COLLIN FM 1777 (1014-04-015)
Items: 86
County: COLLIN
Length: 0.0000 MILES
Highway: FM 1777
District: DALLAS
Control Number: 1014-04-015
DBE Goal: 0.0%
Project: F 2026(723)
Guaranty: $100,000.00
Time: 188 WORKING DAYS
Engineer's Estimate: $9,890,108.45
Date: 11/06/2025 (7 months ago)
Contract Number: 11253209
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00066969
Contract Type: Federal
Project Description: REHABILITATE EXISTING PAVEMENT AND ADD SHOULDERS
Mail/Deliver Bids To: N/A
JENNIFER VORSTER
DEREJE TESEMMA
COLLIN FM 1777 (1014-04-015)
Project Name: N/A
Project: F 2026(723)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: FM 6
Limits To: CR 677
Project Description: REHABILITATE EXISTING PAVEMENT AND ADD SHOULDERS
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$9,890,108.45 | |||
| $6,601,557.92 |
-33.25%
-$3,288,550.53
|
|||
| $8,194,616.12 |
-17.14%
-$1,695,492.33
|
24.13%
$1,593,058.20
|
||
| $8,369,102.26 |
-15.38%
-$1,521,006.19
|
26.77%
$1,767,544.34
|
-2.13%
-$174,486.14
|
|
| $8,448,571.66 |
-14.58%
-$1,441,536.79
|
27.98%
$1,847,013.74
|
-0.95%
-$79,469.40
|
|
| $9,398,450.50 |
-4.97%
-$491,657.95
|
42.37%
$2,796,892.58
|
-11.24%
-$949,878.84
|
E
Engineer's Estimate
$9,890,108.45
1
$6,601,557.92
Over/Under Est:
-33.25%
-$3,288,550.53
$8,194,616.12
Over/Under Est:
-17.14%
-$1,695,492.33
Amt Left:
24.13%
$1,593,058.20
$8,369,102.26
Over/Under Est:
-15.38%
-$1,521,006.19
Amt Left:
26.77%
$1,767,544.34
Delta:
-2.13%
-$174,486.14
$8,448,571.66
Over/Under Est:
-14.58%
-$1,441,536.79
Amt Left:
27.98%
$1,847,013.74
Delta:
-0.95%
-$79,469.40
$9,398,450.50
Over/Under Est:
-4.97%
-$491,657.95
Amt Left:
42.37%
$2,796,892.58
Delta:
-11.24%
-$949,878.84
| Subcontractor | Percentage | Amount |
|---|---|---|
| REYNOLDS ASPHALT & CONSTRUCTION COMPANY | 18.65% | $1,231,190.55 |
| BAHENA CONSTRUCTION CO., INC. | 9.46% | $624,507.38 |
| J. H. ODEN CONTRACTING COMPANY | 1.65% | $108,925.71 |
| TEXOP CONSTRUCTION | 1.20% | $79,218.70 |
| DUSTIN ALLEN, INC. | 0.83% | $54,792.93 |
| STRIPE-A-ZONE, LLC | 0.81% | $53,472.62 |
| CATOCON, INC. | 0.59% | $38,949.19 |
| MOJICA CONSTRUCTION LLC | 0.43% | $28,386.70 |
| PANOLA SIGN & BARRICADE, INC. | 0.26% | $17,164.05 |
| SURFACE PREPARATION TECHNOLOGIES, LLC | 0.17% | $11,222.65 |
| Total: | 34.05% | $2,247,830.48 |
Bid Items & Bid Tabulations
86
Total
0 of 86