COLLIN FM 6 (0619-01-026)

Items: 87

County: COLLIN
Length: N/A
Highway: FM 6
District: DALLAS
Control Number: 0619-01-026
DBE Goal: N/A
Project: C 619-1-26
Guaranty: N/A
Time: 310 WORKING DAYS
Engineer's Estimate: $7,966,089.17
Date: 06/01/2022 (4 years ago)
Contract Number: N/A
Type: RESTORE EXISTING PAVEMENT, ADD SHOULDERS
Mail/Deliver Bids To: N/A
JENNIFER VORSTER
GERALD WALTMAN
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$7,966,089.17
$9,710,335.03
Over/Under Est: 21.9% $1,744,245.86
Over/Under Est: 22.07% $1,758,214.17
Amt Left: 0.14% $13,968.31
Over/Under Est: 23.07% $1,837,590.04
Amt Left: 0.96% $93,344.18
Delta: -0.82% -$79,375.87
Over/Under Est: 34.4% $2,740,084.10
Amt Left: 10.26% $995,838.24
Delta: -9.21% -$902,494.06
Over/Under Est: 56.59% $4,507,724.07
Amt Left: 28.46% $2,763,478.21
Delta: -16.51% -$1,767,639.97

Bid Items & Bid Tabulations

87 Total 0 of 87
COLLIN  |  FM 6  |  DALLAS  |  0619-01-026  |  06/01/2022  |  $7,966,089.17  |  C 619-1-26  |  RESTORE EXIST PAVMT, ADD SHOULDERS  |  310 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AUSTIN BRIDGE & ROAD SERVICES, LP
TEXAS MATERIALS GROUP, INC.
FOUTSCO PAVING COMPANY, LLC
A. K. GILLIS & SONS, LLC
ED BELL CONSTRUCTION COMPANY
PREPARING ROW
STA 407.000 $600.000 $1,000.000 $1,000.000 $50.000 $750.000 $750.000
REMOVING CONC (RIPRAP)
CY 13.000 $70.000 $144.040 $87.000 $15.000 $20.000 $210.000
REMOVING CONC (DRIVEWAYS)
SY 2,978.000 $12.000 $15.410 $18.000 $9.000 $12.000 $21.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 11,994.000 $6.550 $5.690 $3.000 $7.000 $18.530 $10.000
REMOVING STAB BASE & ASPH PAV (4"-12")
SY 7,738.000 $8.000 $8.450 $8.000 $6.000 $41.040 $12.000
EXCAVATION (ROADWAY)
CY 9,247.000 $12.000 $13.470 $19.000 $30.000 $18.950 $50.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 6,520.000 $13.000 $7.430 $11.000 $30.000 $15.590 $50.000
BACKFILL (TY A OR B)
STA 407.000 $225.000 $95.860 $210.000 $140.000 $350.400 $500.000
BLADING
STA 348.000 $100.000 $146.830 $120.000 $120.000 $301.500 $50.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 258,828.000 $0.120 $0.700 $0.155 $0.010 $0.140 $0.160
DRILL SEED (TEMP)(WARM OR COOL)
SY 258,828.000 $0.120 $0.660 $0.142 $0.010 $0.100 $0.120
VEGETATIVE WATERING
MG 77,006.000 $2.000 $0.030 $0.010 $0.010 $0.800 $0.010
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 11,674.000 $66.000 $73.800 $81.000 $90.000 $100.590 $84.000
PLANE ASPH CONC PAV (1" TO 3")
SY 116,744.000 $2.000 $1.520 $1.280 $1.000 $0.980 $1.500
RIPRAP (STONE COMMON)(GROUT)(12 IN)
CY 99.000 $225.000 $302.740 $72.000 $70.000 $289.490 $315.000
RC PIPE (CL III)(18 IN)
LF 3,640.000 $58.000 $70.340 $46.000 $45.000 $45.000 $50.000
RC PIPE (CL III)(24 IN)
LF 1,394.000 $68.000 $86.090 $77.000 $75.000 $65.000 $60.000
RC PIPE (CL III)(30 IN)
LF 322.000 $90.000 $104.510 $103.000 $100.000 $85.000 $90.000
RC PIPE (CL III)(36 IN)
LF 317.000 $130.000 $147.700 $142.000 $138.000 $125.000 $120.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 206.000 $700.000 $1,254.120 $770.000 $750.000 $675.000 $800.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 66.000 $1,000.000 $1,662.770 $985.000 $950.000 $1,100.000 $1,200.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 12.000 $2,300.000 $2,125.820 $2,100.000 $2,000.000 $3,200.000 $2,500.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 14.000 $4,000.000 $4,920.160 $4,650.000 $4,500.000 $6,500.000 $6,000.000
