COLEMAN US 84 (0054-04-113)

Items: 76

County: COLEMAN
Length: 0.3980 MILES
Highway: US 84
District: BROWNWOOD
Control Number: 0054-04-113
DBE Goal: 6.0%
Project: BR 2025(084)
Guaranty: $56,000.00
Time: 107 WORKING DAYS
Engineer's Estimate: $2,804,984.30
Date: 10/01/2024 (1 year ago)
Contract Number: 10243017
Type: BRIDGE MAINTENANCE
Project ID: A00063008
Project Description: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (9)
E
Engineer's Estimate
$2,804,984.30
$2,768,114.50
Over/Under Est: -1.31% -$36,869.80
Over/Under Est: -1.07% -$29,900.45
Amt Left: 0.25% $6,969.35
$2,987,736.80
Over/Under Est: 6.52% $182,752.50
Amt Left: 7.93% $219,622.30
Delta: -7.66% -$212,652.95
Over/Under Est: 9.64% $270,380.77
Amt Left: 11.1% $307,250.57
Delta: -2.93% -$87,628.27
Over/Under Est: 10.29% $288,496.55
Amt Left: 11.75% $325,366.35
Delta: -0.59% -$18,115.78
$3,347,383.00
Over/Under Est: 19.34% $542,398.70
Amt Left: 20.93% $579,268.50
Delta: -8.21% -$253,902.15
Over/Under Est: 19.86% $556,988.90
Amt Left: 21.45% $593,858.70
Delta: -0.44% -$14,590.20
Over/Under Est: 22.18% $622,015.10
Amt Left: 23.8% $658,884.90
Delta: -1.93% -$65,026.20
Over/Under Est: 84.74% $2,376,812.70
Amt Left: 87.2% $2,413,682.50
Delta: -51.21% -$1,754,797.60
Subcontractor Percentage Amount
STONE RIVER BRIDGE, LLC 41.77% $1,156,241.43
TEXCO SERVICES, LLC 8.76% $242,486.83
SJ&J CONSTRUCTION, LLC 3.75% $103,804.29
FC TRAFFIC CONTROL, INC. 1.05% $29,065.20
TEXAS CUTTING & CORING, LP 0.18% $4,982.61
Total: 55.51% $1,536,580.36

Bid Items & Bid Tabulations

76 Total 0 of 76
COLEMAN  |  US 84  |  BROWNWOOD  |  0054-04-113  |  10/01/2024  |  $2,804,984.30  |  BR 2025(084)  |  BRIDGE MAINT  |  107 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ICOS MANAGEMENT, LLC
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
THK CONSTRUCTION LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
BLACKSMITH VENTURES LLC
FNH CONSTRUCTION, LLC
SCR CIVIL CONSTRUCTION, LLC
STRUCTURAL INTEGRITY GROUP LLC
SOUTHERN ROAD & BRIDGE, LLC
PREPARING ROW
STA 1.000 $10,000.000 $8,000.000 $7,606.800 $5,000.000 $5,000.000 $25,000.000 $150,000.000 $30,000.000 $4,000.000 $85,000.000
EXCAV (CHANNEL)
CY 192.000 $75.000 $100.000 $91.200 $30.000 $250.000 $50.000 $30.000 $196.000 $60.000 $125.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 142.000 $10.000 $15.000 $9.100 $20.680 $1.000 $2.000 $2.000 $15.000 $1.000 $30.000
BROADCAST SEED (TEMP_WARM)
SY 446.000 $6.000 $5.000 $6.100 $20.130 $1.000 $2.000 $2.000 $10.000 $1.000 $30.000
BROADCAST SEED (TEMP_COOL)
SY 446.000 $6.000 $5.000 $6.100 $20.130 $1.000 $2.000 $2.000 $10.000 $1.000 $30.000
PLAN & TEXT CONC PAV(0" TO 3")
SY 1,044.000 $12.000 $15.000 $16.500 $29.010 $15.000 $8.000 $20.000 $23.600 $19.000 $19.000
FLOWABLE BACKFILL
CY 13.000 $1,600.000 $600.000 $1,093.400 $1,000.000 $600.000 $1,000.000 $350.000 $1,615.000 $1,000.000 $550.000
CL B CONC (MISC)
CY 160.000 $1,450.000 $800.000 $451.500 $937.500 $850.000 $500.000 $800.000 $1,072.000 $905.000 $550.000
REINF CONC SLAB
SF 1,913.000 $50.000 $70.000 $66.600 $55.000 $125.000 $125.000 $35.000 $87.050 $86.000 $100.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 243.500 $40.000 $30.000 $88.300 $86.250 $80.000 $75.000 $45.000 $56.000 $90.000 $22.000
