CHEROKEE FM 22 (0634-01-014)

Items: 106

County: CHEROKEE
Length: N/A
Highway: FM 22
District: TYLER
Control Number: 0634-01-014
DBE Goal: N/A
Project: STP 2021(318)HES
Guaranty: N/A
Time: 249 WORKING DAYS
Engineer's Estimate: $5,329,289.88
Date: 02/05/2021 (5 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (8)
E
Engineer's Estimate
$5,329,289.88
$5,533,705.84
Over/Under Est: 3.84% $204,415.96
Over/Under Est: 10.91% $581,497.76
Amt Left: 6.81% $377,081.80
Over/Under Est: 11.04% $588,226.30
Amt Left: 6.94% $383,810.34
Delta: -0.11% -$6,728.54
Over/Under Est: 13.18% $702,327.17
Amt Left: 9% $497,911.21
Delta: -1.93% -$114,100.87
Over/Under Est: 14.46% $770,447.04
Amt Left: 10.23% $566,031.08
Delta: -1.13% -$68,119.87
$6,140,788.64
Over/Under Est: 15.23% $811,498.76
Amt Left: 10.97% $607,082.80
Delta: -0.67% -$41,051.72
$6,298,830.20
Over/Under Est: 18.19% $969,540.32
Amt Left: 13.83% $765,124.36
Delta: -2.57% -$158,041.56
Over/Under Est: 29.45% $1,569,524.26
Amt Left: 24.67% $1,365,108.30
Delta: -9.53% -$599,983.94
Subcontractor Percentage Amount
FOUTSCO PAVING COMPANY, LLC 13.31% $736,536.25
MADDEN CONTRACTING COMPANY, LLC. 12.96% $717,168.28
R & G CONSTRUCTION, LLC 8.78% $485,859.37
HODGES AND SON CONSTRUCTION COMPANY, INC. 4.14% $229,095.42
ISAACS CONSTRUCTION SERVICES LLC 1.51% $83,558.96
STRIPING TECHNOLOGY, L.P. 1.22% $67,511.21
MORRIS COUNTY CONTRACTORS, L.L.C. 1.07% $59,210.65
TORO BRAVO CONSTRUCTION, LLC 0.92% $50,910.09
PANOLA SIGN & BARRICADE, INC. 0.49% $27,115.16
WEST TEXAS ROCK RESOURCES, LLC 0.15% $8,300.56
Total: 44.55% $2,465,265.95

Bid Items & Bid Tabulations

106 Total 0 of 106
CHEROKEE  |  FM 22  |  TYLER  |  0634-01-014  |  02/05/2021  |  $5,329,289.88  |  STP 2021(318)HES  |  HAZARD ELIM & SAFETY  |  249 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STATELINE CONSTRUCTION, LLC
MADDEN CONTRACTING COMPANY, LLC.
LONGVIEW BRIDGE AND ROAD, LTD.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
EAST TEXAS BRIDGE, INC.
