Show Job Controls
Bid Cobra

COLEMAN US 283 (0099-01-035)

Items: 77

County: COLEMAN
Length: N/A
Highway: US 283
District: BROWNWOOD
Control Number: 0099-01-035
DBE Goal: N/A
Project: STP 2022(260)HES
Guaranty: N/A
Time: 199 WORKING DAYS
Engineer's Estimate: $2,950,129.90
Date: 01/07/2022 (4 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$2,950,129.90
$3,177,408.86
Over/Under Est: 7.7% $227,278.96
$3,768,855.10
Over/Under Est: 27.75% $818,725.20
Amt Left: 18.61% $591,446.24
$4,041,742.24
Over/Under Est: 37% $1,091,612.34
Amt Left: 27.2% $864,333.38
Delta: -7.24% -$272,887.14

Bid Items & Bid Tabulations

77 Total 0 of 77
COLEMAN  |  US 283  |  BROWNWOOD  |  0099-01-035  |  01/07/2022  |  $2,950,129.90  |  STP 2022(260)HES  |  HWY IMPRV  |  199 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. H. STRAIN & SONS, INC.
PRATER DIRT WORK LLC
REECE ALBERT, INC.
PREPARING ROW
STA 129.000 $130.000 $310.000 $380.000 $1,582.540
PREP ROW (TREE)(24"-30"DIA)
EA 3.000 $1,200.000 $2,000.000 $2,000.000 $1,575.050
REMOVING CONC (CURB)
LF 186.000 $12.000 $15.000 $15.000 $10.600
EXCAVATION (ROADWAY)
CY 10,935.000 $12.000 $14.000 $24.000 $7.640
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 4,300.000 $15.000 $11.000 $19.000 $7.770
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 10.500 $835.000 $500.000 $480.000 $711.020
DRILL SEEDING (TEMP) (WARM)
AC 5.250 $685.000 $500.000 $440.000 $450.010
DRILL SEEDING (TEMP) (COOL)
AC 5.250 $685.000 $500.000 $440.000 $450.010
PROOF ROLLING
HR 4.000 $100.000 $100.000 $200.000 $73.470
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 14,219.000 $45.000 $45.000 $61.000 $63.250
PRIME COAT (RC-250)
GAL 8,074.000 $5.000 $5.000 $6.000 $5.040
ASPH (AC-20-5TR)
GAL 29,354.000 $5.000 $5.000 $4.450 $4.170
AGGR(TY-B GR-5 SAC-B)
CY 294.000 $150.000 $120.000 $190.000 $131.660
AGGR(TY-PB GR-4 SAC-B)
CY 668.000 $100.000 $120.000 $165.000 $176.640
PLAN & TEXT CONC PAV(0" TO 1")
SY 22,532.000 $0.750 $1.000 $1.000 $2.220
PLAN & TEXT CONC PAV(0" TO 1-1/2")
SY 889.000 $2.000 $3.000 $2.000 $3.550
PLAN & TEXT ASPH CONC PAV (1")
SY 33,798.000 $0.750 $1.100 $1.000 $2.320
CL C CONC (CULV)
CY 3.800 $2,000.000 $1,400.000 $4,400.000 $1,406.290
RIPRAP (CONC)(5 IN)
CY 12.000 $1,200.000 $560.000 $1,000.000 $562.520
RETROFIT RAIL (TY T631)
LF 430.000 $80.000 $90.000 $105.000 $10.130
CMP AR (GAL STL DES 3)
LF 166.000 $110.000 $125.000 $210.000 $123.750
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 4.000 $5,500.000 $8,400.000 $9,500.000 $8,437.750
SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1) (C)
EA 2.000 $8,500.000 $10,650.000 $11,000.000 $10,687.810
SET (TY I)(S= 7 FT)(HW= 4 FT)(4:1) (C)
EA 2.000 $10,000.000 $11,760.000 $15,500.000 $11,812.850
SET (TY II) (42 IN) (CMP) (4: 1) (C)
EA 2.000 $3,500.000 $7,850.000 $4,700.000 $7,875.230
SET (TY II) (DES 3) (CMP) (6: 1) (P)
EA 12.000 $2,000.000 $3,375.000 $2,650.000 $3,375.100
SET (TY II) (DES 4) (CMP) (4: 1) (C)
EA 2.000 $3,000.000 $4,000.000 $3,650.000 $3,937.620
REMOV STR (PIPE)
EA 6.000 $400.000 $560.000 $1,550.000 $562.520
MOBILIZATION
LS 1.000 $280,000.000 $195,000.000 $120,000.000 $398,285.900
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $5,000.000 $3,000.000 $6,250.000 $18,228.440
ROCK FILTER DAMS (REMOVE)
LF 80.000 $15.000 $10.000 $15.000 $12.960
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,200.000 $5.000 $5.000 $4.000 $2.590
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,200.000 $1.000 $2.000 $1.000 $1.130
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,400.000 $7.000 $6.000 $5.000 $2.250
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,400.000 $1.000 $2.000 $1.000 $0.900