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 48.500 $400.000 $200.000 $169.700 $300.000 $300.000 $300.000 $1,000.000 $416.000 $115.000 $55.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 6.000 $1,200.000 $600.000 $252.600 $300.000 $350.000 $1,000.000 $1,000.000 $560.000 $500.000 $85.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 6.000 $1,400.000 $1,200.000 $286.900 $300.000 $400.000 $1,000.000 $1,000.000 $1,000.000 $800.000 $85.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 268.000 $400.000 $220.000 $226.200 $170.000 $275.000 $150.000 $350.000 $373.000 $215.000 $85.000
RIPRAP (MOW STRIP)(4 IN)
CY 72.000 $770.000 $700.000 $995.300 $1,000.000 $800.000 $750.000 $550.000 $1,700.000 $750.000 $1,250.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 120.000 $400.000 $320.000 $341.500 $250.000 $250.000 $350.000 $185.000 $455.000 $335.000 $125.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 287.000 $300.000 $340.000 $340.100 $250.000 $275.000 $250.000 $200.000 $455.000 $255.000 $125.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 1,137.000 $75.000 $70.000 $50.800 $64.860 $65.000 $50.000 $80.000 $51.350 $62.000 $185.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 890.000 $85.000 $60.000 $47.400 $59.360 $65.000 $50.000 $80.000 $46.000 $65.000 $88.000
MULTI-LAYER POLYMER OVERLAY
SY 1,081.000 $60.000 $60.000 $76.900 $85.800 $65.000 $50.000 $85.000 $63.000 $44.000 $52.000
STR STEEL (SHEAR ANCHOR)
LB 243.000 $50.000 $100.000 $153.000 $125.000 $50.000 $75.000 $125.000 $175.000 $215.000 $250.000
CLEAN & PAINT EXIST STR (SYSTEM II)
LS 1.000 $60,000.000 $200,000.000 $363,034.100 $425,500.000 $400,000.000 $310,000.000 $375,000.000 $396,000.000 $424,350.000 $448,000.000
RETROFIT RAIL (TY T631)
LF 623.000 $135.000 $210.000 $102.400 $106.270 $200.000 $200.000 $120.000 $121.300 $110.000 $220.000
RETROFIT RAIL (TY T223)(MOD)
LF 707.000 $300.000 $240.000 $221.400 $250.000 $225.000 $300.000 $200.000 $215.000 $660.000 $220.000
PIPE (GALV) (4 IN X 6 IN)
LF 24.000 $200.000 $400.000 $367.900 $1,000.000 $300.000 $200.000 $100.000 $1,035.000 $300.000 $250.000
SHOT BLASTING
SY 698.000 $13.000 $12.000 $23.200 $11.500 $6.000 $10.000 $20.000 $8.200 $4.000 $35.000
RAISING EXIST STRUCT
LS 1.000 $65,000.000 $40,000.000 $51,872.500 $140,000.000 $182,000.000 $110,000.000 $165,000.000 $48,500.000 $25,000.000 $225,000.000
MOBILIZATION
LS 1.000 $280,000.000 $200,000.000 $277,494.000 $300,000.000 $300,000.000 $300,000.000 $330,000.000 $336,000.000 $280,000.000 $585,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $10,000.000 $6,000.000 $11,947.800 $24,634.650 $5,000.000 $10,000.000 $8,500.000 $11,000.000 $14,500.000 $45,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 4.000 $600.000 $2,000.000 $1,000.300 $300.000 $100.000 $15,000.000 $160.000 $300.000 $500.000 $1,000.000
TMA (STATIONARY)