A. L. HELMCAMP, INC.
PIERCE R & B LLC
HIGHWAY 19 CONSTRUCTION LLC
PREPARING ROW
STA 36.000 $1,500.000 $800.000 $1,200.000 $1,500.000 $1,700.000 $2,600.000 $3,200.000 $1,400.000 $1,000.000
REMOVING CONC (DRIVEWAYS)
SY 57.000 $15.000 $12.000 $20.000 $10.000 $21.000 $15.000 $45.000 $21.000 $25.000
REMOVING STAB BASE & ASPH PAV (9")
SY 3,857.000 $3.250 $2.970 $3.000 $3.750 $22.000 $9.000 $10.000 $3.190 $15.000
EXCAVATION (ROADWAY)
CY 9,668.000 $7.000 $7.500 $7.500 $8.000 $8.750 $7.000 $15.000 $9.500 $10.000
EXCAVATION (CHANNEL)
CY 2,113.000 $10.000 $9.000 $9.000 $11.000 $12.000 $8.000 $19.000 $26.000 $10.000
SUBGRADE WIDENING (ORD COMP)
STA 234.000 $300.000 $186.000 $400.000 $215.000 $399.000 $350.000 $250.000 $359.000 $500.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 4,887.000 $18.000 $7.770 $8.000 $11.000 $29.500 $12.000 $9.000 $8.450 $17.000
BACKFILL (TY A)
STA 234.000 $170.000 $200.000 $200.000 $300.000 $139.000 $340.000 $150.000 $216.000 $250.000
BLADING
STA 255.000 $200.000 $125.000 $125.000 $125.000 $138.000 $150.000 $110.000 $137.000 $150.000
FURNISHING AND PLACING TOPSOIL (4")
SY 13,126.000 $3.320 $2.430 $2.500 $1.400 $2.450 $1.000 $2.000 $2.600 $3.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 32,949.000 $0.150 $0.110 $0.100 $0.170 $0.100 $0.110 $0.120 $0.150 $0.770
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 65,897.000 $0.650 $0.630 $0.610 $0.750 $0.630 $0.670 $0.680 $0.680 $0.770
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 32,949.000 $0.550 $0.580 $0.570 $0.650 $0.580 $0.620 $0.620 $0.660 $0.250
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 32,949.000 $0.500 $0.560 $0.550 $0.650 $0.560 $0.600 $0.620 $0.660 $0.250
VEGETATIVE WATERING
MG 725.000 $10.000 $5.000 $6.000 $1.000 $29.000 $5.000 $22.000 $25.000 $100.000
CEMENT
TON 224.000 $150.000 $161.000 $165.000 $170.000 $163.000 $165.000 $170.000 $187.000 $180.000
CEMENT TREAT (EXIST MATL)(DC)(8")
SY 12,466.000 $2.170 $4.390 $4.500 $2.500 $4.200 $3.000 $3.200 $4.680 $7.000
EMULS ASPH (EROSN CONT)(CSS-1)
GAL 3,349.000 $3.690 $4.250 $4.250 $3.500 $4.000 $5.000 $3.000 $4.480 $5.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 31,362.000 $3.050 $2.750 $3.000 $3.750 $2.750 $3.250 $3.400 $3.150 $4.500
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 747.000 $106.000 $144.000 $130.000 $140.000 $136.000 $140.000 $140.000 $136.600 $150.000
D-GR HMA(SQ) TY-D PG64-22
TON 351.000 $130.000 $130.000 $130.000 $140.000 $175.000 $160.000 $165.000 $136.710 $180.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 1,000.000 $50.000 $69.000 $71.500 $60.000 $67.000 $65.000 $80.000 $75.670 $35.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 1,883.000 $3.000 $9.000 $10.000 $3.600 $6.000 $6.000 $7.000 $13.160 $7.000
CEM STABIL BKFL
CY 356.000 $100.000 $210.000 $210.000 $175.000 $165.000 $175.000 $160.000 $225.000 $180.000
DRILL SHAFT (18 IN)
LF 420.000 $85.000 $85.000 $85.000 $100.000 $68.000 $65.000 $105.000 $86.000 $180.000
DRILL SHAFT (36 IN)
LF 1,164.000 $175.000 $196.000 $196.000 $220.000 $202.000 $208.000 $135.000 $222.000 $220.000
CL C CONC (ABUT)(HPC)
CY 146.200 $845.000 $875.000 $875.000 $850.000 $850.000 $900.000 $1,000.000 $950.000 $1,000.000
CL C CONC (CAP)(HPC)
