Bid Cobra

COLLIN FM 428 (2678-01-014)

Items: 90

County: COLLIN
Length: 3.8340 MILES
Highway: FM 428
District: DALLAS
Control Number: 2678-01-014
DBE Goal: 700.0%
Project: F 2026(025)
Guaranty: $100,000.00
Time: 231 WORKING DAYS
Engineer's Estimate: $7,332,346.58
Date: 09/04/2025 (9 months ago) Changed
Contract Number: 9253037
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00187789
Contract Type: Federal
Project Description: RECLAIM, BASE REPAIR, HMAC PAVEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JENNIFER VORSTER
DEREJE TESEMMA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$7,332,346.58
$6,821,246.89
Over/Under Est: -6.97% -$511,099.69
Over/Under Est: -0.08% -$5,748.89
Amt Left: 7.41% $505,350.80
$7,661,093.16
Over/Under Est: 4.48% $328,746.58
Amt Left: 12.31% $839,846.27
Delta: -4.57% -$334,495.47
$7,891,102.64
Over/Under Est: 7.62% $558,756.06
Amt Left: 15.68% $1,069,855.75
Delta: -3.00% -$230,009.48
Over/Under Est: 10.54% $772,825.42
Amt Left: 18.82% $1,283,925.11
Delta: -2.71% -$214,069.36
Subcontractor Percentage Amount
CDM HOLDINGS 20.56% $1,402,448.36
JM YANEZ CONSTRUCTION, INC. 6.14% $418,824.56
HILBASH INVESTMENT LLC 2.08% $141,881.94
J. H. ODEN CONTRACTING COMPANY 1.53% $104,365.08
TEXAS TRAFFIC AND BARRICADE, LLC 1.08% $73,669.47
TRP CONSTRUCTION GROUP, LLC 0.89% $60,709.10
MARCOMS CONSTRUCTION LLC 0.81% $55,252.10
DUSTIN ALLEN, INC. 0.71% $48,430.85
CATOCON, INC. 0.59% $40,245.36
SITE BARRICADES 0.25% $17,053.12
PROFESSIONAL TRAFFIC CONTROL LLC 0.18% $12,278.24
Total: 34.82% $2,375,158.18

