Bid Cobra

COLLIN FM 3133 (3236-02-012)

Items: 94

County: COLLIN
Length: N/A
Highway: FM 3133
District: DALLAS
Control Number: 3236-02-012
DBE Goal: N/A
Project: STP 2021(220)HES
Guaranty: N/A
Time: 369 WORKING DAYS
Engineer's Estimate: $7,303,416.19
Date: 02/05/2021 (5 years ago)
Contract Number: N/A
Type: RESTORE EXSISTING PAVEMT, ADD SHOULDERS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (10)
E
Engineer's Estimate
$7,303,416.19
$5,929,503.18
Over/Under Est: -18.81% -$1,373,913.01
Over/Under Est: -17.04% -$1,244,260.91
Amt Left: 2.19% $129,652.10
Over/Under Est: -11.49% -$839,053.67
Amt Left: 9.02% $534,859.34
Delta: -6.69% -$405,207.24
$6,726,234.11
Over/Under Est: -7.9% -$577,182.08
Amt Left: 13.44% $796,730.93
Delta: -4.05% -$261,871.59
Over/Under Est: -5.48% -$400,201.30
Amt Left: 16.42% $973,711.71
Delta: -2.63% -$176,980.78
$7,688,769.71
Over/Under Est: 5.28% $385,353.52
Amt Left: 29.67% $1,759,266.53
Delta: -11.38% -$785,554.82
Over/Under Est: 10.39% $758,557.10
Amt Left: 35.96% $2,132,470.11
Delta: -4.85% -$373,203.58
Over/Under Est: 10.74% $784,662.91
Amt Left: 36.4% $2,158,575.92
Delta: -0.32% -$26,105.81
$8,604,953.17
Over/Under Est: 17.82% $1,301,536.98
Amt Left: 45.12% $2,675,449.99
Delta: -6.39% -$516,874.07
Over/Under Est: 22.47% $1,640,821.32
Amt Left: 50.84% $3,014,734.33
Delta: -3.94% -$339,284.34

Bid Items & Bid Tabulations

94 Total 0 of 94
COLLIN  |  FM 3133  |  DALLAS  |  3236-02-012  |  02/05/2021  |  $7,303,416.19  |  STP 2021(220)HES  |  RESTORE EXSISTING PAVEMT, ADD SHOULD...  |  369 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. K. GILLIS & SONS, LLC
ED BELL CONSTRUCTION COMPANY
HARRISON, WALKER AND HARPER, LLC
JAGOE-PUBLIC COMPANY
HIGHWAY 19 CONSTRUCTION LLC
A. L. HELMCAMP, INC.
TEXAS MATERIALS GROUP, INC.
TIERRA LEASE SERVICE, LLC
ALTUS CONSTRUCTION LLC
REYNOLDS ASPHALT & CONSTRUCTION COMPANY
PREPARING ROW
STA 255.110 $3,500.000 $472.870 $350.000 $162.650 $576.770 $250.000 $800.000 $2,300.000 $250.000 $1,993.950 $440.000
REMOVING CONC (PAV)
SY 1,500.000 $7.250 $4.000 $4.000 $1.000 $21.500 $35.000 $25.000 $18.000 $22.000 $4.960 $32.000
REMOVING CONC (DRIVEWAYS)
SY 2,059.000 $13.000 $14.000 $4.000 $11.350 $17.210 $15.000 $25.000 $19.000 $18.000 $15.040 $36.600
REMOV STAB BASE AND ASPH PAV (0"-12")
SY 4,573.000 $6.000 $3.000 $4.000 $5.850 $4.800 $5.000 $15.000 $9.630 $7.000 $7.620 $13.000
EXCAVATION (ROADWAY)
CY 233.000 $10.000 $30.080 $21.000 $25.300 $21.990 $25.000 $14.000 $20.268 $13.000 $11.430 $40.000
SUBGRADE WIDENING (ORD COMP)
STA 255.110 $375.000 $226.270 $210.000 $466.550 $289.980 $300.000 $290.000 $310.000 $300.000 $881.640 $1,370.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 7,334.100 $12.000 $11.940 $4.000 $11.750 $15.250 $11.000 $18.000 $20.000 $35.000 $8.840 $37.800
BACKFILL (TY A OR B)
STA 255.110 $200.000 $207.230 $210.000 $419.100 $265.620 $150.000 $200.000 $225.000 $125.000 $164.260 $240.000
BLADING
STA 255.110 $210.000 $207.230 $210.000 $137.550 $38.440 $150.000 $100.000 $198.120 $75.000 $132.960 $69.200