REMOV STR (SET)
EA 86.000 $300.000 $519.910 $310.000 $300.000 $150.000 $350.000
REMOV STR (HEADWALL)
EA 2.000 $1,000.000 $2,625.460 $1,040.000 $1,000.000 $800.000 $1,000.000
REMOV STR (PIPE)
LF 4,249.000 $15.000 $24.220 $15.550 $15.000 $10.000 $12.000
MOBILIZATION
LS 1.000 $724,000.000 $971,033.500 $653,708.000 $900,000.000 $866,657.000 $1,300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $10,000.000 $30,000.000 $16,000.000 $4,000.000 $19,100.000 $52,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 620.000 $28.000 $32.000 $37.000 $10.000 $32.000 $34.000
ROCK FILTER DAMS (REMOVE)
LF 620.000 $8.750 $8.000 $14.000 $5.000 $8.000 $16.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 166.000 $24.000 $15.000 $20.000 $10.000 $15.000 $23.000
CONSTRUCTION EXITS (REMOVE)
SY 166.000 $8.500 $5.000 $14.000 $5.000 $5.000 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 10,265.000 $1.800 $3.000 $1.850 $3.000 $3.000 $1.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 10,265.000 $0.500 $0.500 $0.490 $1.000 $0.500 $0.200
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,850.000 $3.000 $5.000 $3.500 $5.000 $5.000 $3.850
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,850.000 $1.100 $0.750 $1.080 $1.000 $0.750 $1.000
INTERSECTIONS (CONC)
SY 1,017.000 $90.000 $194.000 $120.000 $110.000 $95.000 $110.000
INTERSECTIONS (ACP)
SY 3,614.000 $50.000 $43.640 $56.000 $55.000 $45.370 $55.000
DRIVEWAYS (CONC)
SY 1,961.000 $85.000 $90.000 $105.000 $100.000 $95.000 $115.000
DRIVEWAYS (ACP)
SY 8,380.000 $40.000 $41.830 $61.000 $60.000 $44.020 $63.000
RUMBLE STRIPS (SHOULDER)
LF 63,368.000 $0.350 $0.180 $0.085 $0.120 $0.140 $0.120
RUMBLE STRIPS (CENTERLINE)
LF 31,684.000 $0.350 $0.200 $0.085 $0.120 $0.140 $0.120
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 55.000 $255.000 $269.000 $335.000 $270.000 $269.000 $282.450
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 4.000 $270.000 $299.000 $408.000 $300.000 $299.000 $313.950
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 4.000 $580.000 $669.000 $820.000 $700.000 $669.000 $702.450
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 112.000 $500.000 $588.000 $890.000 $600.000 $588.000 $617.400
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 8.000 $575.000 $758.000 $955.000 $800.000 $758.000 $795.900
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 5.000 $820.000 $969.000 $1,160.000 $1,000.000 $696.000 $1,017.450
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 12.000 $850.000 $1,067.000 $1,275.000 $1,100.000 $1,067.000 $1,120.350
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 2.000 $1,000.000 $1,269.000 $1,465.000 $1,300.000 $1,269.000 $1,332.450
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 9.000 $1,000.000 $1,287.000 $1,570.000 $1,350.000 $1,287.000 $1,351.350
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 20.000 $50.000 $69.000 $71.500 $75.000 $69.000 $73.240
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 3,480.000 $0.400 $0.360 $0.370 $0.400 $0.320 $1.050
