Show Job Controls
Bid Cobra

CHAMBERS IH0010 (6472-92-001)

Items: 68

County: CHAMBERS
Length: 0.0100 MILES
Highway: IH0010
District: BEAUMONT
Control Number: 6472-92-001
DBE Goal: N/A
Project: RMC - A00212082
Guaranty: $7,000.00
Time: 365 CALENDAR DAYS
Engineer's Estimate: $368,260.00
Date: 02/18/2025 (1 year ago)
Contract Number: 2252004
Type: METAL BEAM GUARD FENCE REPAIR
Project ID: A00212082
Project Description: METAL BEAM GUARD FENCE REPAIR
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
8350 EASTEX FREEWAY, BEAUMONT, TX 77708
ROBERTO M RODRIGUEZ
DANIEL DUKE THOMPSON
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$368,260.00
$258,947.00
Over/Under Est: -29.68% -$109,313.00
Over/Under Est: -26.65% -$98,127.00
Amt Left: 4.32% $11,186.00
$311,609.00
Over/Under Est: -15.38% -$56,651.00
Amt Left: 20.34% $52,662.00
Delta: -15.35% -$41,476.00
Over/Under Est: -11.03% -$40,610.00
Amt Left: 26.53% $68,703.00
Delta: -5.15% -$16,041.00
Over/Under Est: 31.83% $117,211.00
Amt Left: 87.48% $226,524.00
Delta: -48.17% -$157,821.00
Over/Under Est: 156.32% $575,668.80
Amt Left: 264.53% $684,981.80
Delta: -94.44% -$458,457.80