COMPOST MANUF TOPSOIL (4")
SY 183,915.000 $1.150 $0.500 $0.680 $1.100 $0.890 $1.500 $0.900 $1.000 $1.200 $0.900 $0.800
DRILL SEED (TEMP)(WARM OR COOL)
SY 183,915.000 $0.100 $0.080 $0.110 $0.100 $0.080 $0.090 $0.100 $0.096 $0.080 $0.150 $0.100
DRILL SEEDING (PERM)(WARM OR COOL)
SY 183,915.000 $0.300 $0.090 $0.170 $0.100 $0.100 $0.013 $0.140 $0.100 $0.080 $0.230 $0.150
VEGETATIVE WATERING
MG 54,720.000 $2.250 $0.470 $1.000 $1.500 $7.250 $1.000 $1.000 $0.010 $10.000 $1.840 $1.000
FL BS (CMP IN PLACE)(TY D GR 1-2)(11")
SY 83,693.000 $16.000 $15.830 $16.000 $15.000 $18.250 $24.000 $21.000 $17.000 $20.000 $22.590 $21.450
FL BS(RDWY DEL)(TY D GR 1-2)(FNAL POS)
CY 5,197.000 $48.000 $45.230 $40.000 $45.250 $39.500 $61.000 $72.000 $21.000 $55.000 $72.750 $70.900
REWORK BS MTL (TY C)(13"-15.5")(OC)
SY 56,692.000 $1.900 $2.090 $2.000 $3.350 $3.950 $3.600 $3.100 $1.950 $1.250 $3.990 $2.350
CEMENT
TON 440.000 $150.000 $137.000 $175.000 $139.350 $242.000 $135.000 $175.000 $157.926 $150.000 $180.080 $170.000
CEMENT TREAT (MX EXST MTL & NW BS) (6")
SY 85,038.000 $1.750 $1.560 $2.000 $2.440 $1.900 $2.760 $4.000 $2.000 $1.500 $1.790 $1.450
EMULS ASPH (PRIME)(MS-2 OR SS-1)
GAL 16,441.000 $4.650 $4.050 $4.500 $3.350 $5.460 $3.500 $3.000 $4.243 $3.250 $4.050 $3.900
ASPH (AC-20-5TR)
GAL 11,511.000 $2.750 $4.160 $3.320 $3.650 $3.520 $4.000 $3.500 $4.367 $3.750 $4.410 $4.000
ASPH (CRS-2P)
GAL 13,702.000 $4.500 $4.350 $3.380 $3.750 $3.580 $4.000 $3.000 $4.242 $4.000 $4.490 $4.250
ASPH (RC-250)
GAL 11,508.000 $4.000 $4.490 $3.700 $4.050 $3.920 $4.000 $3.000 $4.393 $4.500 $4.920 $4.350
AGGR(TY-PB GR-5 SAC-B)
CY 262.000 $95.000 $172.790 $136.000 $150.150 $144.200 $180.000 $100.000 $176.459 $225.000 $180.790 $344.000
AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B)
CY 524.000 $125.000 $129.040 $133.000 $146.850 $141.020 $153.000 $100.000 $179.482 $120.000 $176.800 $243.000
CEM STABIL BKFL
CY 756.100 $137.000 $200.000 $120.000 $248.350 $153.750 $180.000 $220.000 $120.373 $85.000 $107.670 $177.000
CUT & RESTORING PAV
SY 370.100 $140.000 $115.000 $120.000 $165.550 $58.830 $150.000 $125.000 $144.448 $100.000 $136.790 $130.000
TRENCH EXCAVATION PROTECTION
LF 594.400 $2.100 $15.000 $4.000 $16.550 $10.600 $10.000 $17.000 $14.445 $20.000 $3.830 $5.900
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 3.000 $140.000 $266.670 $525.000 $698.200 $636.190 $400.000 $275.000 $300.930 $800.000 $185.810 $253.000
RIPRAP (MOW STRIP)(4 IN)
CY 7.400 $575.000 $525.000 $800.000 $579.550 $636.190 $500.000 $575.000 $782.424 $450.000 $523.830 $863.000
RC PIPE (CL III)(15 IN)
LF 27.000 $87.000 $38.000 $50.000 $47.300 $42.410 $37.000 $45.000 $55.000 $60.000 $87.890 $105.000
RC PIPE (CL III)(18 IN)
LF 1,607.000 $50.000 $43.000 $55.000 $53.550 $49.830 $41.000 $47.000 $58.000 $61.500 $57.160 $148.350
RC PIPE (CL III)(24 IN)
LF 615.100 $70.000 $68.000 $65.000 $84.650 $66.800 $52.000 $75.000 $110.000 $78.000 $77.730 $172.000
RC PIPE (CL III)(30 IN)
LF 912.400 $100.000 $82.000 $95.000 $102.050 $90.130 $81.000 $90.000 $160.000 $76.000 $96.630 $205.000
