COLLIN FM 75 (0387-01-014)

Items: 58

County: COLLIN
Length: N/A
Highway: FM 75
District: DALLAS
Control Number: 0387-01-014
DBE Goal: N/A
Project: STP 1702(817)
Guaranty: N/A
Time: 105 WORKING DAYS
Engineer's Estimate: $1,317,598.43
Date: 08/08/2017 (8 years ago)
Contract Number: N/A
Type: WIDEN, OVERLAY, BASE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$1,317,598.43
$1,442,556.40
Over/Under Est: 9.48% $124,957.97
Over/Under Est: 14.55% $191,736.26
Amt Left: 4.63% $66,778.29
Over/Under Est: 17.26% $227,398.53
Amt Left: 7.1% $102,440.56
Delta: -2.36% -$35,662.27
Over/Under Est: 17.96% $236,602.18
Amt Left: 7.74% $111,644.21
Delta: -0.60% -$9,203.65
Over/Under Est: 21.1% $278,059.67
Amt Left: 10.61% $153,101.70
Delta: -2.67% -$41,457.49
$1,839,197.00
Over/Under Est: 39.59% $521,598.57
Amt Left: 27.5% $396,640.60
Delta: -15.26% -$243,538.90

Bid Items & Bid Tabulations

58 Total 0 of 58
COLLIN  |  FM 75  |  DALLAS  |  0387-01-014  |  08/08/2017  |  $1,317,598.43  |  STP 1702(817)  |  WIDEN, OVERLAY, BASE REPAIR  |  105 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAGOE-PUBLIC COMPANY
OLDCASTLE MATERIALS TEXAS, INC.
THE LANE CONSTRUCTION CORPORATION
AUSTIN BRIDGE & ROAD SERVICES, LP
ED BELL CONSTRUCTION COMPANY
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 57.800 $500.000 $900.000 $2,255.000 $900.000 $2,000.000 $3,750.000 $2,000.000
REMOVING CONC (DRIVEWAYS)
SY 350.000 $25.000 $35.000 $15.000 $25.000 $35.000 $21.000 $20.000
EXCAVATION (ROADWAY)
CY 58.000 $10.000 $50.000 $46.000 $40.000 $50.000 $21.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 477.000 $20.000 $42.000 $24.000 $50.000 $53.000 $31.500 $35.000
BACKFILL (TY A OR B)
STA 57.800 $189.000 $400.000 $235.000 $500.000 $380.000 $105.000 $350.000
BLADING
STA 57.800 $110.000 $125.000 $245.000 $250.000 $65.000 $525.000 $250.000
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
SY 24,413.000 $0.300 $0.400 $0.400 $0.450 $0.380 $0.550 $0.500
DRILL SEED (TEMP)(WARM OR COOL)
SY 24,413.000 $0.150 $0.180 $0.175 $0.170 $0.170 $0.100 $0.500
VEGETATIVE WATERING
MG 3,253.000 $12.000 $28.000 $0.010 $25.500 $1.000 $1.050 $20.000
SUPERPAVE MIXTURES SP-C SAC-B PG64-22
TON 3,944.000 $82.000 $75.000 $76.000 $85.000 $88.000 $75.600 $90.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 1,630.000 $64.000 $50.000 $74.000 $45.000 $65.000 $52.500 $85.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 16,508.000 $2.000 $2.000 $1.800 $1.000 $3.000 $1.540 $4.000
PLAN & TEXT ASPH CONC PAV(0" TO 4")
SY 13,840.000 $3.000 $2.950 $3.100 $2.250 $5.000 $2.360 $4.000
CUT & RESTORING PAV
SY 231.000 $125.000 $185.000 $96.000 $135.000 $125.000 $168.000 $200.000
TRENCH EXCAVATION PROTECTION
LF 214.000 $5.000 $11.000 $0.100 $2.000 $20.000 $8.400 $3.500
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 54.000 $168.000 $200.000 $135.000 $115.000 $185.000 $116.500 $185.000
CONC BOX CULV (8 FT X 4 FT)
LF 45.000 $500.000 $550.000 $525.000 $510.000 $516.000 $525.000 $1,000.000
RC PIPE (CL III)(18 IN)
LF 1,174.000 $60.000 $75.000 $47.000 $90.000 $46.500 $63.000 $75.000
RC PIPE (CL III)(24 IN)
LF 128.000 $75.000 $135.000 $58.000 $100.000 $57.000 $84.000 $95.000
RC PIPE (CL III)(36 IN)
LF 76.000 $140.000 $180.000 $152.000 $160.000 $150.000 $189.000 $125.000
RC PIPE (CL III)(42 IN)
LF 60.000 $130.000 $235.000 $171.000 $195.000 $171.000 $220.500 $185.000
RC PIPE (CL III)(48 IN)
LF 113.000 $188.500 $280.000 $260.000 $220.000 $258.000 $262.500 $250.000
HEADWALL (CH - FW - 0) (DIA= 36 IN)
EA 2.000 $5,800.000 $5,700.000 $4,700.000 $5,900.000 $4,650.000 $5,250.000 $5,000.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 2.000 $4,000.000 $5,500.000 $3,700.000 $4,800.000 $3,610.000 $4,200.000 $5,000.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 2.000 $6,200.000 $7,000.000 $4,150.000 $5,500.000 $4,125.000 $5,250.000 $5,000.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 4.000 $9,000.000 $12,000.000 $5,250.000 $10,500.000 $5,155.000 $9,450.000 $8,500.000
