COLLIN SH 5 (0047-09-033)

Items: 50

County: COLLIN
Length: N/A
Highway: SH 5
District: DALLAS
Control Number: 0047-09-033
DBE Goal: N/A
Project: STP 2019(257)
Guaranty: N/A
Time: 126 WORKING DAYS
Engineer's Estimate: $1,908,411.45
Date: 12/05/2018 (7 years ago)
Contract Number: N/A
Type: MILL, BASE REPAIR, OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,908,411.45
$1,873,091.10
Over/Under Est: -1.85% -$35,320.35
Over/Under Est: 4.56% $87,050.75
Amt Left: 6.53% $122,371.10
Over/Under Est: 8.21% $156,738.42
Amt Left: 10.25% $192,058.77
Delta: -3.49% -$69,687.67
Over/Under Est: 24.78% $472,951.52
Amt Left: 27.14% $508,271.87
Delta: -15.31% -$316,213.10
$2,524,295.79
Over/Under Est: 32.27% $615,884.34
Amt Left: 34.77% $651,204.69
Delta: -6.00% -$142,932.82

Bid Items & Bid Tabulations

50 Total 0 of 50
COLLIN  |  SH 5  |  DALLAS  |  0047-09-033  |  12/05/2018  |  $1,908,411.45  |  STP 2019(257)  |  MILL, BASE REPAIR, OVERLAY  |  126 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
THE LANE CONSTRUCTION CORPORATION
AUSTIN BRIDGE & ROAD SERVICES, LP
REYNOLDS ASPHALT & CONSTRUCTION COMPANY
JAGOE-PUBLIC COMPANY
PREPARING ROW
STA 148.000 $500.000 $150.000 $200.000 $100.000 $250.000 $1,100.000
SUBGRADE WIDENING (ORD COMP)
STA 20.560 $290.000 $1,600.000 $2,000.000 $4,950.000 $2,500.000 $3,250.000
BACKFILL (TY A OR B)
STA 143.200 $140.000 $150.000 $225.000 $305.000 $300.000 $172.000
BLADING
STA 20.560 $60.000 $1,600.000 $150.000 $300.000 $400.000 $285.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 1,740.000 $0.100 $1.000 $1.000 $1.020 $1.200 $1.050
VEGETATIVE WATERING
MG 57.000 $7.000 $25.000 $70.000 $133.000 $145.120 $45.000
SUPERPAVE MIXTURES SP-B PG64-22
TON 2,564.000 $68.000 $93.000 $83.000 $98.000 $100.000 $83.000
SUPERPAVE MIXTURES SP-C SAC-B PG64-22
TON 7,481.000 $80.000 $91.000 $83.000 $89.000 $95.000 $88.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 3,550.000 $53.000 $40.000 $44.000 $48.000 $75.000 $68.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 3,356.000 $65.000 $43.000 $49.000 $54.000 $90.000 $81.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 35,514.000 $1.750 $2.000 $2.000 $2.000 $2.100 $1.270
MOBILIZATION
LS 1.000 $179,000.000 $168,000.000 $125,000.000 $205,000.000 $150,000.000 $230,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,000.000 $8,000.000 $23,000.000 $7,500.000 $16,700.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 500.000 $25.000 $30.000 $24.500 $28.350 $32.600 $26.500
ROCK FILTER DAMS (REMOVE)
LF 500.000 $6.000 $4.000 $8.000 $12.990 $14.900 $8.700
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $1.750 $7.000 $5.000 $13.430 $15.400 $5.400
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $0.500 $2.000 $1.000 $3.780 $4.300 $1.100
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 100.000 $3.750 $9.000 $4.750 $10.170 $11.700 $5.200
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $0.550 $3.000 $1.000 $5.070 $5.800 $1.100
DRIVEWAYS (ACP)
SY 967.000 $30.000 $21.000 $29.000 $28.000 $16.900 $18.500
RUMBLE STRIPS (CENTERLINE)
LF 5,450.000 $0.750 $1.000 $0.650 $1.100 $3.450 $1.700
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,044.000 $0.450 $0.600 $0.800 $1.970 $2.300 $0.620
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 1,150.000 $0.500 $1.200 $1.550 $1.190 $1.150 $1.250
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 3,090.000 $0.300 $0.600 $0.800 $1.190 $1.150 $0.620
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 253.000 $0.750 $0.600 $2.000 $1.000 $1.730 $0.600
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,559.000 $0.800 $0.600 $1.500 $1.000 $1.730 $0.600
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 6,354.000 $1.000 $1.100 $1.300 $0.960 $1.040 $1.050
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 260.000 $5.000 $6.600 $7.750 $7.240 $6.330 $6.250
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 52.000 $120.000 $110.000 $122.500 $133.000 $167.000 $99.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 40.000 $150.000 $130.000 $155.000 $159.000 $207.000 $125.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 1,440.000 $6.750 $6.600 $7.750 $6.560 $5.980 $6.250
PAVEMENT SEALER 4"
LF 5,820.000 $0.150 $0.220 $0.250 $0.200 $0.290 $0.210
PAVEMENT SEALER 8"
LF 550.000 $0.330 $0.660 $0.800 $0.400 $0.290 $0.620
PAVEMENT SEALER 24"
LF 56.000 $2.300 $2.400 $3.000 $1.740 $2.880 $2.300
PAVEMENT SEALER (ARROW)
EA 5.000 $24.000 $35.000 $41.500 $100.000 $57.500 $34.000
PAVEMENT SEALER (WORD)
EA 5.000 $38.000 $45.000 $53.000 $100.000 $86.300 $43.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 21,194.000 $0.400 $0.450 $0.550 $0.380 $1.150 $0.420
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,150.000 $0.380 $0.550 $0.600 $1.000 $1.150 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 40,690.000 $0.400 $0.450 $0.500 $0.380 $1.150 $0.420
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 78,788.000 $0.600 $0.750 $0.850 $0.770 $1.150 $0.700
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 24,204.000 $0.800 $0.750 $0.900 $0.770 $1.150 $0.700
REFL PAV MRKR TY I-C
EA 322.000 $4.400 $5.000 $5.800 $3.550 $4.890 $4.650
REFL PAV MRKR TY II-A-A
EA 1,027.000 $3.000 $5.000 $5.800 $3.550 $4.310 $4.650
ELIM EXT PAV MRK & MRKS (4")
LF 5,960.000 $0.500 $0.750 $1.000 $1.300 $1.150 $0.780
ELIM EXT PAV MRK & MRKS (8")
LF 80.000 $0.700 $1.500 $2.000 $5.000 $2.300 $1.560
ELIM EXT PAV MRK & MRKS (24")
LF 46.000 $3.500 $4.000 $5.250 $15.000 $4.030 $4.150
ELIM EXT PAV MRK & MRKS (ARROW)
EA 1.000 $45.000 $65.000 $85.000 $500.000 $115.000 $68.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 1.000 $58.000 $75.000 $100.000 $500.000 $230.000 $77.000
TMA (STATIONARY)
EA 2.000 $5,000.000 $20,000.000 $25,000.000 $13,500.000 $17,500.000 $42,000.000
TMA (MOBILE OPERATION)
HR 1,152.000 $115.000 $25.000 $100.000 $46.000 $17.250 $204.000
Totals: $1,908,411.450 $1,873,091.100 $1,995,462.200 $2,065,149.870 $2,381,362.970 $2,524,295.790