CY 60.000 $900.000 $990.000 $990.000 $950.000 $875.000 $950.000 $1,200.000 $1,150.000 $1,500.000
CL C CONC (COLUMN)(HPC)
CY 27.200 $880.000 $990.000 $990.000 $950.000 $925.000 $1,000.000 $1,500.000 $1,400.000 $800.000
REINF CONC SLAB
SF 11,050.000 $14.500 $18.850 $18.850 $17.000 $19.600 $23.000 $22.000 $18.000 $21.000
APPROACH SLAB
CY 154.200 $350.000 $605.000 $605.000 $500.000 $490.000 $530.000 $750.000 $525.000 $500.000
PRESTR CONC GIRDER (TX28)
LF 830.000 $135.000 $182.000 $182.000 $140.000 $157.000 $154.000 $155.000 $164.000 $178.000
PRESTR CONC GIRDER (TX34)
LF 456.000 $140.000 $184.000 $184.000 $140.000 $162.000 $154.000 $155.000 $160.000 $174.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 2,044.000 $120.000 $107.000 $107.000 $150.000 $144.000 $160.000 $80.000 $120.000 $100.000
RIPRAP (MOW STRIP)(4 IN)
CY 104.000 $430.000 $405.000 $405.000 $500.000 $397.000 $500.000 $510.000 $500.000 $450.000
RAIL (TY T223)
LF 838.000 $90.000 $105.000 $105.000 $80.000 $88.000 $90.000 $120.000 $115.000 $110.000
ARMOR JOINT (SEALED)
LF 180.000 $140.000 $78.000 $78.000 $60.000 $91.000 $60.000 $65.000 $70.000 $150.000
RC PIPE (CL III)(18 IN)
LF 342.000 $40.000 $45.000 $40.000 $50.000 $43.000 $40.000 $60.000 $85.000 $45.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 18.000 $600.000 $695.000 $650.000 $640.000 $612.000 $575.000 $650.000 $700.000 $750.000
REMOV STR (PIPE)
LF 100.000 $15.000 $5.000 $4.000 $10.000 $12.500 $15.000 $45.000 $10.000 $50.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $18,000.000 $13,275.000 $13,275.000 $10,000.000 $15,500.000 $30,000.000 $21,000.000 $20,000.000 $30,000.000
MOBILIZATION
LS 1.000 $506,000.000 $285,000.000 $452,500.000 $500,000.000 $300,000.000 $330,000.000 $480,000.000 $495,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $5,000.000 $1,700.000 $2,000.000 $2,500.000 $4,100.000 $4,000.000 $8,100.000 $3,500.000 $3,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,940.000 $31.000 $27.000 $31.000 $35.000 $32.000 $33.000 $29.000 $27.350 $40.000
ROCK FILTER DAMS (REMOVE)
LF 1,940.000 $9.500 $9.750 $9.000 $8.000 $9.300 $3.000 $3.000 $8.960 $10.000
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 1,000.000 $18.000 $7.000 $20.000 $15.000 $22.000 $20.000 $20.000 $20.000 $10.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 120.000 $68.000 $40.000 $75.000 $100.000 $148.000 $75.000 $75.000 $75.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 20,441.000 $2.500 $2.400 $2.350 $2.900 $2.400 $2.850 $2.000 $2.470 $2.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 20,441.000 $0.750 $0.850 $0.600 $0.650 $0.650 $0.500 $0.500 $0.800 $0.500
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 120.000 $95.000 $45.000 $110.000 $135.000 $175.000 $125.000 $90.000 $100.000 $20.000
DRIVEWAYS (ACP)
SY 1,277.000 $35.000 $24.000 $25.000 $35.000 $30.000 $24.000 $35.000 $25.260 $55.000
TURNOUTS (ACP)
SY 514.000 $43.750 $32.000 $35.000 $50.000 $40.000 $24.000 $40.000 $33.740 $55.000
DRIVEWAYS (CONC) (HES)
SY 68.000 $90.000 $57.000 $110.000 $125.000 $93.000 $125.000 $165.000 $150.000 $150.000
RUMBLE STRIPS (SHOULDER)
LF 46,446.000 $0.160 $0.130 $0.260 $0.160 $0.200 $0.200 $0.150 $0.130 $0.120
RUMBLE STRIPS (CENTERLINE)
LF 23,223.000 $0.160 $0.130 $0.260 $0.160 $0.200 $0.200 $0.150 $0.130 $0.120