WINGWALL (PW - 1) (HW=6 FT)
EA 2.000 $13,000.000 $14,000.000 $17,000.000 $12,650.000 $17,050.000 $12,600.000 $12,000.000
SET (TY II) (18 IN) (RCP) (3: 1) (P)
EA 102.000 $720.000 $650.000 $875.000 $900.000 $877.000 $630.000 $1,250.000
SET (TY II) (42 IN) (RCP) (3: 1) (P)
EA 2.000 $4,637.000 $5,350.000 $1,875.000 $5,000.000 $3,800.000 $6,300.000 $6,500.000
REMOV STR (HEADWALL)
EA 2.000 $1,280.000 $650.000 $775.000 $2,250.000 $775.000 $1,680.000 $1,500.000
REMOV STR (PIPE)
LF 1,403.000 $15.000 $14.000 $10.550 $16.000 $11.000 $16.800 $30.000
MOBILIZATION
LS 1.000 $120,000.000 $140,000.000 $150,015.000 $75,000.000 $150,000.000 $172,000.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $9,000.000 $7,500.000 $26,000.000 $33,000.000 $8,250.000 $21,000.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 140.000 $31.000 $43.000 $41.000 $24.500 $40.660 $25.730 $30.000
ROCK FILTER DAMS (REMOVE)
LF 140.000 $12.000 $11.500 $11.000 $10.000 $10.950 $10.500 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 155.600 $28.000 $37.000 $36.000 $22.500 $35.210 $20.210 $45.000
CONSTRUCTION EXITS (REMOVE)
SY 155.600 $8.300 $10.500 $10.100 $13.000 $10.060 $10.500 $20.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 140.000 $5.000 $5.700 $5.450 $4.500 $5.420 $4.730 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 140.000 $1.200 $1.000 $0.960 $1.000 $0.920 $1.050 $8.000
DRIVEWAYS (CONC)
SY 350.000 $85.000 $80.000 $93.000 $80.000 $106.000 $105.000 $85.000
DRIVEWAYS (ACP)
SY 2,054.000 $30.000 $19.000 $41.000 $37.000 $54.000 $32.730 $38.000
TURNOUTS (ACP)
SY 82.000 $61.000 $60.000 $102.000 $32.000 $130.000 $78.930 $35.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 31.000 $220.000 $240.000 $230.000 $225.000 $225.000 $246.750 $650.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 2.000 $275.000 $240.000 $275.000 $225.000 $270.000 $257.250 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 31.000 $470.000 $420.000 $450.000 $400.000 $445.000 $480.900 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 9.000 $550.000 $525.000 $510.000 $500.000 $505.000 $567.000 $650.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $667.000 $735.000 $575.000 $700.000 $570.000 $635.250 $650.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $750.000 $735.000 $750.000 $700.000 $745.000 $868.350 $650.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 6.000 $50.000 $52.500 $47.000 $50.000 $45.000 $47.250 $100.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 20.000 $57.000 $52.500 $47.000 $50.000 $45.000 $49.350 $100.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 2,601.000 $0.300 $1.000 $1.050 $1.000 $1.000 $1.200 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 578.000 $1.100 $0.750 $1.020 $2.300 $0.400 $1.200 $5.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 24.000 $2.300 $1.250 $1.030 $1.000 $1.000 $1.050 $10.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 215.000 $3.500 $5.250 $5.250 $5.000 $5.000 $5.250 $10.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 252.000 $6.500 $7.500 $7.350 $7.100 $7.100 $7.460 $20.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 10,994.000 $0.350 $0.410 $0.420 $0.400 $0.390 $0.410 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 11,196.000 $0.350 $0.420 $0.420 $0.400 $0.400 $0.420 $0.500
REFL PAV MRKR TY II-A-A
EA 143.000 $3.100 $5.250 $5.200 $5.000 $5.000 $5.250 $15.000
Totals: $1,317,598.430 $1,442,556.400 $1,509,334.695 $1,544,996.960 $1,554,200.622 $1,595,658.106 $1,839,197.000