Bid Items & Bid Tabulations

90 Total 0 of 90
COLLIN  |  FM 428  |  DALLAS  |  2678-01-014  |  09/04/2025  |  $7,332,346.58  |  F 2026(025)  |  REHAB EXIST ROADWAY  |  231 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AUSTIN BRIDGE & ROAD SERVICES, LP
QUALITY EXCAVATION, LLC
JAGOE-PUBLIC COMPANY
OVERLAND CORPORATION
GREY SKY CONSTRUCTION LLC
PREPARING ROW
STA 202.440 $700.000 $3,369.510 $700.000 $150.000 $1,200.000 $3,500.000
REMOV CONC (MOWSTRIP)
LF 652.000 $14.000 $12.000 $21.250 $9.000 $21.000 $50.000
REMOV CONC (DRIVEWAYS)
SY 453.000 $22.000 $22.200 $28.500 $25.000 $58.000 $20.000
EXCAV (ROADWAY)
CY 6.000 $22.000 $567.620 $39.000 $100.000 $175.000 $50.000
EMBANK (FNL)(DC)(TY C)
CY 1,705.000 $30.000 $31.970 $53.000 $80.000 $81.000 $40.000
BACKFILL (TY A OR B)
STA 202.440 $300.000 $258.200 $748.000 $400.000 $430.000 $250.000
BLADING
STA 202.440 $300.000 $27.100 $580.000 $100.000 $165.000 $250.000
DRILL SEED (PERM_RURAL_CLAY)
SY 147,714.000 $0.290 $0.180 $0.160 $0.050 $0.190 $0.500
DRILL SEED (TEMP_WARM_COOL)
SY 147,714.000 $0.290 $0.160 $0.150 $0.050 $0.170 $0.500
VEGETATIVE WATERING
TGL 43,948.000 $1.500 $0.100 $4.000 $1.000 $10.000 $5.000
CEMENT
TON 292.000 $317.000 $412.500 $355.000 $400.000 $405.000 $350.000
ASPHALT BINDER (PG 64-22)
TON 570.000 $2,195.280 $852.500 $565.000 $800.000 $837.000 $165.000
FOAM ASPH TRT (EXIST MATL) (8")
SY 68,415.000 $4.200 $3.850 $8.500 $5.000 $4.000 $5.000
FOG SEAL (SS-1)
GAL 8,290.000 $2.000 $8.800 $5.400 $10.000 $9.000 $6.000
ASPH (CRS-2P)
GAL 17,671.000 $5.500 $8.800 $4.600 $8.000 $9.000 $6.000
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
GAL 14,839.000 $5.750 $8.800 $4.800 $8.000 $9.000 $6.000
AGGR (TY-B, GR-3)(SAC-B)
CY 678.000 $180.000 $220.000 $265.000 $300.000 $225.000 $250.000
SP MIXES SP-C SAC-B PG70-22
TON 16,563.000 $140.000 $127.100 $141.000 $135.000 $155.000 $155.000
TACK COAT
GAL 4,105.000 $3.500 $4.250 $0.540 $1.000 $3.550 $10.000
RIPRAP (CONC)(4 IN)
CY 10.000 $620.000 $588.660 $605.000 $1,100.000 $550.000 $550.000
RIPRAP (MOW STRIP)(4 IN)
CY 95.000 $710.000 $574.440 $640.000 $1,400.000 $600.000 $550.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 156.000 $180.000 $146.250 $161.000 $410.000 $175.000 $185.000
RC PIPE (CL III)(18 IN)
LF 500.000 $75.000 $55.000 $106.000 $90.000 $70.000 $95.000
RC PIPE (CL III)(24 IN)
LF 63.000 $85.000 $70.000 $170.000 $120.000 $90.000 $125.000
RC PIPE (CL III)(30 IN)
LF 316.000 $115.000 $120.000 $177.000 $290.000 $115.000 $150.000
RC PIPE (CL III)(36 IN)
LF 132.000 $135.000 $160.000 $285.000 $390.000 $150.000 $165.000
RC PIPE (CL III)(42 IN)
LF 12.000 $260.000 $175.000 $345.000 $600.000 $225.000 $250.000
RC PIPE (CL III)(48 IN)
LF 141.000 $260.000 $255.000 $370.000 $500.000 $275.000 $275.000
HEADWALL (CH - PW - 0) (DIA= 42 IN)
EA 1.000 $22,000.000 $13,137.450 $9,000.000 $25,000.000 $25,000.000 $11,500.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 32.000 $1,300.000 $975.000 $2,100.000 $1,600.000 $1,300.000 $1,500.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 1.000 $1,200.000 $1,175.000 $2,100.000 $1,400.000 $1,400.000 $2,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,500.000 $1,500.000 $2,650.000 $2,000.000 $1,800.000 $2,000.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 20.000 $2,800.000 $3,750.000 $6,000.000 $5,000.000 $3,700.000 $3,000.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 6.000 $4,700.000 $6,750.000 $8,200.000 $6,000.000 $8,000.000 $3,500.000
SET (TY II) (48 IN) (RCP) (6: 1) (P)
EA 6.000 $9,500.000 $9,875.000 $13,500.000 $10,000.000 $15,000.000 $6,500.000
REMOV STR (SET)
EA 9.000 $175.000 $350.000 $550.000 $360.000 $160.000 $500.000
REMOV STR (PIPE)
LF 958.000 $20.000 $7.500 $21.500 $20.000 $16.000 $50.000
MOBILIZATION
LS 1.000 $699,403.410 $750,337.290 $730,000.000 $850,000.000 $760,000.000 $800,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $10,000.000 $26,598.410 $15,000.000 $35,000.000 $20,000.000 $8,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $18,000.000 $20,000.000 $19,000.000 $30,000.000 $20,000.000 $20,000.000
TMA (STATIONARY)
DAY 275.000 $275.000 $2.000 $200.000 $150.000 $310.000 $250.000
TMA (MOBILE OPERATION)
HR 168.000 $110.000 $3.000 $110.000 $25.000 $200.000 $55.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 380.000 $40.000 $40.000 $52.000 $60.000 $45.000 $30.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 20.000 $90.000 $100.000 $154.000 $190.000 $110.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 400.000 $16.500 $14.000 $19.500 $24.000 $15.000 $20.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 172.000 $40.000 $35.000 $46.000 $5.000 $38.000 $50.000
