PREPARING ROW
|
STA
|
60.610
|
$8,000.000
|
$6,500.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
4,394.000
|
$11.700
|
$15.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
381.000
|
$17.410
|
$15.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
1,089.000
|
$6.220
|
$7.500
|
|
|
REMOVING STAB BASE & ASPH PAV (4"-22")
|
SY
|
18,571.000
|
$5.220
|
$13.650
|
|
|
REMOVING STAB BASE AND ASPH PAV (5"-8")
|
SY
|
1,257.000
|
$3.000
|
$9.450
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
12,407.000
|
$10.000
|
$5.000
|
|
|
EMBANKMENT (FINAL) (DENS CONT) (TY C1)
|
CY
|
21,611.000
|
$15.000
|
$31.500
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
36,897.000
|
$1.580
|
$0.750
|
|
|
BLOCK SODDING
|
SY
|
36,897.000
|
$4.000
|
$4.000
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
10,654.000
|
$0.110
|
$0.150
|
|
|
VEGETATIVE WATERING
|
MG
|
7,074.000
|
$5.920
|
$1.000
|
|
|
LIME (HYD, COM, OR QK(SLURRY))
|
TON
|
695.000
|
$310.000
|
$300.000
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
41,501.000
|
$4.000
|
$8.000
|
|
|
CONC PVMT (CONT REINF - CRCP) (8")
|
SY
|
23,529.000
|
$125.000
|
$90.000
|
|
|
CURB (TYPE II)
|
LF
|
8,136.000
|
$8.000
|
$4.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
240.000
|
$90.170
|
$200.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
1,917.000
|
$2.500
|
$10.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
828.000
|
$26.270
|
$100.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
8.000
|
$300.000
|
$532.130
|
|
|
DRILL SHAFT (TRF SIG POLE) (30 IN)
|
LF
|
11.000
|
$286.040
|
$580.500
|
|
|
DRILL SHAFT (TRF SIG POLE) (36 IN)
|
LF
|
13.000
|
$312.630
|
$682.630
|
|
|
DRILL SHAFT (TRF SIG POLE) (48 IN)
|
LF
|
22.000
|
$575.380
|
$784.750
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
13.000
|
$572.370
|
$1,000.000
|
|
|
RIPRAP (STONE COMMON)(GROUT)(18 IN)
|
CY
|
165.000
|
$194.650
|
$750.000
|
|
|
RAIL (HANDRAIL)(TY E)
|
LF
|
70.000
|
$144.400
|
$300.000
|
|
|
RAIL (TY PR11)
|
LF
|
58.000
|
$89.690
|
$300.000
|
|
|
CONC BOX CULV (6 FT X 4 FT)
|
LF
|
132.000
|
$430.000
|
$480.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
633.000
|
$75.330
|
$60.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
3,955.000
|
$105.000
|
$90.000
|
|
|
RC PIPE (CL III)(42 IN)
|
LF
|
394.000
|
$187.560
|
$200.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
64.000
|
$195.600
|
$275.000
|
|
|
MANH (COMPL)(PRM)(72IN)
|
EA
|
1.000
|
$10,000.000
|
$11,550.000
|
|
|
INLET (COMPL)(PCU)(3FT)(BOTH)
|
EA
|
33.000
|
$8,000.000
|
$10,500.000
|
|
|
INLET (COMPL)(PSL)(FG)(5FTX5FT-4FTX4FT)
|
EA
|
2.000
|
$7,350.000
|
$8,400.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 42 IN)
|
EA
|
1.000
|
$8,300.000
|
$8,400.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 48 IN)
|
EA
|
2.000
|
$10,500.000
|
$11,550.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 42 IN)
|
EA
|
1.000
|
$9,750.000
|
$9,450.000
|
|
|
WINGWALL (PW - 1) (HW=10 FT)
|
EA
|
2.000
|
$45,237.500
|
$52,500.000
|
|
|
SET (TY II) (18 IN) (RCP) (3: 1) (P)
|
EA
|
1.000
|
$850.000
|
$1,500.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
22.000
|
$1,000.000
|
$1,050.000
|
|
|
REMOV STR (SET)
|
EA
|
27.000
|
$413.140
|
$400.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
10.000
|
$1,436.960
|
$2,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
429.000
|
$19.370
|
$30.000
|
|
|
REMOV STR (DRIVEWAY CULVERT)
|
EA
|
16.000
|
$745.480
|
$750.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$900,000.000
|
$1,200,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
26.000
|
$12,000.000
|
$21,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
364.000
|
$28.800
|
$30.100
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
