CLAY US 287 (0224-01-062)
Items: 44
County: CLAY
Length: N/A
Highway: US 287
District: WICHITA FALLS
Control Number: 0224-01-062
DBE Goal: N/A
Project: F 2023(805)
Guaranty: N/A
Time: 51 WORKING DAYS
Engineer's Estimate: $1,980,125.33
Date: 05/04/2023 (3 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
CALLAN COLTHARP
CODY BATES
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,980,125.33 | |||
| $2,393,785.60 |
20.89%
$413,660.27
|
|||
| $2,408,894.82 |
21.65%
$428,769.49
|
0.63%
$15,109.22
|
||
| $2,768,658.83 |
39.82%
$788,533.50
|
15.66%
$374,873.23
|
-14.93%
-$359,764.01
|
E
Engineer's Estimate
$1,980,125.33
1
Awarded
$2,393,785.60
Over/Under Est:
20.89%
$413,660.27
$2,408,894.82
Over/Under Est:
21.65%
$428,769.49
Amt Left:
0.63%
$15,109.22
$2,768,658.83
Over/Under Est:
39.82%
$788,533.50
Amt Left:
15.66%
$374,873.23
Delta:
-14.93%
-$359,764.01
| Subcontractor | Percentage | Amount |
|---|---|---|
| HJC FARMS, INC. | 4.69% | $112,268.54 |
| TRP CONSTRUCTION GROUP, LLC | 1.45% | $34,709.89 |
| WOLFE CONSTRUCTION GROUP, INCORPORATED | 0.66% | $15,798.98 |
| KING GEORGE TRAFFIC SOLUTIONS LLC | 0.37% | $8,857.01 |
| Total: | 7.17% | $171,634.42 |
Bid Items & Bid Tabulations
44
Total
0 of 44