MTL W-BEAM GD FEN (STEEL POST)
LF 575.000 $26.500 $23.500 $21.000 $24.750 $23.000 $24.000 $22.000 $23.750 $21.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 11.000 $1,820.000 $1,600.000 $1,500.000 $1,850.000 $3,500.000 $1,800.000 $1,800.000 $1,581.560 $1,565.000
REMOVE METAL BEAM GUARD FENCE
LF 150.000 $2.500 $2.000 $1.000 $4.400 $3.000 $3.000 $2.500 $2.580 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $200.000 $200.000 $100.000 $250.000 $100.000 $250.000 $200.000 $228.030 $200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 11.000 $2,650.000 $2,600.000 $2,100.000 $2,585.000 $2,420.000 $2,600.000 $2,500.000 $2,579.060 $2,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $245.000 $150.000 $100.000 $250.000 $100.000 $200.000 $250.000 $175.530 $200.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $23,000.000 $27,500.000 $25,000.000 $28,000.000 $29,000.000 $28,000.000 $26,000.000 $27,372.110 $25,250.000
WIRE FENCE (TY A)
LF 614.000 $15.000 $12.000 $18.000 $12.000 $17.500 $15.000 $10.000 $13.780 $15.000
GATE (TY 1)
EA 3.000 $1,213.640 $2,200.000 $2,000.000 $850.000 $2,100.000 $2,000.000 $550.000 $864.040 $1,500.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 34.000 $250.000 $200.000 $125.000 $260.000 $242.000 $270.000 $240.000 $205.930 $250.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 3.000 $275.000 $220.000 $140.000 $260.000 $242.000 $325.000 $250.000 $249.470 $280.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 3.000 $450.000 $405.000 $325.000 $435.000 $406.000 $470.000 $410.000 $437.000 $400.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 17.000 $590.000 $550.000 $500.000 $565.000 $530.000 $650.000 $540.000 $567.670 $530.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 3.000 $725.000 $645.000 $600.000 $710.000 $663.000 $770.000 $670.000 $683.440 $690.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $750.000 $690.000 $725.000 $825.000 $773.000 $930.000 $800.000 $746.800 $800.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 2.000 $750.000 $775.000 $1,000.000 $1,000.000 $937.000 $1,150.000 $950.000 $823.870 $900.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 38.000 $375.000 $250.000 $330.000 $325.000 $304.000 $415.000 $310.000 $254.530 $450.000
REMOVE SM RD SN SUP&AM
EA 62.000 $90.000 $85.000 $35.000 $95.000 $88.000 $50.000 $90.000 $92.300 $90.000
RELOCATE SM RD SN SUP & AM TY TEMP
EA 2.000 $225.000 $400.000 $325.000 $94.000 $88.000 $590.000 $90.000 $420.250 $500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 26.000 $22.000 $20.000 $15.000 $19.000 $18.000 $25.000 $20.000 $20.100 $22.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 36.000 $31.000 $20.000 $20.000 $30.000 $28.000 $35.000 $30.000 $21.640 $75.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 51,422.000 $0.230 $0.130 $0.150 $0.130 $0.120 $0.130 $0.120 $0.130 $0.120
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 166.000 $0.750 $0.550 $0.500 $0.550 $0.550 $0.550 $0.500 $0.960 $0.500
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 294.000 $3.000 $2.600 $2.500 $2.750 $2.600 $3.000 $2.500 $2.870 $2.500
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 3,170.000 $0.300 $0.130 $0.150 $0.130 $0.120 $0.130 $0.120 $0.150 $0.120