ROCK FILTER DAMS (INSTALL) (TY 1) (6:1)
LF 80.000 $40.000 $65.000 $50.000 $67.500
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 450.000 $65.000 $100.000 $95.000 $101.250
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 1,350.000 $6.000 $18.000 $17.000 $16.880
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 450.000 $15.000 $25.000 $30.000 $25.310
CONC CURB (MOD) (TYPE I)
LF 186.000 $65.000 $56.000 $52.500 $56.250
INTERSECTIONS (ACP)
SY 372.000 $50.000 $45.000 $60.000 $95.680
DRIVEWAYS (SURF TREAT)
SY 629.000 $30.000 $30.000 $30.000 $44.530
TURNOUTS (ACP)
SY 15.000 $60.000 $75.000 $60.000 $375.800
RUMBLE STRIPS (SHOULDER)
LF 25,748.000 $0.400 $0.370 $0.300 $0.190
RUMBLE STRIPS (CENTERLINE)
LF 12,874.000 $0.300 $0.370 $0.300 $0.270
MTL W-BEAM GD FEN (STEEL POST)
LF 800.000 $31.000 $39.000 $37.000 $41.630
REMOVE METAL BEAM GUARD FENCE
LF 1,300.000 $4.000 $2.250 $3.000 $3.380
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,500.000 $3,415.000 $3,800.000 $3,937.620
CRASH CUSH ATTEN (MOVE & RESET)
EA 6.000 $2,000.000 $2,750.000 $2,650.000 $2,812.580
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,000.000 $1,100.000 $1,100.000 $1,125.030
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $7,700.000 $7,000.000 $7,875.230
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 1.000 $350.000 $540.000 $600.000 $483.770
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $625.000 $775.000 $1,125.000 $951.780
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 3.000 $695.000 $960.000 $1,200.000 $1,121.660
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $760.000 $1,350.000 $1,550.000 $1,562.670
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 10.000 $340.000 $540.000 $805.000 $714.400
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 9.000 $430.000 $640.000 $900.000 $748.150
REMOVE SM RD SN SUP&AM
EA 16.000 $115.000 $22.500 $110.000 $197.320
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 16.000 $30.000 $22.000 $30.000 $20.250
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 36.000 $30.000 $25.750 $110.000 $39.380
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 12.000 $60.000 $100.000 $100.000 $101.250
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 24,000.000 $0.500 $0.340 $0.330 $0.340
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 24,000.000 $0.500 $0.390 $0.380 $0.390
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 300.000 $3.000 $5.120 $5.000 $5.230
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,488.000 $1.500 $1.750 $2.000 $1.140
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 738.000 $0.600 $1.000 $1.000 $1.010
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 34.000 $11.000 $22.000 $22.000 $22.500
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 4.000 $400.000 $880.000 $880.000 $900.030
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 4,172.000 $0.500 $0.450 $0.450 $0.460
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 25,544.000 $0.600 $0.400 $0.400 $0.420
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 25,848.000 $0.600 $0.400 $0.400 $0.410
REFL PAV MRKR TY I-C
EA 210.000 $5.000 $5.120 $5.000 $5.230
REFL PAV MRKR TY II-A-A
EA 324.000 $5.000 $5.120 $5.000 $5.230
SP MIXES SP-C SAC-B PG76-22
TON 8,654.000 $100.000 $122.660 $141.000 $127.850
BONDING COURSE
GAL 5,398.000 $2.000 $3.500 $4.000 $4.490
TMA (STATIONARY)
DAY 100.000 $261.000 $250.000 $300.000 $328.150
TMA (MOBILE OPERATION)
HR 320.000 $65.000 $70.000 $60.000 $63.600
Totals: $2,950,129.900 $3,177,408.860 $3,768,855.100 $4,041,742.247