RC PIPE (CL III)(36 IN)
LF 485.500 $125.000 $120.000 $125.000 $149.400 $132.540 $126.000 $130.000 $220.000 $100.000 $127.470 $360.000
RC PIPE (CL III)(42 IN)
LF 147.400 $155.000 $175.000 $200.000 $217.850 $190.860 $188.000 $190.000 $227.505 $120.000 $178.060 $300.000
RC PIPE (CL III)(48 IN)
LF 134.000 $195.000 $215.000 $225.000 $267.650 $238.570 $221.000 $235.000 $285.000 $140.000 $230.850 $341.000
HEADWALL (CH - PW - S) (DIA= 48 IN)
EA 2.000 $8,960.000 $11,000.000 $20,000.000 $12,142.550 $12,617.700 $12,000.000 $12,000.000 $13,241.040 $25,000.000 $19,939.530 $12,400.000
SET (TY II) (15 IN) (RCP) (6: 1) (P)
EA 2.000 $775.000 $600.000 $630.000 $662.300 $689.200 $600.000 $650.000 $842.610 $1,750.000 $718.620 $1,678.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 4.000 $850.000 $600.000 $630.000 $662.300 $561.970 $600.000 $650.000 $902.798 $1,700.000 $718.620 $1,650.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 110.000 $750.000 $650.000 $700.000 $717.500 $795.230 $664.000 $705.000 $932.891 $1,350.000 $808.450 $2,000.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 8.000 $1,100.000 $675.000 $700.000 $745.100 $689.200 $678.000 $730.000 $962.984 $1,550.000 $898.280 $1,884.000
SET (TY II) (24 IN) (RCP) (3: 1) (P)
EA 1.000 $2,300.000 $675.000 $700.000 $745.100 $689.200 $678.000 $730.000 $1,023.170 $2,000.000 $898.280 $1,884.000
SET (TY II) (24 IN) (RCP) (4: 1) (P)
EA 30.000 $1,250.000 $775.000 $800.000 $855.500 $763.420 $759.000 $850.000 $1,023.171 $2,000.000 $1,018.050 $2,235.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 8.000 $1,600.000 $1,100.000 $1,650.000 $1,214.250 $1,272.370 $916.000 $1,200.000 $2,407.461 $2,500.000 $1,553.620 $2,472.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 4.000 $2,300.000 $1,400.000 $2,200.000 $1,545.400 $1,590.470 $1,056.000 $1,250.000 $2,407.463 $2,600.000 $1,864.350 $2,825.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 10.000 $2,450.000 $2,500.000 $1,300.000 $2,759.650 $2,014.590 $2,316.000 $2,750.000 $3,009.327 $2,800.000 $2,920.810 $3,530.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 12.000 $2,500.000 $2,300.000 $1,500.000 $2,538.850 $4,241.240 $2,026.000 $2,500.000 $3,611.193 $3,500.000 $3,000.500 $3,530.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 8.000 $4,000.000 $6,000.000 $4,200.000 $6,623.150 $4,453.310 $4,306.000 $6,500.000 $5,416.789 $5,000.000 $7,092.090 $5,060.000
SET (TY II) (42 IN) (RCP) (3: 1) (C)
EA 4.000 $4,000.000 $3,500.000 $3,150.000 $3,863.500 $6,361.860 $3,710.000 $3,800.000 $5,416.790 $5,000.000 $4,637.140 $4,355.000
SET (TY II) (42 IN) (RCP) (6: 1) (P)
EA 2.000 $10,000.000 $7,000.000 $5,250.000 $7,727.000 $6,679.960 $6,600.000 $7,600.000 $7,222.385 $9,000.000 $8,592.340 $5,535.000
REMOV STR (INLET)
EA 3.000 $550.000 $1,000.000 $500.000 $1,103.850 $795.230 $500.000 $1,100.000 $842.610 $1,000.000 $650.890 $765.000
REMOV STR (WINGWALL)
EA 6.000 $1,250.000 $1,000.000 $3,000.000 $1,103.850 $848.250 $500.000 $1,100.000 $1,203.732 $1,000.000 $1,528.060 $824.000
REMOV STR (SMALL)