CONSTRUCTION EXITS (REMOVE)
SY 172.000 $13.000 $17.000 $16.500 $1.000 $18.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,294.000 $4.500 $4.250 $4.870 $6.000 $4.500 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,294.000 $1.200 $1.500 $1.100 $1.250 $1.600 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,507.000 $6.000 $5.000 $8.750 $11.000 $5.250 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,507.000 $1.750 $1.000 $0.890 $1.000 $1.000 $5.000
DRIVEWAYS (CONC) (HES)
SY 453.000 $175.000 $93.320 $110.000 $130.000 $160.000 $125.000
DRIVEWAYS (ACP)
SY 7,868.000 $80.000 $66.100 $98.500 $120.000 $100.000 $42.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 36,683.000 $0.750 $0.070 $0.160 $0.120 $0.150 $0.500
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 17,173.000 $0.750 $0.090 $0.190 $0.150 $0.150 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 950.000 $25.000 $20.250 $24.670 $34.000 $24.300 $30.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 4.000 $1,300.000 $1,179.000 $1,387.560 $1,500.000 $24.840 $5.000
REMOVE METAL BEAM GUARD FENCE
LF 225.000 $4.000 $2.000 $3.780 $3.250 $2.970 $3,850.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,600.000 $2,770.000 $3,313.950 $4,100.000 $3,186.000 $1,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $500.000 $200.000 $323.950 $330.000 $270.000 $1,150.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 7.000 $275.000 $220.000 $237.560 $290.000 $237.000 $30.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 27.000 $35.000 $29.000 $31.310 $38.000 $31.320 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 79.000 $660.000 $550.000 $593.900 $700.000 $594.000 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 1.000 $750.000 $590.000 $637.090 $800.000 $637.200 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $750.000 $685.000 $739.670 $900.000 $739.800 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,025.000 $990.000 $1,069.020 $1,300.000 $1,069.200 $1,150.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,250.000 $990.000 $1,069.020 $1,300.000 $1,069.200 $1,150.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 2.000 $1,100.000 $990.000 $1,069.020 $1,300.000 $1,069.200 $1,150.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $30.000 $31.000 $32.390 $31.000 $27.000 $100.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 16.000 $50.000 $59.000 $63.710 $80.000 $63.720 $100.000
WK ZN PAV MRK NON-REMOV (W)8"(DOT)
LF 174.000 $0.600 $3.500 $3.780 $2.500 $0.770 $6.000
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,600.000 $0.600 $0.700 $0.760 $1.250 $0.650 $6.000
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 6.000 $311.000 $175.000 $188.970 $150.000 $88.800 $250.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 6.000 $400.000 $195.000 $210.560 $210.000 $88.800 $250.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 3,160.000 $0.900 $0.450 $0.490 $1.250 $0.380 $1.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 23,020.000 $0.900 $0.360 $0.390 $0.400 $0.360 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 268.000 $3.000 $2.500 $2.550 $2.500 $2.020 $6.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,413.000 $3.000 $2.000 $3.250 $2.500 $2.020 $6.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 231.000 $1.750 $1.500 $1.620 $2.500 $1.240 $1.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 174.000 $2.500 $2.000 $2.160 $2.500 $1.600 $6.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,600.000 $2.500 $1.250 $1.350 $1.250 $1.480 $6.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 254.000 $10.000 $7.000 $7.560 $9.000 $7.990 $20.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 6.000 $275.000 $200.000 $215.960 $330.000 $171.680 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 6.000 $300.000 $235.000 $253.760 $420.000 $183.520 $250.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 5.000 $72.000 $45.000 $48.590 $100.000 $65.120 $150.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 3,160.000 $1.500 $0.600 $0.650 $0.800 $0.720 $1.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 39,933.000 $1.500 $0.500 $0.540 $0.700 $0.690 $1.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 23,020.000 $1.500 $0.500 $0.540 $0.700 $0.690 $1.000
REFL PAV MRKR TY I-C
EA 106.000 $6.000 $4.250 $4.590 $9.000 $0.690 $6.000
REFL PAV MRKR TY II-A-A
EA 692.000 $6.000 $4.250 $4.590 $7.000 $4.610 $6.000
Totals: $7,332,346.580 $6,821,246.896 $7,326,597.690 $7,661,093.160 $7,891,102.640 $8,105,172.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $130,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $130,000.00
Total: $260,000.00