CHEROKEE US0084 (6346-94-001)

Items: 20

County: CHEROKEE
Length: N/A
Highway: US0084
District: TYLER
Control Number: 6346-94-001
DBE Goal: N/A
Project: BPM - 634694001
Guaranty: N/A
Time: 100 W
Engineer's Estimate: $297,282.50
Date: 12/10/2019 (6 years ago)
Contract Number: N/A
Type: BPM
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$297,282.50
Over/Under Est: -8.18% -$24,329.50
Over/Under Est: -1.15% -$3,417.50
Amt Left: 7.66% $20,912.00
Over/Under Est: -0.36% -$1,074.50
Amt Left: 8.52% $23,255.00
Delta: -0.80% -$2,343.00
Over/Under Est: 5.95% $17,676.50
Amt Left: 15.39% $42,006.00
Delta: -6.33% -$18,751.00
Over/Under Est: 16.74% $49,771.00
Amt Left: 27.15% $74,100.50
Delta: -10.19% -$32,094.50
Over/Under Est: 89.53% $266,168.50
Amt Left: 106.43% $290,498.00
Delta: -62.35% -$216,397.50

Bid Items & Bid Tabulations

20 Total 0 of 20
CHEROKEE  |  US0084  |  TYLER  |  6346-94-001  |  12/10/2019  |  $297,282.50  |  BPM - 634694001  |  BPM  |  100 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
RED BARON BUILDING COMPANY, L.L.C.
BLACKSTONE CONCRETE VENTURES, LLC
L & M MOWING CONTRACTORS, LLC
LELAND & BRADLEE CONSTRUCTION, INC.
BAKER & COMPANY CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
EXCAVATION (CHANNEL)
CY 118.000 $35.000 $30.000 $50.000 $36.360 $20.000 $90.000 $100.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 330.000 $33.000 $28.000 $20.000 $35.000 $20.000 $50.000 $80.000
STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY)
SY 433.000 $0.500 $1.000 $5.000 $1.500 $3.000 $3.000 $2.000
VEGETATIVE WATERING
MG 4.700 $40.000 $50.000 $100.000 $58.720 $10.000 $125.000 $500.000
FLOWABLE BACKFILL
CY 32.000 $250.000 $230.000 $400.000 $243.790 $220.000 $330.000 $350.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 416.000 $145.000 $125.000 $50.000 $141.950 $175.000 $175.000 $350.000
RIPRAP (CONC)(4 IN)
CY 37.000 $500.000 $500.000 $850.000 $559.880 $350.000 $500.000 $550.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 427.000 $230.000 $145.000 $300.000 $149.480 $125.000 $110.000 $185.000
MOBILIZATION
LS 1.000 $27,000.000 $47,000.000 $15,000.000 $14,876.360 $20,000.000 $43,600.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $1,750.000 $1,500.000 $1,000.000 $4,140.300 $8,000.000 $4,275.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 90.000 $35.000 $30.000 $200.000 $52.510 $50.000 $69.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 90.000 $20.000 $15.000 $20.000 $13.070 $20.000 $19.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,600.000 $3.000 $2.000 $2.500 $2.960 $4.500 $4.400 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,600.000 $2.000 $1.000 $1.000 $1.170 $1.500 $1.250 $2.000
JT SEALING AND CLEANING(EXPANSION JTS)
LF 704.000 $20.000 $30.000 $10.000 $35.230 $7.000 $55.000 $85.000
TREE AND BRUSH REMOVAL
AC 0.600 $2,300.000 $500.000 $5,000.000 $12,200.000 $7,000.000 $16,000.000 $6,500.000
STORM SEWER CLEAN (BOX CULV)(ALL SIZES)
LF 424.000 $32.000 $50.000 $50.000 $61.450 $100.000 $23.000 $100.000
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 94.000 $50.000 $40.000 $50.000 $39.330 $10.000 $50.000 $300.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 56.000 $50.000 $75.000 $55.000 $67.360 $20.000 $70.000 $300.000
TMA (STATIONARY)
DAY 58.000 $200.000 $100.000 $20.000 $246.760 $500.000 $355.000 $450.000
Totals: $297,282.500 $272,953.000 $293,865.000 $296,208.004 $314,959.000 $347,053.500 $563,451.000