COLLIN FM 2933 (2977-01-008)

Items: 56

County: COLLIN
Length: N/A
Highway: FM 2933
District: DALLAS
Control Number: 2977-01-008
DBE Goal: N/A
Project: STP 1702(460)HES
Guaranty: N/A
Time: 86 WORKING DAYS
Engineer's Estimate: $1,430,045.50
Date: 07/11/2017 (8 years ago)
Contract Number: N/A
Type: BASE REPAIR, LEVEL UP, OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$1,430,045.50
$1,562,281.63
Over/Under Est: 9.25% $132,236.13
Over/Under Est: 12% $171,569.49
Amt Left: 2.52% $39,333.36
Over/Under Est: 15.84% $226,453.24
Amt Left: 6.03% $94,217.11
Delta: -3.43% -$54,883.75
Over/Under Est: 18.55% $265,284.08
Amt Left: 8.52% $133,047.95
Delta: -2.34% -$38,830.84
$1,707,738.00
Over/Under Est: 19.42% $277,692.50
Amt Left: 9.31% $145,456.37
Delta: -0.73% -$12,408.42
$2,025,193.20
Over/Under Est: 41.62% $595,147.70
Amt Left: 29.63% $462,911.57
Delta: -18.59% -$317,455.20

Bid Items & Bid Tabulations

56 Total 0 of 56
COLLIN  |  FM 2933  |  DALLAS  |  2977-01-008  |  07/11/2017  |  $1,430,045.50  |  STP 1702(460)HES  |  BASE REPAIR, LEVEL UP, OVERLAY  |  86 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AUSTIN BRIDGE & ROAD SERVICES, LP
A. K. GILLIS & SONS, INC.
ED BELL CONSTRUCTION COMPANY
OLDCASTLE MATERIALS TEXAS, INC.
JAGOE-PUBLIC COMPANY
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 66.300 $500.000 $700.000 $1,103.320 $2,500.000 $2,000.000 $1,800.000 $2,000.000
EXCAVATION (ROADWAY)
CY 1,475.000 $10.000 $21.000 $18.760 $13.650 $15.000 $26.000 $17.500
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 2,967.000 $12.000 $30.000 $18.660 $21.000 $15.000 $14.000 $25.000
BACKFILL (TY A OR B)
STA 66.300 $185.000 $265.000 $410.780 $315.000 $225.000 $550.000 $450.000
BLADING
STA 66.300 $110.000 $200.000 $254.390 $189.000 $175.000 $130.000 $250.000
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
SY 14,733.000 $0.500 $0.420 $0.360 $0.600 $0.450 $0.440 $0.650
DRILL SEED (TEMP)(WARM OR COOL)
SY 14,733.000 $0.150 $0.160 $0.140 $0.050 $0.170 $0.170 $0.250
VEGETATIVE WATERING
MG 1,964.000 $15.000 $1.000 $6.420 $1.050 $0.010 $24.000 $30.000
FL BS (RDWY DEL) (TY D GR 1-2)
TON 1,740.000 $27.000 $30.000 $24.200 $19.000 $18.000 $23.000 $38.500
FL BS (CMP IN PLC)(TY D GR1-2)(8")
SY 21,173.000 $13.500 $14.000 $13.610 $13.650 $11.750 $15.000 $13.500
REWORK BS MTL (TY C)(12")(ORD COMP)
SY 15,789.000 $3.150 $3.500 $2.750 $4.000 $4.000 $11.000 $3.250
CEMENT
TON 124.000 $160.000 $180.000 $124.400 $175.000 $160.000 $155.000 $161.000
CEMENT TREAT (EXIST MATL) (7")
SY 21,533.000 $1.500 $2.500 $2.750 $1.250 $2.700 $3.500 $3.250
EMULS ASPH (PRIME)(MS-2 OR SS-1)
GAL 4,161.000 $5.000 $9.500 $3.970 $5.250 $4.000 $2.500 $8.000
ASPH (CRS-2P)
GAL 5,206.000 $3.000 $2.970 $3.750 $3.150 $3.920 $3.250 $8.000
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
GAL 4,371.000 $4.000 $2.800 $3.590 $3.150 $4.000 $3.150 $8.000
AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B)
CY 129.000 $150.000 $215.000 $158.100 $262.500 $330.000 $230.000 $300.000
SUPERPAVE MIXTURES SP-D SAC-B PG64-22
TON 2,287.000 $77.000 $72.000 $66.000 $78.750 $82.000 $65.000 $105.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 733.000 $78.000 $56.000 $121.240 $42.000 $65.000 $56.000 $98.500
PLAN & TEXT ASPH CONC PAV(0" TO 6")
SY 1,097.000 $5.000 $11.000 $11.250 $11.550 $11.000 $11.000 $10.000
CUT & RESTORING PAV
SY 27.000 $80.000 $110.000 $150.000 $210.000 $55.000 $154.000 $250.000
RC PIPE (CL III)(18 IN)
LF 702.000 $56.000 $62.000 $50.000 $72.000 $65.000 $54.000 $55.000
RC PIPE (CL III)(24 IN)
LF 101.000 $125.000 $83.000 $60.000 $94.500 $85.000 $65.000 $105.000
SET (TY II) (18 IN) (RCP) (3: 1) (P)
