Show Job Controls
Bid Cobra

CHEROKEE US 69 (0199-01-084)

Items: 36

County: CHEROKEE
Length: N/A
Highway: US 69
District: TYLER
Control Number: 0199-01-084
DBE Goal: N/A
Project: NH 1902(286)
Guaranty: N/A
Time: 231 WORKING DAYS
Engineer's Estimate: $598,150.24
Date: 08/06/2019 (6 years ago)
Contract Number: N/A
Type: SIDEWALKS, DRIVEWAYS, DRNG, STRS, PV MK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$598,150.24
$502,100.00
Over/Under Est: -16.06% -$96,050.24
Over/Under Est: -13.98% -$83,631.34
Amt Left: 2.47% $12,418.90
Over/Under Est: -8.34% -$49,875.24
Amt Left: 9.2% $46,175.00
Delta: -6.56% -$33,756.10
Over/Under Est: 1.66% $9,926.76
Amt Left: 21.11% $105,977.00
Delta: -10.91% -$59,802.00
Over/Under Est: 16.92% $101,226.76
Amt Left: 39.29% $197,277.00
Delta: -15.01% -$91,300.00
Over/Under Est: 24.6% $147,132.76
Amt Left: 48.43% $243,183.00
Delta: -6.56% -$45,906.00

Bid Items & Bid Tabulations

36 Total 0 of 36
CHEROKEE  |  US 69  |  TYLER  |  0199-01-084  |  08/06/2019  |  $598,150.24  |  NH 1902(286)  |  SIDEWALKS, DRIVEWAYS, DRNG, STRS, PV...  |  231 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY 19 CONSTRUCTION LLC
REYNOLDS & KAY, LTD.
L. S. EQUIPMENT CO., INC.
J.R. POPE COMPANY, INC.
EAST TEXAS BRIDGE, INC.
FNH CONSTRUCTION, LLC
REMOVING CONC (DRIVEWAYS)
SY 1,742.000 $22.000 $20.000 $31.000 $5.000 $20.000 $18.000 $30.000
REMOVING CONC (CURB OR CURB & GUTTER)
LF 735.000 $9.890 $10.000 $22.000 $5.000 $15.000 $13.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 10.000 $14.570 $100.000 $100.000 $25.000 $200.000 $50.000 $35.000
COMPOST MANUF TOPSOIL (4")
SY 121.000 $9.330 $10.000 $9.300 $8.500 $10.000 $25.000 $10.000
BLOCK SODDING
SY 121.000 $7.000 $10.000 $10.800 $3.000 $10.000 $10.000 $10.000
D-GR HMA(SQ) TY-D PG64-22
TON 5.000 $153.180 $500.000 $300.000 $250.000 $400.000 $700.000 $1,000.000
RETAINING WALL (CAST - IN - PLACE)
SF 400.000 $90.000 $50.000 $57.000 $85.000 $60.000 $90.000 $150.000
RIPRAP (CONC)(4 IN)
CY 32.300 $800.000 $500.000 $600.000 $600.000 $500.000 $650.000 $500.000
RAIL (HANDRAIL)(TY A)
LF 36.000 $155.360 $110.000 $120.000 $160.000 $150.000 $300.000 $300.000
RAIL (HANDRAIL)(TY E)
LF 30.000 $125.000 $150.000 $230.000 $160.000 $200.000 $300.000 $210.000
INLET (COMP) (TY SIDEWALK BRIDGE)
EA 1.000 $5,557.140 $5,000.000 $9,400.000 $10,000.000 $4,500.000 $14,000.000 $12,500.000
MOBILIZATION
LS 1.000 $39,562.000 $60,000.000 $51,000.000 $52,500.000 $60,000.000 $65,000.000 $70,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $5,000.000 $5,000.000 $2,300.000 $1,500.000 $3,000.000 $10,000.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 505.000 $2.700 $1.000 $3.300 $3.500 $3.000 $4.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 505.000 $0.940 $1.000 $1.400 $1.000 $1.500 $1.000 $2.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 104.000 $6.650 $1.000 $7.000 $8.000 $10.000 $15.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 104.000 $1.130 $1.000 $3.500 $5.000 $5.000 $3.000 $9.000
CONC CURB (TY II)
LF 182.000 $37.000 $35.000 $41.000 $30.000 $15.000 $25.000 $35.000
CONC CURB & GUTTER (TY II)
LF 671.000 $45.000 $35.000 $35.000 $35.000 $35.000 $40.000 $35.000
DRIVEWAYS (CONC)
SY 1,742.000 $95.000 $85.000 $88.000 $100.000 $108.000 $100.000 $100.000
CONC SIDEWALKS (4")
SY 1,011.000 $90.000 $65.000 $61.000 $100.000 $94.500 $80.000 $80.000
CURB RAMPS (TY 1)
EA 7.000 $4,500.000 $1,500.000 $1,900.000 $2,000.000 $2,000.000 $3,800.000 $2,500.000
CURB RAMPS (TY 2)
EA 2.000 $5,000.000 $1,800.000 $2,100.000 $5,000.000 $2,500.000 $4,000.000 $2,500.000
CURB RAMPS (TY 5)
EA 1.000 $5,000.000 $2,500.000 $2,400.000 $5,000.000 $3,000.000 $8,000.000 $2,500.000
CONC SIDEWALKS (SPECIAL) (TYPE B)
SY 16.000 $175.000 $300.000 $86.000 $150.000 $150.000 $150.000 $100.000
GROUND BOX TY D (162922)W/APRON
EA 2.000 $1,339.180 $1,000.000 $820.000 $700.000 $500.000 $1,000.000 $1,000.000
REMOVE GROUND BOX
EA 2.000 $260.240 $300.000 $470.000 $185.000 $100.000 $300.000 $250.000
IN SM RD SN SUP&AM TYTWT(1)UA(P)
EA 7.000 $415.780 $500.000 $700.000 $650.000 $400.000 $700.000 $650.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 1.000 $450.000 $500.000 $560.000 $500.000 $150.000 $600.000 $450.000
REMOVE SM RD SN SUP&AM
EA 6.000 $117.500 $300.000 $280.000 $500.000 $100.000 $100.000 $250.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 622.000 $2.830 $4.000 $4.700 $5.000 $5.000 $5.000 $20.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 124.000 $6.550 $7.000 $8.200 $8.000 $8.000 $8.000 $20.000
ELIM EXT PAV MRK & MRKS (12")
LF 238.000 $1.510 $3.000 $3.500 $4.000 $4.000 $4.000 $10.000
ELIM EXT PAV MRK & MRKS (24")
LF 163.000 $5.000 $4.000 $4.700 $5.000 $5.000 $5.000 $10.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $11,000.000 $5,000.000 $3,500.000 $16,800.000 $12,000.000 $12,000.000 $16,500.000
TMA (STATIONARY)
EA 1.000 $10,000.000 $10,000.000 $12,000.000 $4,500.000 $40,000.000 $30,000.000 $40,000.000
Totals: $598,150.240 $502,100.000 $514,518.900 $548,275.000 $608,077.000 $699,377.000 $745,283.000