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 65,520.000 $0.250 $0.290 $0.300 $0.320 $0.320 $0.530
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,120.000 $1.850 $1.500 $1.100 $0.750 $2.250 $3.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 305.000 $0.800 $0.940 $0.970 $1.000 $1.000 $1.370
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 458.000 $9.450 $6.550 $6.750 $7.000 $7.500 $6.830
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 2.000 $140.000 $125.000 $129.000 $125.000 $175.000 $183.750
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 2.000 $175.000 $150.000 $155.000 $150.000 $200.000 $278.250
PAVEMENT SEALER 4"
LF 3,691.000 $0.200 $0.110 $0.115 $0.110 $0.260 $0.210
PAVEMENT SEALER 8"
LF 305.000 $0.450 $0.220 $0.230 $0.220 $0.520 $0.320
PAVEMENT SEALER 24"
LF 50.000 $1.750 $1.200 $1.250 $1.200 $2.000 $2.360
PAVEMENT SEALER (ARROW)
EA 2.000 $24.000 $22.000 $23.000 $22.000 $25.000 $21.000
PAVEMENT SEALER (WORD)
EA 2.000 $35.000 $28.000 $29.000 $28.000 $35.000 $36.750
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 440.000 $0.450 $0.460 $0.470 $0.500 $1.000 $0.680
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 77,918.000 $0.350 $0.450 $0.460 $0.500 $0.470 $0.490
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 2,500.000 $0.450 $0.640 $0.660 $0.700 $0.750 $0.680
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 3,480.000 $0.300 $0.520 $0.540 $0.550 $0.600 $0.630
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 65,520.000 $0.350 $0.450 $0.460 $0.450 $0.470 $0.470
REFL PAV MRKR TY II-A-A
EA 986.000 $2.900 $4.000 $4.150 $4.000 $4.000 $4.990
REFL PAV MRKR TY II-C-R
EA 21.000 $3.900 $4.000 $4.150 $4.000 $5.000 $4.990
ELIM EXT PAV MRK & MRKS (4")
LF 3,691.000 $0.500 $0.500 $0.520 $0.500 $2.030 $1.050
ELIM EXT PAV MRK & MRKS (8")
LF 305.000 $0.900 $0.720 $0.740 $0.750 $4.060 $2.100
ELIM EXT PAV MRK & MRKS (24")
LF 50.000 $3.000 $3.050 $3.110 $3.100 $12.170 $4.200
ELIM EXT PAV MRK & MRKS (ARROW)
EA 2.000 $50.000 $36.000 $37.000 $36.000 $109.530 $105.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 2.000 $60.000 $42.000 $43.000 $42.000 $121.700 $105.000
PAV SURF PREP FOR MRK (4")
LF 3,691.000 $0.150 $0.050 $0.021 $0.030 $0.200 $0.050
PAV SURF PREP FOR MRK (8")
LF 305.000 $0.350 $0.140 $0.073 $0.070 $0.400 $0.110
PAV SURF PREP FOR MRK (24")
LF 50.000 $1.050 $0.460 $0.480 $0.500 $2.000 $0.350
PAV SURF PREP FOR MRK (ARROW)
EA 2.000 $16.750 $11.250 $11.850 $12.000 $25.000 $10.500
PAV SURF PREP FOR MRK (WORD)
EA 2.000 $27.000 $13.250 $13.750 $15.000 $35.000 $21.000
SP MIXES SP-B SAC-B PG64-22
TON 21,280.000 $80.000 $94.500 $115.000 $135.000 $121.800 $130.000
SP MIXES SP-C SAC-B PG64-22
TON 15,395.000 $90.000 $98.000 $122.000 $123.000 $130.350 $150.000
TACK COAT
GAL 10,951.000 $3.000 $4.000 $3.500 $0.010 $4.750 $1.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $17,600.000 $16,500.000 $20,000.000 $15,000.000 $15,000.000
TMA (STATIONARY)
DAY 310.000 $250.000 $160.000 $320.000 $100.000 $150.000 $157.500
TMA (MOBILE OPERATION)
HR 350.000 $100.000 $1.130 $42.000 $10.000 $150.000 $73.500
Totals: $7,966,089.170 $9,710,335.030 $9,724,303.357 $9,803,679.210 $10,706,173.270 $12,473,813.240