156.000
|
$55.000
|
$63.430
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
520.000
|
$9.780
|
$10.750
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
78.000
|
$20.450
|
$30.100
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
78.000
|
$9.840
|
$10.210
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
8,236.000
|
$1.760
|
$2.850
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
8,236.000
|
$0.710
|
$0.700
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
737.000
|
$6.070
|
$4.570
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
401.000
|
$5.090
|
$5.640
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,138.000
|
$1.420
|
$1.080
|
|
|
CONSTRUCTING DETOURS
|
SY
|
5,569.000
|
$75.000
|
$120.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
2,310.000
|
$32.520
|
$25.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
1,980.000
|
$9.330
|
$7.500
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
2,280.000
|
$10.430
|
$15.000
|
|
|
CONC CURB (DOWEL)
|
LF
|
378.000
|
$25.000
|
$30.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
1,149.000
|
$62.370
|
$125.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
373.000
|
$52.640
|
$111.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
406.000
|
$70.000
|
$100.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
8.000
|
$2,338.940
|
$3,000.000
|
|
|
CURB RAMPS (TY 7)
|
EA
|
8.000
|
$2,161.400
|
$3,000.000
|
|
|
CURB RAMPS (TY 10)
|
EA
|
4.000
|
$2,156.430
|
$3,000.000
|
|
|
CONC MEDIAN
|
SY
|
592.000
|
$70.560
|
$100.000
|
|
|
CONC DIRECTIONAL ISLAND
|
SY
|
306.000
|
$67.430
|
$100.000
|
|
|
RIGHT OF WAY MARKERS
|
EA
|
18.000
|
$154.630
|
$525.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
187.500
|
$21.730
|
$32.250
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,100.000
|
$2,150.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
708.000
|
$3.460
|
$10.750
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$2,742.600
|
$4,300.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
6.000
|
$253.210
|
$430.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
6.000
|
$1,424.380
|
$1,523.940
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
6.000
|
$896.200
|
$761.970
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
6.000
|
$6,800.000
|
$11,560.080
|
|
|
RELOCATE EXISTING MAILBOX
|
EA
|
8.000
|
$400.000
|
$537.500
|
|
|
IN RD IL AM (TY SA) 40T-8 (250W) S
|
EA
|
1.000
|
$5,500.000
|
$8,600.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
97.000
|
$14.410
|
$35.480
|
|
|
CONDT (PVC) (SCH 40) (3")
|
LF
|
206.000
|
$12.850
|
$38.700
|
|
|
CONDT (PVC) (SCH 40) (3") (BORE)
|
LF
|
393.000
|
$30.150
|
$69.880
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
31.000
|
$36.280
|
$37.630
|
|
|
ELEC CONDR (NO.12) INSULATED
|
LF
|
312.000
|
$1.030
|
$2.150
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
1,166.000
|
$1.560
|
$2.150
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
655.000
|
$2.080
|
$3.230
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
42.000
|
$1.590
|
$3.230
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
1.000
|
$893.830
|
$2,408.000
|
|
|
GROUND BOX TY C (162911)W/APRON
|
EA
|
5.000
|
$971.420
|
$2,558.500
|
|
|
ELC SRV TY D 120/240 070(NS)SS(E)PS(U)
|
EA
|
1.000
|
$5,790.010
|
$11,825.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
6.250
|
$18.110
|
$55.900
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
27.000
|
$415.130
|
$682.630
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
5.000
|
$529.500
|
$881.500
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
4.000
|
$935.000
|
$1,123.380
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
|
EA
|
1.000
|
$786.850
|
$1,381.380
