 $43.000 $26.000
ELIM EXT PAV MRK & MRKS (12")
LF 8,945.000 $2.190 $3.000 $2.750 $3.850
ELIM EXT PAV MRK & MRKS (24")
LF 3,245.000 $3.830 $4.000 $5.500 $7.650
ELIM EXT PAV MRK & MRKS (ARROW)
EA 272.000 $42.080 $70.000 $67.000 $91.000
ELIM EXT PAV MRK & MRKS (DBL ARROW)
EA 16.000 $51.970 $100.000 $131.000 $127.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 275.000 $79.690 $70.000 $85.000 $106.000
ELIM EXT PAV MRK & MRKS (18")(YLD TRI)
EA 86.000 $17.010 $20.000 $40.000 $55.000
ELIM EXT PAV MRK & MRKS (UTURN ARROW)
EA 22.000 $49.110 $100.000 $157.000 $239.000
PAV SURF PREP FOR MRK (12")
LF 8,945.000 $0.460 $0.500 $0.010 $0.640
PAV SURF PREP FOR MRK (24")
LF 3,245.000 $0.780 $0.750 $0.010 $1.150
PAV SURF PREP FOR MRK (ARROW)
EA 272.000 $20.000 $20.000 $1.000 $27.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 16.000 $7.170 $20.000 $1.000 $38.000
PAV SURF PREP FOR MRK (UTURN ARR)
EA 22.000 $4.940 $20.000 $1.000 $38.000
PAV SURF PREP FOR MRK (WORD)
EA 275.000 $22.510 $20.000 $1.000 $32.000
PAV SURF PREP FOR MRK (18")(YLD TRI)
EA 86.000 $5.790 $5.000 $1.000 $12.750
TMA (STATIONARY)
DAY 120.000 $400.000 $1.000 $350.000 $500.000
Totals: $463,794.520 $329,329.290 $494,210.950 $641,054.300