COLLIN FM 1827 (1746-01-031)
Items: 108
County: COLLIN
Length: 5.2900 MILES
Highway: FM 1827
District: DALLAS
Control Number: 1746-01-031
DBE Goal: 0.0%
Project: STP 2026(148)HRR
Guaranty: $100,000.00
Time: 228 WORKING DAYS
Engineer's Estimate: $12,202,344.72
Date: 11/06/2025 (7 months ago) Changed
Contract Number: 11253025
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00194003
Contract Type: Federal
Project Description: SAFETY TREAT FIXED OBJECTS, PROFILE EDGE LINE MARKINGS, PROVIDE ADDITIONAL PAVED SURFACE WIDTH, PROFILE CENTERLINE MARKINGS
Mail/Deliver Bids To: N/A
JENNIFER VORSTER
DEREJE TESEMMA
COLLIN FM 1827 (1746-01-031)
Project Name: N/A
Project: STP 2026(148)HRR
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: FM 75
Limits To: FM 545
Project Description: SAFETY TREAT FIXED OBJECTS, PROFILE EDGE LINE MARKINGS, PROVIDE ADDITIONAL PAVED SURFACE WIDTH, PROFILE CENTERLINE MARKINGS
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$12,202,344.72 | |||
| $8,652,246.35 |
-29.09%
-$3,550,098.37
|
|||
| $9,657,530.95 |
-20.86%
-$2,544,813.77
|
11.62%
$1,005,284.60
|
||
| $10,369,990.50 |
-15.02%
-$1,832,354.22
|
19.85%
$1,717,744.15
|
-7.38%
-$712,459.55
|
|
| $11,595,826.66 |
-4.97%
-$606,518.06
|
34.02%
$2,943,580.31
|
-11.82%
-$1,225,836.16
|
|
| $12,530,134.05 |
2.69%
$327,789.33
|
44.82%
$3,877,887.70
|
-8.06%
-$934,307.39
|
E
Engineer's Estimate
$12,202,344.72
1
$8,652,246.35
Over/Under Est:
-29.09%
-$3,550,098.37
$9,657,530.95
Over/Under Est:
-20.86%
-$2,544,813.77
Amt Left:
11.62%
$1,005,284.60
$10,369,990.50
Over/Under Est:
-15.02%
-$1,832,354.22
Amt Left:
19.85%
$1,717,744.15
Delta:
-7.38%
-$712,459.55
$11,595,826.66
Over/Under Est:
-4.97%
-$606,518.06
Amt Left:
34.02%
$2,943,580.31
Delta:
-11.82%
-$1,225,836.16
$12,530,134.05
Over/Under Est:
2.69%
$327,789.33
Amt Left:
44.82%
$3,877,887.70
Delta:
-8.06%
-$934,307.39
| Subcontractor | Percentage | Amount |
|---|---|---|
| TEXANA LAND & ASPHALT, INC. | 20.87% | $1,805,723.81 |
| BAHENA CONSTRUCTION CO., INC. | 13.12% | $1,135,174.72 |
| MOJICA CONSTRUCTION LLC | 5.61% | $485,391.02 |
| J. H. ODEN CONTRACTING COMPANY | 2.52% | $218,036.61 |
| CATOCON, INC. | 0.96% | $83,061.56 |
| STRIPE-A-ZONE, LLC | 0.89% | $77,004.99 |
| MORRIS COUNTY CONTRACTORS, L.L.C. | 0.64% | $55,374.38 |
| TEX OP CONSTRUCTION, LP | 0.32% | $27,687.19 |
| PANOLA SIGN & BARRICADE, INC. | 0.29% | $25,091.51 |
| SURFACE PREPARATION TECHNOLOGIES, LLC | 0.18% | $15,574.04 |
| Total: | 45.40% | $3,928,119.83 |
Bid Items & Bid Tabulations
108
Total
0 of 108