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
12.000
|
$95.400
|
$53.750
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
29,083.000
|
$1.080
|
$0.940
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
121.000
|
$8.000
|
$9.940
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
29,608.000
|
$1.100
|
$0.940
|
|
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
|
LF
|
182.000
|
$2.500
|
$5.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
2,335.000
|
$1.100
|
$1.290
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
470.000
|
$6.670
|
$7.530
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
16.000
|
$125.290
|
$158.030
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
16.000
|
$154.290
|
$213.930
|
|
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
|
EA
|
14.000
|
$82.210
|
$66.650
|
|
REFL PAV MRK TY II (W) 6" (BRK)
|
LF
|
963.000
|
$0.500
|
$1.180
|
|
REFL PAV MRK TY II (W) 6" (DOT)
|
LF
|
182.000
|
$0.450
|
$4.300
|
|
REFL PAV MRK TY II (W) 6" (SLD)
|
LF
|
4,486.000
|
$0.250
|
$0.460
|
|
REFL PAV MRK TY II (W) 8" (SLD)
|
LF
|
2,335.000
|
$0.420
|
$1.610
|
|
REFL PAV MRK TY II (W) 24" (SLD)
|
LF
|
363.000
|
$3.170
|
$3.980
|
|
REFL PAV MRK TY II (W) (ARROW)
|
EA
|
16.000
|
$59.270
|
$91.380
|
|
REFL PAV MRK TY II (W) (WORD)
|
EA
|
16.000
|
$62.750
|
$118.250
|
|
REFL PAV MRK TY II (W) 36" (YLD TRI)
|
EA
|
14.000
|
$27.830
|
$40.850
|
|
REFL PAV MRK TY II (Y) 6" (SLD)
|
LF
|
4,579.000
|
$0.500
|
$0.460
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
1,230.000
|
$0.600
|
$1.130
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
9,015.000
|
$0.530
|
$0.990
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
7,826.000
|
$0.750
|
$0.990
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
219.000
|
$5.000
|
$5.590
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
178.000
|
$4.210
|
$5.590
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
25,890.000
|
$0.520
|
$0.550
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
172.000
|
$0.910
|
$3.230
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
46.000
|
$3.120
|
$11.830
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
4.000
|
$47.300
|
$139.750
|
|
|
ELIM EXT PAV MRK & MRKS (WORD)
|
EA
|
4.000
|
$57.200
|
$161.250
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
18,026.000
|
$0.150
|
$0.220
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
2,335.000
|
$0.130
|
$0.470
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
470.000
|
$1.330
|
$2.040
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
16.000
|
$24.950
|
$62.350
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
16.000
|
$31.030
|
$66.650
|
|
|
PAV SURF PREP FOR MRK (36")(YLD TRI)
|
EA
|
14.000
|
$25.640
|
$80.630
|
|
|
PAV SURF PREP FOR MRK (RPM)
|
EA
|
397.000
|
$1.100
|
$3.230
|
|
|
INSTALL HWY TRF SIG (ISOLATED)
|
EA
|
1.000
|
$32,108.620
|
$45,150.000
|
|
|
REMOVING TRAFFIC SIGNALS
|
EA
|
1.000
|
$9,772.500
|
$6,987.500
|
|
|
TEMP TRAF SIGNALS
|
EA
|
1.000
|
$100,000.000
|
$109,650.000
|
|
|
VEH SIG SEC (12")LED(GRN)
|
EA
|
4.000
|
$327.380
|
$779.380
|
|
|
VEH SIG SEC (12")LED(GRN ARW)
|
EA
|
4.000
|
$372.380
|
$779.380
|
|
|
VEH SIG SEC (12")LED(YEL)
|
EA
|
4.000
|
$392.610
|
$779.380
|
|
|
VEH SIG SEC (12")LED(YEL ARW)
|
EA
|
4.000
|
$373.670
|
$779.380
|
|
|
VEH SIG SEC (12")LED(RED)
|
EA
|
4.000
|
$368.390
|
$779.380
|
|
|
VEH SIG SEC (12")LED(RED ARW)
|
EA
|
4.000
|
$345.560
|
$779.380
|
|
|
PED SIG SEC (LED)(COUNTDOWN)
|
EA
|
4.000
|
$529.990
|
$1,370.630
|
|
|
BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM
|
EA
|
8.000
|
$123.000
|
$155.880
|
|
|
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
|
LF
|
454.000
|
$1.930
|
$3.230
|
|
|