DAY 50.000 $400.000 $2,000.000 $316.700 $400.000 $300.000 $500.000 $250.000 $400.000 $250.000 $325.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 660.000 $8.000 $5.000 $4.700 $5.000 $5.000 $5.000 $4.000 $7.000 $2.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 660.000 $3.000 $2.000 $3.100 $1.000 $2.000 $1.000 $2.000 $2.300 $2.000 $5.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 480.000 $90.000 $90.000 $104.500 $70.000 $100.000 $200.000 $100.000 $150.000 $75.000 $100.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 480.000 $35.000 $15.000 $21.000 $20.000 $35.000 $10.000 $20.000 $50.000 $26.000 $50.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 480.000 $45.000 $15.000 $42.200 $25.000 $35.000 $10.000 $20.000 $70.000 $49.000 $50.000
MTL W-BEAM GD FEN (STEEL POST)
LF 2,112.500 $45.000 $58.000 $33.200 $29.900 $32.000 $35.000 $35.000 $40.100 $45.000 $50.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $3,000.000 $3,400.000 $3,661.300 $2,185.000 $2,500.000 $2,400.000 $1,850.000 $3,777.000 $3,900.000 $3,850.000
REMOVE METAL BEAM GUARD FENCE
LF 2,675.500 $5.000 $12.000 $2.700 $2.480 $3.000 $4.000 $6.000 $4.000 $3.000 $5.000
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $4,000.000 $4,500.000 $3,300.600 $3,450.000 $3,600.000 $3,500.000 $3,250.000 $4,006.000 $4,425.000 $4,500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,500.000 $3,500.000 $2,587.600 $2,875.000 $3,200.000 $2,000.000 $6,500.000 $2,000.000 $3,150.000 $3,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $3,000.000 $3,500.000 $1,080.400 $1,150.000 $1,200.000 $1,000.000 $2,500.000 $1,000.000 $1,400.000 $2,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $12,000.000 $12,000.000 $11,987.400 $10,465.000 $11,000.000 $12,000.000 $21,000.000 $9,000.000 $9,000.000 $10,500.000
WIRE FENCE (WATER GAP)
LF 105.000 $60.000 $50.000 $66.700 $50.000 $35.000 $100.000 $10.000 $85.000 $115.000 $105.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 14.000 $40.000 $200.000 $45.800 $20.700 $25.000 $50.000 $10.000 $25.000 $27.000 $850.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 41.000 $40.000 $150.000 $33.800 $28.750 $35.000 $50.000 $10.000 $48.000 $33.000 $850.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 91.000 $1.000 $40.000 $5.000 $1.150 $3.000 $1.300 $5.000 $1.140 $1.000 $3.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 13,801.000 $1.000 $3.000 $0.900 $1.570 $2.000 $1.200 $5.000 $0.970 $1.200 $3.000
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 6.000 $250.000 $400.000 $460.200 $460.000 $130.000 $250.000 $250.000 $457.780 $530.000 $350.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 4.000 $250.000 $300.000 $540.200 $495.000 $200.000 $285.000 $250.000 $515.000 $670.000 $350.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 18,301.000 $1.000 $2.000 $0.900 $1.640 $2.000 $1.200 $2.000 $0.970 $1.200 $2.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 76.000 $2.000 $60.000 $7.300 $2.880 $2.500 $1.850 $3.000 $2.860 $7.000 $3.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 621.000 $2.000 $28.000 $2.100 $1.670 $1.600 $1.500 $3.000 $1.660 $5.000 $3.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 8.000 $300.000 $600.000 $445.100 $460.000 $200.000 $335.000 $250.000 $457.780 $280.000 $500.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 8.000 $300.000 $900.000 $284.100 $274.850 $250.000 $375.000 $250.000 $273.530 $390.000 $500.000