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 37,045.000 $0.240 $0.130 $0.150 $0.130 $0.120 $0.130 $0.120 $0.130 $0.120
WK ZN PAV MRK REMOV (Y)4"(BRK)
LF 1,362.000 $0.900 $1.000 $1.500 $1.400 $0.750 $1.000 $0.650 $1.100 $1.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 8,458.000 $0.700 $1.000 $1.500 $1.300 $0.750 $1.000 $0.650 $1.060 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,787.000 $0.750 $1.000 $1.000 $1.200 $1.900 $1.500 $0.650 $1.080 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 166.000 $0.810 $1.000 $1.000 $1.100 $1.050 $1.100 $1.100 $1.480 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 294.000 $5.500 $5.750 $5.500 $6.050 $5.650 $6.000 $5.800 $6.020 $6.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 50,172.000 $0.300 $0.480 $0.500 $0.500 $0.500 $0.500 $0.500 $0.480 $0.460
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 3,040.000 $0.300 $0.660 $0.600 $0.660 $0.650 $0.660 $0.650 $0.650 $0.600
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 37,553.000 $0.300 $0.480 $0.500 $0.500 $0.500 $0.500 $0.500 $0.480 $0.460
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 1,250.000 $0.500 $3.100 $3.000 $3.300 $3.000 $3.300 $3.200 $3.210 $3.000
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 150.000 $0.550 $3.100 $3.000 $3.300 $3.000 $3.300 $3.200 $3.630 $3.000
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 625.000 $0.550 $3.100 $3.000 $3.300 $3.000 $3.300 $3.200 $3.270 $3.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 10.000 $31.000 $110.000 $100.000 $110.000 $105.000 $110.000 $105.000 $112.210 $100.000
REFL PAV MRKR TY I-A
EA 66.000 $3.200 $5.500 $5.000 $5.500 $5.150 $5.500 $5.500 $6.340 $5.000
REFL PAV MRKR TY I-C
EA 55.000 $3.300 $5.500 $5.000 $5.500 $5.150 $5.500 $5.500 $6.560 $5.000
REFL PAV MRKR TY II-A-A
EA 622.000 $3.100 $3.600 $3.500 $3.850 $3.600 $4.000 $3.700 $3.790 $3.500
SP MIXES SP-B PG64-22
TON 17,451.000 $81.000 $95.700 $100.000 $97.000 $98.000 $100.000 $98.000 $105.000 $120.000
SP MIXES SP-D SAC-A PG70-22
TON 6,160.000 $88.000 $108.000 $110.000 $105.000 $109.000 $110.000 $105.000 $116.000 $110.000
TACK COAT
GAL 7,467.000 $2.000 $3.000 $1.000 $3.000 $2.800 $3.000 $3.000 $1.060 $8.000
FLOATING TURBIDITY BARRIER(FUR & INST)
LF 200.000 $35.000 $45.000 $47.000 $42.000 $48.000 $55.000 $40.000 $42.360 $50.000
FLOATING TURBIDITY BARRIER (REMOVE)
LF 200.000 $9.000 $10.000 $15.000 $12.000 $15.000 $20.000 $20.000 $12.960 $10.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 56.000 $125.000 $75.000 $90.000 $100.000 $185.000 $150.000 $200.000 $125.000 $100.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $5,500.000 $13,000.000 $18,500.000 $8,000.000 $7,400.000 $12,000.000 $12,000.000 $8,500.000 $10,000.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 174.000 $3.500 $13.000 $12.500 $13.750 $13.000 $13.000 $13.000 $13.540 $12.000
TMA (STATIONARY)
DAY 235.000 $160.000 $75.000 $150.000 $125.000 $180.000 $200.000 $200.000 $135.000 $200.000
TMA (MOBILE OPERATION)
DAY 14.000 $90.000 $125.000 $1.000 $300.000 $0.010 $200.000 $300.000 $150.000 $500.000
Totals: $5,329,289.880 $5,533,705.840 $5,910,787.640 $5,917,516.180 $6,031,617.050 $6,099,736.920 $6,140,788.640 $6,298,830.200 $6,898,814.140