Bid Items & Bid Tabulations

68 Total 0 of 68
CHAMBERS  |  IH0010  |  BEAUMONT  |  6472-92-001  |  02/18/2025  |  $368,260.00  |  RMC - A00212082  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HAZMAT INTERNATIONAL, INC.
BK FIELD OPERATIONS LLC
RHINO EQUITY, LLC
ROY JORGENSEN ASSOCIATES, INC.
ROSS SA ENTERPRISE LLC
ELITE KINGS CONSTRUCTION, LLC
REMOV CONC (RIPRAP)
SY 15.000 $75.000 $5.000 $1.000 $75.000 $200.000 $30.000 $64.000
CONC STR REPAIR (STANDARD)
SF 100.000 $20.000 $20.000 $10.000 $20.000 $125.000 $50.000 $199.200
RIPRAP (MOW STRIP)(4 IN)
CY 30.000 $700.000 $300.000 $400.000 $200.000 $600.000 $400.000 $680.000
RAIL (TY T402)(HPC)
LF 150.000 $160.000 $25.000 $40.000 $60.000 $100.000 $50.000 $199.200
MOBILIZATION (CALLOUT)
EA 15.000 $100.000 $50.000 $1.000 $1.000 $150.000 $50.000 $1,200.000
MOBILIZATION (EMERGENCY)
EA 5.000 $1,000.000 $500.000 $1.000 $1,000.000 $1,500.000 $500.000 $3,200.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 15.000 $200.000 $75.000 $75.000 $50.000 $250.000 $800.000 $280.000
TMA (STATIONARY)
DAY 25.000 $800.000 $3,500.000 $1,000.000 $500.000 $750.000 $7,500.000 $280.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 120.000 $80.000 $50.000 $75.000 $5.000 $50.000 $40.000 $44.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 20.000 $20.000 $5.000 $180.000 $5.000 $50.000 $40.000 $80.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 120.000 $5.000 $5.000 $1.000 $30.000 $25.000 $40.000 $18.400
MTL W-BEAM GD FEN (TIM POST)
LF 100.000 $20.000 $30.000 $22.000 $30.000 $40.000 $50.000 $60.000
MTL THRIE-BEAM GD FEN (TIM POST)
LF 25.000 $20.000 $5.000 $75.000 $30.000 $100.000 $50.000 $68.800
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $500.000 $1,100.000 $2,200.000 $500.000 $1,500.000 $2,500.000 $2,000.000
MTL BEAM GD FEN TRANS (TL2)
EA 1.000 $500.000 $1.000 $1,000.000 $500.000 $2,000.000 $500.000 $2,400.000
MTL BEAM GD FEN TRANS (T101)
EA 1.000 $1,000.000 $1.000 $500.000 $1,000.000 $900.000 $500.000 $2,000.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 100.000 $50.000 $10.000 $10.000 $10.000 $25.000 $8.000 $16.000
TRANSITION ADJUSTMENT
EA 5.000 $100.000 $1.000 $1.000 $100.000 $500.000 $50.000 $280.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,800.000 $900.000 $2,000.000 $1,800.000 $1,000.000 $2,000.000 $1,840.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 25.000 $10.000 $10.000 $5.000 $10.000 $250.000 $300.000 $1,280.000
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $5.000 $5.000 $1.000 $5.000 $15.000 $5.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 5.000 $200.000 $1.000 $1.000 $100.000 $500.000 $1.000 $360.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,500.000 $2,000.000 $500.000 $4,000.000 $3,500.000 $3,500.000 $2,880.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 3.000 $200.000 $100.000 $500.000 $10.000 $1,000.000 $300.000 $960.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $250.000 $1.000 $100.000 $100.000 $1,000.000 $300.000 $448.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $500.000 $1.000 $1.000 $500.000 $2,500.000 $2,000.000 $436.800
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 20.000 $10.000 $1.000 $7.000 $20.000 $120.000 $1.000 $68.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
EA 20.000 $10.000 $1.000 $7.000 $20.000 $125.000 $1.000 $60.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 9.000 $35.000 $10.000 $15.000 $50.000 $100.000 $1.000 $44.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 5.000 $35.000 $10.000 $15.000 $50.000 $150.000 $1.000 $60.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 2.000 $35.000 $1.000 $20.000 $50.000 $200.000 $1.000 $52.000
REPLACE RAIL ELEMENT (W-BEAM)
LF 1,500.000 $50.000 $12.000 $6.000 $20.000 $13.000 $25.000 $28.000
REPLACE RAIL ELEMENT (THRIE-BEAM)