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 1,902.000 $1.000 $5.000 $1.200 $1.150 $1.700 $1.750 $3.000 $1.140 $2.500 $3.000
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 7,972.000 $1.000 $6.000 $0.900 $0.980 $1.700 $1.700 $3.000 $0.970 $2.500 $3.000
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 8,434.000 $1.000 $6.000 $0.900 $0.980 $1.700 $1.700 $3.000 $0.970 $2.500 $3.000
REFL PAV MRKR TY I-C
EA 138.000 $6.000 $30.000 $14.700 $13.800 $8.000 $7.000 $6.000 $13.730 $30.000 $9.000
REFL PAV MRKR TY II-A-A
EA 102.000 $6.500 $30.000 $15.600 $13.800 $8.000 $8.000 $6.000 $13.730 $20.000 $10.000
ELIM EXT PM & MRKS (4")
LF 18,418.000 $0.850 $2.000 $0.600 $0.580 $1.000 $0.900 $1.000 $0.570 $2.500 $2.000
ELIM EXT PM & MRKS (8")
LF 4,149.500 $2.000 $5.000 $1.100 $1.150 $1.250 $1.700 $6.000 $1.140 $3.000 $3.000
ELIM EXT PM & MRKS (ARROW)
EA 2.000 $200.000 $500.000 $70.000 $80.500 $200.000 $125.000 $250.000 $80.110 $170.000 $155.000
ELIM EXT PM & MRKS (WORD)
EA 3.000 $200.000 $500.000 $80.000 $92.000 $200.000 $135.000 $250.000 $91.560 $170.000 $165.000
DRIFTWOOD REMOVAL
CY 10.000 $900.000 $800.000 $814.400 $100.000 $150.000 $250.000 $500.000 $667.000 $550.000 $450.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 12.500 $200.000 $200.000 $207.300 $630.200 $125.000 $200.000 $1,000.000 $169.000 $250.000 $285.000
REP STL BRIDGE MEMBER (BEAM)
EA 1.000 $40,000.000 $14,000.000 $49,387.200 $75,000.000 $20,000.000 $225,000.000 $175,000.000 $118,000.000 $155,000.000 $425,000.000
REP STL BRIDGE MEMBER (BEARINGS)
EA 5.000 $10,000.000 $6,000.000 $273.500 $5,000.000 $5,500.000 $2,500.000 $7,500.000 $2,175.000 $8,800.000 $6,500.000
REPLACING ELASTOMERIC BEARING PADS
EA 8.000 $12,000.000 $10,000.000 $23,028.700 $1,000.000 $1,500.000 $7,500.000 $13,500.000 $15,200.000 $10,000.000 $6,500.000
STEEL BRIDGE ZONE PAINTING REF STR #1
EA 1.000 $70,000.000 $38,000.000 $58,606.900 $63,250.000 $75,000.000 $60,000.000 $65,000.000 $69,520.000 $70,000.000 $188,000.000
STEEL BRIDGE ZONE PAINTING REF STR #2
EA 1.000 $50,000.000 $38,000.000 $38,606.900 $40,250.000 $50,000.000 $40,000.000 $45,000.000 $46,630.000 $49,000.000 $125,000.000
STEEL BRIDGE ZONE PAINTING REF STR #3
EA 1.000 $70,000.000 $38,000.000 $58,606.900 $63,250.000 $75,000.000 $60,000.000 $65,000.000 $69,520.000 $69,400.000 $188,000.000
STEEL BRIDGE ZONE PAINTING REF STR #4
EA 1.000 $70,000.000 $38,000.000 $58,606.900 $63,250.000 $75,000.000 $60,000.000 $65,000.000 $69,520.000 $71,500.000 $188,000.000
STEEL BRIDGE ZONE PAINTING REF STR #5
EA 1.000 $50,000.000 $38,000.000 $38,606.900 $40,250.000 $50,000.000 $40,000.000 $45,000.000 $46,630.000 $51,200.000 $125,000.000
STEEL BRIDGE ZONE PAINTING REF STR #6
EA 1.000 $70,000.000 $38,000.000 $58,606.900 $63,250.000 $75,000.000 $60,000.000 $65,000.000 $69,520.000 $71,200.000 $188,000.000
STEEL BRIDGE ZONE PAINTING REF STR #7
EA 1.000 $50,000.000 $38,000.000 $38,606.900 $40,250.000 $50,000.000 $40,000.000 $45,000.000 $46,630.000 $51,725.000 $125,000.000
Totals: $2,804,984.300 $2,768,114.500 $2,775,083.850 $2,987,736.810 $3,075,365.075 $3,093,480.850 $3,347,383.000 $3,361,973.200 $3,426,999.400 $5,181,797.000