COLLIN FM 3133 (3236-02-012)
Items: 94
County: COLLIN
Length: N/A
Highway: FM 3133
District: DALLAS
Control Number: 3236-02-012
DBE Goal: N/A
Project: STP 2021(220)HES
Guaranty: N/A
Time: 369 WORKING DAYS
Engineer's Estimate: $7,303,416.19
Date: 02/05/2021 (5 years ago)
Contract Number: N/A
Type: RESTORE EXSISTING PAVEMT, ADD SHOULDERS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$7,303,416.19 | |||
| $5,929,503.18 |
-18.81%
-$1,373,913.01
|
|||
| $6,059,155.28 |
-17.04%
-$1,244,260.91
|
2.19%
$129,652.10
|
||
| $6,464,362.52 |
-11.49%
-$839,053.67
|
9.02%
$534,859.34
|
-6.69%
-$405,207.24
|
|
| $6,726,234.11 |
-7.9%
-$577,182.08
|
13.44%
$796,730.93
|
-4.05%
-$261,871.59
|
|
| $6,903,214.89 |
-5.48%
-$400,201.30
|
16.42%
$973,711.71
|
-2.63%
-$176,980.78
|
|
| $7,688,769.71 |
5.28%
$385,353.52
|
29.67%
$1,759,266.53
|
-11.38%
-$785,554.82
|
|
| $8,061,973.29 |
10.39%
$758,557.10
|
35.96%
$2,132,470.11
|
-4.85%
-$373,203.58
|
|
| $8,088,079.10 |
10.74%
$784,662.91
|
36.4%
$2,158,575.92
|
-0.32%
-$26,105.81
|
|
| $8,604,953.17 |
17.82%
$1,301,536.98
|
45.12%
$2,675,449.99
|
-6.39%
-$516,874.07
|
|
| $8,944,237.51 |
22.47%
$1,640,821.32
|
50.84%
$3,014,734.33
|
-3.94%
-$339,284.34
|
E
Engineer's Estimate
$7,303,416.19
1
Awarded
$5,929,503.18
Over/Under Est:
-18.81%
-$1,373,913.01
$6,059,155.28
Over/Under Est:
-17.04%
-$1,244,260.91
Amt Left:
2.19%
$129,652.10
$6,464,362.52
Over/Under Est:
-11.49%
-$839,053.67
Amt Left:
9.02%
$534,859.34
Delta:
-6.69%
-$405,207.24
$6,726,234.11
Over/Under Est:
-7.9%
-$577,182.08
Amt Left:
13.44%
$796,730.93
Delta:
-4.05%
-$261,871.59
$6,903,214.89
Over/Under Est:
-5.48%
-$400,201.30
Amt Left:
16.42%
$973,711.71
Delta:
-2.63%
-$176,980.78
$7,688,769.71
Over/Under Est:
5.28%
$385,353.52
Amt Left:
29.67%
$1,759,266.53
Delta:
-11.38%
-$785,554.82
$8,061,973.29
Over/Under Est:
10.39%
$758,557.10
Amt Left:
35.96%
$2,132,470.11
Delta:
-4.85%
-$373,203.58
$8,088,079.10
Over/Under Est:
10.74%
$784,662.91
Amt Left:
36.4%
$2,158,575.92
Delta:
-0.32%
-$26,105.81
$8,604,953.17
Over/Under Est:
17.82%
$1,301,536.98
Amt Left:
45.12%
$2,675,449.99
Delta:
-6.39%
-$516,874.07
$8,944,237.51
Over/Under Est:
22.47%
$1,640,821.32
Amt Left:
50.84%
$3,014,734.33
Delta:
-3.94%
-$339,284.34
Bid Items & Bid Tabulations
94
Total
0 of 94