EA 101.000 $1,250.000 $200.000 $500.000 $220.750 $265.080 $300.000 $220.000 $925.000 $900.000 $2,688.880 $648.000
MOBILIZATION
LS 1.000 $676,711.000 $612,443.210 $551,000.000 $604,213.550 $610,000.000 $550,000.000 $750,000.000 $804,991.000 $1,325,000.000 $830,813.810 $800,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $10,000.000 $5,720.000 $21,000.000 $6,550.250 $3,000.000 $2,000.000 $20,000.000 $43,000.000 $2,160.000 $19,939.530 $27,200.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 600.000 $30.000 $28.000 $26.250 $30.900 $29.690 $28.000 $35.000 $33.704 $30.000 $37.220 $32.900
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 200.000 $60.000 $45.000 $31.500 $49.650 $47.710 $45.000 $80.000 $54.168 $48.000 $59.820 $82.400
ROCK FILTER DAMS (REMOVE)
LF 800.000 $7.500 $7.000 $15.000 $7.750 $7.420 $6.000 $10.000 $8.426 $7.500 $9.310 $10.500
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 122.000 $25.000 $20.000 $20.000 $22.050 $21.210 $20.000 $20.000 $24.075 $21.000 $26.590 $30.550
CONSTRUCTION EXITS (REMOVE)
SY 122.000 $12.000 $10.000 $10.000 $11.050 $10.600 $10.000 $5.000 $12.037 $10.500 $13.290 $10.350
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,594.000 $2.500 $2.200 $2.000 $2.450 $2.330 $3.000 $6.000 $2.648 $2.500 $2.920 $6.400
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,594.000 $0.750 $0.500 $0.200 $0.550 $0.530 $50.000 $0.750 $0.602 $0.750 $0.660 $0.680
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,364.000 $4.000 $4.000 $3.250 $4.450 $4.240 $4.500 $5.000 $4.815 $4.500 $5.320 $5.250
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,364.000 $1.250 $1.000 $1.050 $1.100 $1.060 $0.750 $0.750 $1.204 $1.250 $1.330 $0.680
DRIVEWAYS (ACP)
SY 5,225.000 $45.000 $59.440 $60.000 $41.700 $49.500 $47.000 $80.000 $49.629 $50.000 $63.780 $53.850
DRIVEWAYS (CONC) (HES)
SY 1,985.000 $100.000 $95.000 $78.750 $104.850 $80.000 $100.000 $105.000 $154.525 $95.000 $78.090 $110.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 46,780.000 $0.200 $0.120 $0.130 $0.150 $0.130 $0.120 $0.200 $0.181 $0.220 $0.160 $0.180
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 22,307.000 $0.150 $0.120 $0.130 $0.150 $0.130 $0.120 $0.200 $0.181 $0.270 $0.160 $0.180
MTL W-BEAM GD FEN (TIM POST)
LF 100.000 $20.000 $25.000 $18.640 $23.750 $26.510 $30.000 $20.000 $30.093 $23.000 $26.590 $27.550
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,585.000 $2,850.000 $2,541.000 $2,329.150 $3,021.890 $2,750.000 $2,615.000 $3,430.630 $2,300.000 $2,725.070 $3,255.000
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 29.000 $210.000 $225.000 $204.230 $143.500 $238.570 $230.000 $250.000 $270.840 $150.000 $186.100 $360.000
MAILBOX INSTALL-D (TWG-POST) TY 1
EA 4.000 $225.000 $235.000 $244.130 $149.000 $249.170 $255.000 $280.000 $282.878 $150.000 $195.410 $300.000
MAILBOX INSTALL-M (TWG-POST) TY 4