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
|
LF
|
561.000
|
$3.860
|
$3.230
|
|
|
TRF SIG CBL (TY A)(14 AWG)(10 CONDR)
|
LF
|
692.000
|
$2.380
|
$7.530
|
|
|
TRF SIG CBL (TY C)(12 AWG)(2 CONDR)
|
LF
|
704.000
|
$1.280
|
$2.150
|
|
|
RELOCT RDSD FLSH BCN AM (SOLAR PWRD)
|
EA
|
1.000
|
$3,500.000
|
$3,762.500
|
|
|
INS TRF SIG PL AM(S)1 ARM(28')LUM
|
EA
|
1.000
|
$12,500.000
|
$19,350.000
|
|
|
INS TRF SIG PL AM(S)1 ARM(40')LUM
|
EA
|
1.000
|
$15,430.000
|
$26,337.500
|
|
|
INS TRF SIG PL AM(S)1 ARM(65')LUM
|
EA
|
1.000
|
$36,240.000
|
$49,450.000
|
|
|
PED POLE ASSEMBLY
|
EA
|
2.000
|
$3,589.550
|
$6,450.000
|
|
|
PED DETECT PUSH BUTTON (APS)
|
EA
|
4.000
|
$1,203.260
|
$1,290.000
|
|
|
PED DETECTOR CONTROLLER UNIT
|
EA
|
1.000
|
$3,855.250
|
$5,375.000
|
|
|
FULL - WIDTH MOWING
|
CYC
|
3.000
|
$3,704.000
|
$3,300.000
|
|
|
LITTER REMOVAL
|
CYC
|
3.000
|
$2,500.000
|
$3,300.000
|
|
|
DECOMPOSED GRANITE (3" DEPTH)
|
SY
|
2,374.000
|
$30.000
|
$50.000
|
|
|
SP MIXES SP-B PG64-22
|
TON
|
10,656.000
|
$105.000
|
$150.000
|
|
|
SP MIXES SP-C SAC-B PG64-22
|
TON
|
1,702.000
|
$125.000
|
$165.000
|
|
|
TACK COAT
|
GAL
|
1,850.000
|
$3.000
|
$1.080
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
3.000
|
$7,881.720
|
$21,000.000
|
|
|
BBU SYSTEM (EXTERNAL BATT CABINET)
|
EA
|
1.000
|
$7,860.530
|
$10,320.000
|
|
|
TMA (STATIONARY)
|
DAY
|
432.000
|
$93.430
|
$105.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
150.000
|
$64.280
|
$52.500
|
|
|
RVDS(PRESENCE AND ADVANCE DET)
|
EA
|
3.000
|
$9,020.330
|
$10,212.500
|
|
|
VIVDS TEMPORARY
|
EA
|
1.000
|
$23,366.670
|
$32,250.000
|
|
|
20" AWWA C303 RCCP
|
LF
|
1,453.000
|
$300.000
|
$365.500
|
|
|
20"X20" 90 DEGREE RCCP BEND
|
EA
|
2.000
|
$3,000.000
|
$16,662.500
|
|
|
20"X20" 73 DEGREE RCCP BEND
|
EA
|
1.000
|
$5,000.000
|
$16,662.500
|
|
|
20" X 20" 45 DEGREE RCCP BEND
|
EA
|
7.000
|
$3,000.000
|
$11,287.500
|
|
|
REMOVE EXISTING WATER MAIN
|
LS
|
1.000
|
$367,500.000
|
$103,200.000
|
|
|
THRUST RESTRAINT
|
LF
|
547.000
|
$170.000
|
$225.750
|
|
|
EXISTING PIPE JOINT RESTRAINTS
|
LF
|
110.000
|
$500.000
|
$408.500
|
|
|
CONNECT TO EXISTING WATERLINE
|
EA
|
2.000
|
$20,000.000
|
$45,150.000
|
|
|
TESTING AND DISINFECTION
|
LS
|
1.000
|
$8,718.000
|
$125,237.500
|
|
|
6" COMBINATION AIR RELEASE ASSEMBLY
|
EA
|
1.000
|
$40,000.000
|
$64,500.000
|
|
|
8" BLOWOFF VALVE ASSEMBLY
|
EA
|
2.000
|
$40,000.000
|
$61,275.000
|
|
|
TRENCH EXCAVATION SAFETY & SUPPORT
|
LF
|
1,453.000
|
$5.000
|
$2.150
|
|
|
SALVAGE EXIST BLOW-OFF VALVE & PIPING
|
EA
|
2.000
|
$1,000.000
|
$7,740.000
|
|
|
SILT FENCE
|
LF
|
1,453.000
|
$10.000
|
$5.380
|
|
|
SAND BACKFILL
|
CY
|
45.000
|
$25.000
|
$123.630
|
|
|
FLOWABLE FILL
|
CY
|
22.000
|
$100.000
|
$252.630
|
|
|
REM DERILICT WOODEN SHED
|
LS
|
1.000
|
$100.000
|
$53,750.000
|
|
|
REM & REPLACE WOODEN FENCE
|
LF
|
668.000
|
$40.000
|
$106.430
|
|
|
REM & REPLACE CHAIN LINK FENCE
|
LS
|
92.000
|
$25.000
|
$70.950
|
|
|
REM & REPLACE BARBED WIRE FENCE
|
LF
|
30.000
|
$10.000
|
$32.250
|
|
|
REM & REPLACE BOX WIRE FENCE
|
EA
|
200.000
|
$10.000
|
$16.130
|
|
|
REM & REPLACE 12IN CMP
|
LF
|
20.000
|
$100.000
|
$134.380
|
|
|
INSTALL ACCESS GATE
|
EA
|
5.000
|
$500.000
|
$2,150.000
|
|
|
REMOVE & REPLACE TREE
|
EA
|
2.000
|
$2,000.000
|
$1,290.000
|
|
|
REMOVE TREE
|
EA
|
8.000
|
$100.000
|
$1,720.000
|
|
|
REMOVE & REPLACE ASPHALT DRIVEWAY
|
SY
|
406.000
|
$100.000
|
$505.250
|
|
|
RESTORATION & SEEDING
|
AC
|
2.000
|
$1,500.000
|
$5,375.000
|
|
|
SWPPP
|
EA
|
1.000
|
$5,000.000
|
$8,062.500
|
|
|
DISP OF HVY CHLOR WATER MN FLUS WATER
|
LF
|
1,453.000
|
$6.000
|
$80.630
|
|
|
CONST SURV & STAKING (W & WW MAINS)
|
LF
|
1,453.000
|
$8.000
|
$10.750
|
|
Totals: |
$11,334,044.302
|
$13,639,341.230
|