Items: 69

County: CHAMBERS
Length: N/A
Highway: IH0010
District: BEAUMONT
Control Number: 6313-38-001
DBE Goal: N/A
Project: RMC - 631338001
Guaranty: N/A
Time: 365 W
Engineer's Estimate: $464,662.46
Date: 06/07/2017 (9 years ago)
Contract Number: N/A
Type: METAL BEAM GUARD FENCE REPAIRS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (1)
E
Engineer's Estimate
$464,662.46
$445,531.00
Over/Under Est: -4.12% -$19,131.46

Bid Items & Bid Tabulations

69 Total 0 of 69
CHAMBERS  |  IH0010  |  BEAUMONT  |  6313-38-001  |  06/07/2017  |  $464,662.46  |  RMC - 631338001  |  METAL BEAM GUARD FENCE REPAIRS  |  365 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
ISI CONTRACTING, INC.
REMOVING CONC (RIPRAP)
SY 10.000 $12.650 $28.000
CONC STR REPAIR (STANDARD)
SF 5.000 $150.000 $100.000
CONC STR REPR(REMOVE AND REPLACE CAP)
CY 5.000 $1,000.000 $1,800.000
RIPRAP (MOW STRIP)(4 IN)
CY 1.000 $1,500.000 $800.000
RAIL (TY T402)(HPC)
LF 1.000 $500.000 $1,500.000
MOBILIZATION (CALLOUT)
EA 6.000 $1,000.000 $500.000
MOBILIZATION (EMERGENCY)
EA 6.000 $2,500.000 $1,200.000
MTL W-BEAM GD FEN (TIM POST)
LF 100.000 $20.000 $18.000
MTL THRIE-BEAM GD FEN (TIM POST)
LF 35.000 $177.730 $25.000
TERMINAL ANCHOR SECTION
EA 10.000 $750.000 $200.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 3.000 $1,900.000 $2,500.000
MTL BEAM GD FEN TRANS (TL2)
EA 3.000 $1,032.700 $1,000.000
MTL BEAM GD FEN TRANS (T101)
EA 3.000 $1,200.000 $1,200.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 250.000 $11.700 $8.000
MTL THRIE-BEAM GD FEN ADJUSTMENT
LF 3.000 $25.000 $35.000
TERMINAL ANCHOR SECTION ADJUSTMENT
EA 1.000 $366.670 $200.000
TRANSITION ADJUSTMENT
EA 1.000 $712.140 $200.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,100.000 $1,100.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 20.000 $30.000 $25.000
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $2.500 $1.300
REMOVE TERMINAL ANCHOR SECTION
EA 10.000 $188.580 $80.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,900.000 $2,600.000
CRASH CUSH ATTEN (INSTL)
EA 1.000 $20,000.000 $26,000.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,000.000 $800.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 10.000 $81.690 $14.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 10.000 $62.370 $14.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 10.000 $17.870 $18.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 10.000 $27.130 $18.000
INSTL DEL ASSM (D-SY)SZ 1(FLX)GND
EA 10.000 $89.330 $14.000
INSTL DEL ASSM (D-SY)SZ (BRF)GF1
EA 10.000 $26.380 $17.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 3,500.000 $13.000 $14.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 30.000 $30.000 $23.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 30.000 $30.000 $23.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 275.000 $34.000 $40.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 150.000 $40.000 $33.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 300.000 $45.000 $36.000
REM / REPL STEEL POST W / CONC FND
EA 1.000 $90.000 $100.000
REPAIR STEEL POST WITH BASE PLATE
EA 1.000 $120.000 $125.000
REALIGN POSTS
EA 170.000 $12.000 $6.000
INSTALL BLOCKOUT (TYPE SPECIFIED)
EA 1.000 $5.000 $6.000
REMOVE & REPLACE BLOCKOUT
EA 200.000 $5.000 $6.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 3,000.000 $20.000 $14.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 275.000 $50.000 $45.000
REPAIR OF TERMINAL ANCHORS POSTS
EA 1.000 $50.000 $40.000
REPLACE TERMINAL ANCHOR POSTS
EA 10.000 $125.000 $150.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 10.000 $2,800.000 $2,800.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 45.000 $1,000.000 $1,075.000
REM & RESET SGT IMPACT HEAD
EA 100.000 $150.000 $170.000
REPLACE SGT CABLE ASSEMBLY
EA 45.000 $90.000 $96.000
REPLACE SGT STRUT
EA 35.000 $40.000 $64.000
REPLACE SGT OBJECT MARKER
EA 1.000 $50.000 $30.000
REPAIR RAIL ELEMENT (CURVED RAIL)(FURN)
LF 100.000 $8.000 $7.000
REMOVE AND REPLACE (TRACC)
EA 1.000 $10,000.000 $15,000.000
REPAIR (TRACC)
EA 1.000 $2,000.000 $2,000.000
REPAIR (WIDE TRACC)
EA 1.000 $2,000.000 $2,000.000
REMOVE AND REPLACE (NARROW QUAD)
EA 1.000 $12,000.000 $15,500.000
REPAIR (CATGR - FRONT SECTION)
EA 1.000 $1,500.000 $500.000
REPAIR (CATGR - END SECTION)
EA 1.000 $1,000.000 $500.000
REMOVE AND REPLACE (CATGR)
EA 1.000 $4,500.000 $5,000.000
REPAIR (QUAD) (N) (BAY)
EA 15.000 $950.000 $1,000.000
REPAIR (QUAD) (W) (BAY)
EA 1.000 $1,500.000 $1,800.000
REPAIR (GREAT SYS) (BAY)
EA 2.000 $1,500.000 $500.000
REPAIR REACT (CYLINDERS)
EA 1.000 $1,900.000 $3,000.000
REPAIR REACT (W) (CYLINDERS)
EA 1.000 $1,900.000 $3,000.000
REPAIR (TRACC) (BAY)
EA 15.000 $750.000 $800.000
REPAIR (WIDE TRACC) (BAY)
EA 1.000 $1,200.000 $1,400.000
REMOVE AND REPLACE (TAU II) (N)
EA 1.000 $22,000.000 $20,000.000
REMOVE AND REPLACE TAU II (W)
EA 1.000 $30,000.000 $32,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 1.000 $150.000 $110.000
Totals: $464,662.460 $445,531.000