EA 1.000 $500.000 $350.000 $383.250 $320.100 $371.110 $381.000 $415.000 $421.310 $325.000 $378.850 $430.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 45.000 $500.000 $483.000 $507.150 $496.750 $512.130 $490.000 $530.000 $581.402 $500.000 $558.310 $435.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $660.000 $570.000 $598.500 $607.100 $604.380 $610.000 $660.000 $686.127 $600.000 $697.880 $665.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $850.000 $785.000 $824.250 $750.650 $832.350 $780.000 $845.000 $944.930 $750.000 $864.050 $830.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 34.000 $50.000 $40.000 $53.290 $27.600 $42.410 $70.000 $76.000 $48.149 $27.000 $73.110 $120.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 52,526.000 $0.250 $0.270 $0.280 $0.300 $0.270 $0.270 $0.310 $0.349 $0.310 $0.360 $0.400
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 4,050.000 $0.250 $0.350 $0.370 $0.400 $0.270 $0.350 $0.400 $0.421 $0.380 $0.470 $0.550
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 23,486.000 $0.250 $0.270 $0.280 $0.300 $0.270 $0.270 $0.300 $0.349 $0.310 $0.360 $0.400
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,478.000 $1.000 $2.250 $2.000 $1.100 $0.830 $1.000 $1.500 $1.109 $0.540 $1.460 $1.200
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 123.000 $2.000 $2.000 $2.100 $2.200 $0.710 $2.000 $2.200 $1.745 $1.570 $2.660 $3.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 170.000 $9.250 $6.000 $6.300 $6.650 $15.900 $6.000 $6.500 $15.649 $14.040 $7.980 $0.040
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 47,271.000 $0.350 $0.370 $0.390 $0.400 $0.480 $0.370 $0.400 $0.481 $0.430 $0.490 $0.550
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 5,255.000 $0.450 $0.480 $0.500 $0.550 $0.700 $0.480 $0.550 $0.638 $0.570 $0.640 $0.720
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 4,050.000 $0.350 $0.390 $0.410 $0.450 $0.470 $0.390 $0.450 $0.566 $0.510 $0.520 $0.600
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 23,486.000 $0.350 $0.370 $0.390 $0.400 $0.470 $0.370 $0.400 $0.481 $0.430 $0.490 $0.560
REFL PAV MRKR TY II-A-A
EA 541.000 $3.500 $4.000 $4.200 $4.450 $4.510 $4.000 $4.500 $6.019 $5.400 $5.320 $6.050
FULL - WIDTH MOWING
CYC 2.000 $5,120.000 $3,000.000 $3,300.000 $3,000.000 $3,180.930 $3,250.000 $5,000.000 $3,250.075 $3,240.000 $6,646.510 $3,150.000
SP MIXES SP-C SAC-B PG64-22
TON 9,603.000 $92.500 $87.750 $90.000 $105.050 $85.750 $88.000 $92.000 $93.000 $105.000 $112.210 $97.000
TACK COAT
GAL 4,762.000 $1.500 $3.500 $1.000 $1.250 $5.130 $6.000 $4.000 $3.587 $4.250 $1.330 $8.900
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $11,500.000 $15,000.000 $7,350.000 $15,250.000 $7,800.000 $5,000.000 $12,000.000 $18,160.790 $20,000.000 $10,285.460 $20,700.000
TMA (STATIONARY)
DAY 450.000 $240.000 $100.000 $52.500 $175.000 $245.000 $100.000 $100.000 $298.007 $270.000 $199.400 $262.000
TMA (MOBILE OPERATION)
HR 120.000 $60.000 $100.000 $42.000 $100.000 $44.960 $25.000 $70.000 $38.631 $21.000 $53.170 $100.000
Totals: $7,303,416.190 $5,929,503.210 $6,059,155.280 $6,464,362.544 $6,726,234.164 $6,903,214.895 $7,688,769.710 $8,061,973.469 $8,088,079.100 $8,604,953.227 $8,944,237.512