LF 25.000 $50.000 $20.000 $100.000 $20.000 $75.000 $30.000 $48.000
REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM)
EA 25.000 $30.000 $25.000 $100.000 $20.000 $300.000 $40.000 $400.000
REPLACE TIMBER POST W/O CONC FND
EA 10.000 $30.000 $30.000 $500.000 $200.000 $350.000 $100.000 $160.000
REPLACE STEEL POST W/O CONC FND
EA 10.000 $80.000 $1.000 $50.000 $200.000 $300.000 $100.000 $88.000
REPLACE TIMBER POST W/ CONC FND
EA 10.000 $80.000 $100.000 $500.000 $200.000 $300.000 $100.000 $224.000
REALIGN POSTS
EA 75.000 $25.000 $50.000 $300.000 $15.000 $50.000 $30.000 $48.000
REM OBSOLETE GET & REPL W/ SGT
EA 2.000 $3,000.000 $6,000.000 $12,000.000 $4,000.000 $5,500.000 $5,000.000 $5,200.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 15.000 $1,700.000 $500.000 $500.000 $1,700.000 $1,000.000 $500.000 $1,520.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 100.000 $100.000 $150.000 $150.000 $200.000 $75.000 $55.000 $44.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 10.000 $70.000 $100.000 $100.000 $200.000 $250.000 $100.000 $78.400
REPLACE BLOCKOUT
EA 50.000 $150.000 $150.000 $450.000 $50.000 $50.000 $20.000 $40.000
RESET SGT IMPACT HEAD
EA 10.000 $400.000 $500.000 $300.000 $200.000 $250.000 $50.000 $464.000
REPLACE SGT OBJECT MARKER
EA 16.000 $100.000 $35.000 $1.000 $100.000 $100.000 $10.000 $120.000
REPLACE SGT CABLE ASSEMBLY
EA 15.000 $200.000 $100.000 $1.000 $200.000 $125.000 $10.000 $150.400
REPLACE SGT STRUT
EA 7.000 $200.000 $50.000 $1.000 $100.000 $100.000 $20.000 $148.000
REPLACE POSTS (TL-4)(TRINITY)
EA 50.000 $225.000 $200.000 $155.000 $150.000 $200.000 $300.000 $400.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 10.000 $100.000 $25.000 $1.000 $10.000 $100.000 $150.000 $520.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 2.000 $200.000 $1.000 $100.000 $200.000 $1,000.000 $80.000 $52.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 20.000 $500.000 $600.000 $100.000 $100.000 $500.000 $120.000 $6,800.000
REPLACE CABLE (TL-4)
LF 1,000.000 $2.500 $1.000 $1.000 $0.250 $0.500 $4.000 $48.000
CHECK / RE-TENSION CABLE (TL-4)
EA 10.000 $800.000 $200.000 $1,000.000 $200.000 $1,000.000 $100.000 $248.000
REMOVE (TAU II-R) NARROW
EA 10.000 $450.000 $2,200.000 $1.000 $1.000 $1,000.000 $500.000 $1,600.000
REPLACE (TAU II-R) NARROW
EA 10.000 $1,000.000 $100.000 $1,500.000 $8,000.000 $2,000.000 $5,000.000 $34,240.000
REMOVE (NARROW QUAD)
EA 1.000 $3,000.000 $2,000.000 $1.000 $1.000 $2,500.000 $1,000.000 $2,000.000
REPLACE (NARROW QUAD)
EA 1.000 $13,000.000 $500.000 $30,000.000 $10,000.000 $2,500.000 $25,000.000 $20,000.000
REPAIR (NARROW QUAD BAY)
EA 1.000 $5,000.000 $2,000.000 $750.000 $1,800.000 $4,000.000 $1,000.000 $2,800.000
REPAIR (WIDE QUAD BAY)
EA 1.000 $5,000.000 $1.000 $400.000 $2,000.000 $4,000.000 $1,000.000 $1,200.000
REMOVE (TAU II) WIDE
EA 1.000 $500.000 $500.000 $1.000 $1.000 $2,500.000 $1,000.000 $3,200.000
REPLACE (TAU II) WIDE
EA 1.000 $2,000.000 $225.000 $3,000.000 $10,000.000 $2,500.000 $30,000.000 $32,000.000
REMOVE (NARROW TRACC)
EA 1.000 $2,500.000 $1.000 $2,000.000 $1.000 $2,500.000 $500.000 $2,800.000
REPLACE (NARROW TRACC)
EA 1.000 $13,000.000 $1.000 $1,000.000 $10,000.000 $1,000.000 $500.000 $640.000
REMOVE (WIDE TRACC)
EA 1.000 $2,500.000 $500.000 $1.000 $1.000 $2,000.000 $500.000 $280.000
REPLACE (WIDE TRACC)
EA 1.000 $13,000.000 $500.000 $1,000.000 $10,000.000 $1,000.000 $500.000 $200.000
REPAIR (WIDE TRACC)
LF 1.000 $3,000.000 $100.000 $200.000 $2,000.000 $1,000.000 $500.000 $520.000
REPAIR (WIDE TRACC BAY)
EA 1.000 $1,000.000 $100.000 $1.000 $1,500.000 $3,000.000 $500.000 $360.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 1.000 $3,500.000 $2,000.000 $1,250.000 $3,500.000 $2,000.000 $500.000 $608.000
Totals: $368,260.000 $258,947.000 $270,133.000 $311,609.000 $327,650.000 $485,471.000 $943,928.800