COLLIN FM 547 (1014-01-014)
Items: 90
County: COLLIN
Length: N/A
Highway: FM 547
District: DALLAS
Control Number: 1014-01-014
DBE Goal: N/A
Project: BR 2023(917)
Guaranty: N/A
Time: 290 WORKING DAYS
Engineer's Estimate: $5,137,605.65
Date: 06/02/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JENNIFER VORSTER
GERALD WALTMAN
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$5,137,605.65 | |||
| $4,898,841.15 |
-4.65%
-$238,764.50
|
|||
| $5,510,286.81 |
7.25%
$372,681.16
|
12.48%
$611,445.66
|
||
| $5,569,299.95 |
8.4%
$431,694.30
|
13.69%
$670,458.80
|
-1.07%
-$59,013.14
|
|
| $5,630,846.81 |
9.6%
$493,241.16
|
14.94%
$732,005.66
|
-1.11%
-$61,546.86
|
|
| $6,118,000.00 |
19.08%
$980,394.35
|
24.89%
$1,219,158.85
|
-8.65%
-$487,153.19
|
|
| $7,399,984.60 |
44.04%
$2,262,378.95
|
51.06%
$2,501,143.45
|
-20.95%
-$1,281,984.60
|
E
Engineer's Estimate
$5,137,605.65
1
Awarded
$4,898,841.15
Over/Under Est:
-4.65%
-$238,764.50
$5,510,286.81
Over/Under Est:
7.25%
$372,681.16
Amt Left:
12.48%
$611,445.66
$5,569,299.95
Over/Under Est:
8.4%
$431,694.30
Amt Left:
13.69%
$670,458.80
Delta:
-1.07%
-$59,013.14
$5,630,846.81
Over/Under Est:
9.6%
$493,241.16
Amt Left:
14.94%
$732,005.66
Delta:
-1.11%
-$61,546.86
$6,118,000.00
Over/Under Est:
19.08%
$980,394.35
Amt Left:
24.89%
$1,219,158.85
Delta:
-8.65%
-$487,153.19
$7,399,984.60
Over/Under Est:
44.04%
$2,262,378.95
Amt Left:
51.06%
$2,501,143.45
Delta:
-20.95%
-$1,281,984.60
| Subcontractor | Percentage | Amount |
|---|---|---|
| HILBASH INVESTMENT LLC | 10.30% | $509,447.39 |
| PEACHTREE CONSTRUCTION, LTD. | 6.54% | $323,474.36 |
| WYLIE DRILLING & DRAINAGE, INC. | 4.40% | $217,628.01 |
| USA SWPPP INSPECTIONS, INC.DBA USA EROSION | 2.60% | $128,598.37 |
| ODUM SERVICES, LLC | 1.35% | $66,772.23 |
| HERMANOS STEEL, LLC | 0.78% | $38,579.51 |
| DUSTROL, INC. | 0.53% | $26,214.28 |
| PENHALL COMPANY | 0.48% | $23,741.24 |
| KING GEORGE TRAFFIC SOLUTIONS LLC | 0.45% | $22,257.41 |
| FC TRAFFIC CONTROL, INC. | 0.39% | $19,289.76 |
| DFW REBAR, INC. | 0.11% | $5,440.70 |
| Total: | 27.93% | $1,381,443.26 |
Bid Items & Bid Tabulations
90
Total
0 of 90