PREPARING ROW
|
STA
|
240.050
|
$600.000
|
$100.000
|
$2,415.000
|
$2,100.000
|
|
|
REMOVING CONC (SIDEWALKS)
|
SY
|
22.000
|
$12.000
|
$25.000
|
$20.000
|
$63.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
749.000
|
$13.000
|
$25.000
|
$20.000
|
$21.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
4,451.000
|
$10.000
|
$30.000
|
$20.000
|
$21.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
9,369.000
|
$10.000
|
$30.000
|
$30.000
|
$21.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
240.050
|
$215.000
|
$200.000
|
$450.000
|
$450.000
|
|
|
BLADING
|
STA
|
240.050
|
$205.000
|
$50.000
|
$250.000
|
$900.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
149,554.000
|
$0.100
|
$0.150
|
$0.500
|
$0.220
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
149,554.000
|
$0.100
|
$0.010
|
$0.500
|
$0.200
|
|
|
VEGETATIVE WATERING
|
MG
|
44,495.000
|
$2.500
|
$0.010
|
$10.000
|
$1.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
|
SY
|
803.000
|
$143.000
|
$150.000
|
$120.000
|
$136.820
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
67,013.000
|
$3.150
|
$1.500
|
$5.000
|
$4.000
|
|
|
CEM STABIL BKFL
|
CY
|
366.000
|
$190.000
|
$200.000
|
$350.000
|
$185.000
|
|
|
CUT & RESTORING PAV
|
SY
|
323.000
|
$150.000
|
$150.000
|
$200.000
|
$155.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
4.000
|
$145.000
|
$220.000
|
$350.000
|
$1,250.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
154.000
|
$3.000
|
$24.000
|
$10.000
|
$10.000
|
|
|
RIPRAP (CONC)(6 IN)
|
CY
|
1.000
|
$600.000
|
$1,500.000
|
$2,000.000
|
$2,100.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(12 IN)
|
CY
|
158.000
|
$150.000
|
$175.000
|
$165.000
|
$250.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
592.000
|
$200.000
|
$166.000
|
$185.000
|
$215.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
51.000
|
$41.000
|
$550.000
|
$550.000
|
$800.000
|
|
|
CONC BOX CULV (8 FT X 6 FT)
|
LF
|
58.000
|
$405.000
|
$2,000.000
|
$1,500.000
|
$840.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
1,846.000
|
$44.500
|
$86.000
|
$85.000
|
$84.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
658.000
|
$75.000
|
$121.000
|
$105.000
|
$126.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
195.000
|
$90.000
|
$165.000
|
$135.000
|
$157.500
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
67.000
|
$120.000
|
$211.000
|
$200.000
|
$262.500
|
|
|
RC PIPE (CL III)(42 IN)
|
LF
|
108.000
|
$150.000
|
$300.000
|
$300.000
|
$315.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
9.000
|
$280.000
|
$365.000
|
$350.000
|
$840.000
|
|
|
RC PIPE (CL IV)(24 IN)
|
LF
|
205.000
|
$110.000
|
$256.000
|
$135.000
|
$157.500
|
|
|
HEADWALL (CH - PW - 0) (DIA= 30 IN)
|
EA
|
4.000
|
$5,500.000
|
$8,100.000
|
$6,500.000
|
$9,400.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
4.000
|
$5,000.000
|
$11,000.000
|
$7,500.000
|
$11,550.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 42 IN)
|
EA
|
2.000
|
$9,000.000
|
$17,000.000
|
$11,500.000
|
$13,650.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 48 IN)
|
EA
|
2.000
|
$10,166.670
|
$22,000.000
|
$15,000.000
|
$15,750.000
|
|
|
WINGWALL (PW - 1) (HW=11 FT)
|
EA
|
1.000
|
$72,000.000
|
$38,000.000
|
$50,000.000
|
$73,500.000
|
|
|
WINGWALL (PW - 1) (HW=12 FT)
|
EA
|
1.000
|
$87,000.000
|
$41,000.000
|
$60,000.000
|
$84,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (P)
|
EA
|
4.000
|
$600.000
|
$1,200.000
|
$1,000.000
|
$840.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
116.000
|
$660.000
|
$1,000.000
|
$850.000
|
$1,155.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
14.000
|
$787.500
|
$1,400.000
|
$1,250.000
|
$945.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (P)
|
EA
|
2.000
|
$775.000
|
$2,500.000
|
$1,350.000
|
$1,050.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
30.000
|
$1,000.000
|
$1,500.000
|
$1,450.000
|
$1,260.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
8.000
|
$2,525.160
|
$3,500.000
|
$2,350.000
|
$2,100.000
|
|
|
REMOV STR (SET)
|
EA
|
20.000
|
$1,100.000
|
$600.000
|
$500.000
|
$210.000
|
|
|
REMOV STR (PIPE)
|
LF
|
2,611.000
|
$10.000
|
$10.000
|
$50.000
|
$15.750
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$512,809.850
|
$660,000.000
|
$700,000.000
|
$862,500.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
14.000
|
$12,000.000
|
$35,000.000
|
$8,500.000
|
$31,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,670.000
|
$28.000
|
$15.000
|
$30.000
|
$47.250
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,670.000
|
$7.000
|
$5.000
|
$15.000
|
$23.100
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