EA 52.000 $720.000 $775.000 $550.000 $735.000 $800.000 $725.000 $1,250.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 2.000 $818.000 $815.000 $700.000 $945.000 $850.000 $1,050.000 $1,500.000
SET (TY II) (24 IN) (RCP) (3: 1) (P)
EA 4.000 $1,800.000 $825.000 $700.000 $945.000 $850.000 $750.000 $2,000.000
REMOV STR (PIPE)
LF 786.000 $25.000 $10.000 $20.000 $21.000 $11.000 $12.000 $30.000
MOBILIZATION
LS 1.000 $130,000.000 $110,000.000 $163,044.760 $148,000.000 $159,464.000 $160,000.000 $190,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $9,000.000 $4,500.000 $8,866.000 $21,000.000 $40,000.000 $6,500.000 $12,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 100.000 $30.000 $39.200 $38.000 $26.250 $40.000 $41.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 100.000 $12.000 $9.770 $15.000 $10.500 $9.800 $10.250 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 155.600 $30.000 $26.970 $27.000 $21.000 $27.000 $28.500 $45.000
CONSTRUCTION EXITS (REMOVE)
SY 155.600 $10.000 $8.900 $10.000 $7.350 $9.000 $9.500 $20.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 160.000 $5.000 $3.930 $5.000 $4.150 $4.000 $4.200 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 160.000 $1.000 $0.660 $1.000 $1.050 $0.680 $0.700 $6.000
DRIVEWAYS (CONC)
SY 338.000 $74.000 $90.000 $100.000 $84.000 $85.000 $62.500 $115.000
DRIVEWAYS (ACP)
SY 4,803.000 $33.000 $45.000 $43.530 $35.000 $34.000 $27.000 $35.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 13.000 $228.000 $220.000 $220.000 $246.750 $230.000 $265.000 $650.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 2.000 $270.000 $580.000 $580.000 $624.750 $600.000 $525.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 21.000 $470.000 $450.000 $450.000 $498.750 $475.000 $450.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 2.000 $550.000 $500.000 $500.000 $525.000 $525.000 $630.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 5.000 $600.000 $545.000 $545.000 $624.750 $565.000 $580.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $650.000 $590.000 $590.000 $687.750 $610.000 $580.000 $650.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 10.000 $50.000 $45.000 $45.000 $57.750 $48.000 $42.000 $100.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 2,656.000 $0.350 $0.500 $1.510 $0.160 $0.520 $1.590 $2.500
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 682.000 $2.000 $0.500 $2.000 $2.690 $1.050 $0.630 $5.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 348.000 $2.500 $2.000 $2.950 $2.360 $2.200 $3.100 $1.500
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 385.000 $3.500 $4.000 $3.150 $3.680 $4.400 $3.320 $3.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 16.000 $6.300 $10.000 $5.000 $8.400 $11.000 $5.250 $6.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 13,473.000 $0.350 $0.450 $0.365 $0.400 $0.480 $0.380 $0.500
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 1,260.000 $2.300 $1.500 $0.500 $0.630 $1.650 $0.530 $1.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,715.000 $0.350 $0.650 $0.550 $0.440 $0.720 $0.580 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 10,951.000 $0.420 $0.500 $0.365 $0.400 $0.550 $0.380 $0.500
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 24.000 $0.420 $15.000 $13.000 $26.250 $16.000 $13.750 $50.000
REFL PAV MRKR TY II-A-A
EA 166.000 $4.000 $5.000 $5.300 $3.360 $5.500 $5.600 $6.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $11,800.000 $15,000.000 $12,000.000 $9,450.000 $10,000.000 $10,500.000 $14,500.000
Totals: $1,430,045.500 $1,562,281.632 $1,601,615.017 $1,656,498.740 $1,695,329.580 $1,707,738.000 $2,025,193.200