172.000
|
$23.000
|
$10.000
|
$40.000
|
$15.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
172.000
|
$8.000
|
$2.000
|
$20.000
|
$7.500
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
22,370.000
|
$2.000
|
$1.000
|
$4.000
|
$2.100
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
22,370.000
|
$0.500
|
$0.500
|
$2.000
|
$0.530
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
1,584.000
|
$4.000
|
$2.000
|
$18.000
|
$4.730
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,584.000
|
$0.750
|
$1.000
|
$9.000
|
$2.100
|
|
|
DRIVEWAYS (CONC)
|
SY
|
919.000
|
$91.670
|
$85.000
|
$85.000
|
$126.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
5,895.000
|
$45.000
|
$90.000
|
$45.000
|
$85.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
37,009.000
|
$0.350
|
$0.150
|
$0.500
|
$0.250
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
18,183.000
|
$0.350
|
$0.150
|
$0.500
|
$0.250
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
312.500
|
$21.250
|
$20.000
|
$28.000
|
$26.560
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$1,601.360
|
$1,800.000
|
$1,850.000
|
$3,495.720
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
180.000
|
$2.350
|
$3.000
|
$3.000
|
$5.250
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$175.000
|
$250.000
|
$500.000
|
$262.500
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
6.000
|
$2,524.120
|
$2,800.000
|
$3,250.000
|
$2,966.250
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
5.000
|
$375.000
|
$250.000
|
$1,000.000
|
$262.500
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
38.000
|
$235.000
|
$200.000
|
$850.000
|
$210.000
|
|
|
MAILBOX INSTALL-D (TWW-POST) TY 4
|
EA
|
2.000
|
$300.000
|
$250.000
|
$850.000
|
$262.500
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
3.000
|
$718.000
|
$500.000
|
$850.000
|
$525.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
123.000
|
$603.250
|
$575.000
|
$800.000
|
$612.150
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
2.000
|
$625.000
|
$690.000
|
$1,120.000
|
$913.500
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
1.000
|
$533.000
|
$715.000
|
$1,120.000
|
$829.500
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
2.000
|
$727.290
|
$895.000
|
$1,120.000
|
$945.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
|
EA
|
1.000
|
$1,200.000
|
$1,100.000
|
$1,120.000
|
$1,050.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
17.000
|
$27.000
|
$22.000
|
$100.000
|
$47.250
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
28.000
|
$19.000
|
$70.000
|
$100.000
|
$57.750
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
|
LF
|
1,181.000
|
$0.350
|
$0.400
|
$1.000
|
$0.420
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
41,955.000
|
$0.400
|
$0.260
|
$0.350
|
$0.270
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
2,454.000
|
$1.000
|
$1.000
|
$4.000
|
$5.250
|
|
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
|
LF
|
96.000
|
$2.000
|
$2.000
|
$6.000
|
$2.100
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
44.000
|
$3.460
|
$5.000
|
$6.000
|
$5.250
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
268.000
|
$6.500
|
$7.000
|
$20.000
|
$7.350
|
|
REFL PAV MRK TY II (W) (RR XING)
|
EA
|
2.000
|
$375.000
|
$300.000
|
$1,000.000
|
$315.000
|
|
|
PAVEMENT SEALER 6"
|
LF
|
2,056.000
|
$0.450
|
$0.560
|
$1.000
|
$0.590
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
47,967.000
|
$0.520
|
$0.560
|
$0.750
|
$0.590
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
1,181.000
|
$0.950
|
$0.600
|
$1.000
|
$0.630
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
41,955.000
|
$0.860
|
$0.560
|
$0.750
|
$0.590
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
589.000
|
$4.130
|
$4.000
|
$6.000
|
$4.200
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
2,056.000
|
$0.450
|
$0.250
|
$1.000
|
$0.260
|
|
|
RELOCT RDSD FLSH BCN AM (SOLAR PWRD)
|
EA
|
2.000
|
$4,000.000
|
$4,000.000
|
$15,000.000
|
$7,500.000
|
|
|
SP MIXES SP-B PG64-22
|
TON
|
10,566.000
|
$135.000
|
$168.000
|
$130.000
|
$157.500
|
|
|
SP MIXES SP-C SAC-B PG64-22
|
TON
|
9,551.000
|
$120.000
|
$169.000
|
$145.000
|
$147.000
|
|
|
TACK COAT
|
GAL
|
8,897.000
|
$4.170
|
$12.000
|
$6.000
|
$3.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$23,000.000
|
$16,500.000
|
$15,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
200.000
|
$130.000
|
$1.000
|
$250.000
|
$165.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
200.000
|
$125.000
|
$1.000
|
$65.000
|
$75.000
|
|
Totals: |
$5,851,893.905
|
$7,607,273.370
|
$8,170,885.500
|
$8,451,825.970
|