Show Job Controls
Bid Cobra

CHAMBERS FM 1663 (1464-01-018)

Items: 29

County: CHAMBERS
Length: N/A
Highway: FM 1663
District: BEAUMONT
Control Number: 1464-01-018
DBE Goal: N/A
Project: STP 2021(531)HES
Guaranty: N/A
Time: 40 WORKING DAYS
Engineer's Estimate: $856,972.70
Date: 05/05/2021 (5 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$856,972.70
Over/Under Est: -14.07% -$120,579.20
Over/Under Est: -12.89% -$110,485.43
Amt Left: 1.37% $10,093.77
Over/Under Est: -9.3% -$79,674.49
Amt Left: 5.55% $40,904.71
Delta: -4.13% -$30,810.94

Bid Items & Bid Tabulations

29 Total 0 of 29
CHAMBERS  |  FM 1663  |  BEAUMONT  |  1464-01-018  |  05/05/2021  |  $856,972.70  |  STP 2021(531)HES  |  HAZARD ELIM & SAFETY  |  40 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
TEXAS MATERIALS GROUP, INC.
ANGEL BROTHERS HOLDINGS CORP.
REMOVING CONC (DRIVEWAYS)
SY 14.000 $17.000 $300.000 $76.000 $90.000
SUBGRADE WIDENING (ORD COMP)
STA 83.510 $213.000 $335.000 $595.000 $695.000
BACKFILL (TY B)
STA 83.510 $145.000 $185.000 $158.000 $192.000
BROADCAST SEED (TEMP) (WARM)
SY 14,846.000 $0.300 $0.140 $0.130 $0.140
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 14,846.000 $1.440 $0.390 $0.310 $0.300
VEGETATIVE WATERING
MG 10.390 $7.250 $806.000 $45.000 $65.000
PROOF ROLLING
HR 74.000 $108.000 $45.000 $90.000 $80.000
D-GR HMA(SQ) TY-B PG64-22
TON 2,527.000 $110.000 $97.550 $87.000 $102.750
TACK COAT
GAL 459.000 $3.000 $3.250 $8.000 $2.450
MOBILIZATION
LS 1.000 $64,000.000 $55,000.000 $47,000.000 $48,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,500.000 $3,000.000 $1,850.000 $2,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 200.000 $4.500 $9.650 $5.050 $7.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $1.000 $7.650 $1.020 $1.750
DRIVEWAYS (ACP)
SY 130.000 $35.000 $30.000 $30.000 $72.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 16,582.000 $0.200 $0.300 $0.390 $0.300
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 8,273.000 $0.200 $0.300 $0.520 $0.300
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 23.000 $225.000 $225.000 $221.000 $200.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 583.000 $1.100 $1.000 $1.500 $0.550
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 16,822.000 $0.450 $0.430 $0.310 $0.350
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 2,090.000 $0.450 $0.430 $0.360 $0.350
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 2,199.000 $0.450 $0.430 $0.360 $0.350
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 86.000 $12.000 $15.000 $15.250 $15.000
PREFAB PAV MRK TY C (W) (WORD)
EA 6.000 $245.000 $225.000 $510.000 $250.000
REFL PAV MRKR TY II-A-A
EA 133.000 $3.500 $5.000 $3.050 $10.000
JT / CRCK ROUT / SEAL(RUBBER - ASPHALT)
LF 16,702.000 $5.000 $2.000 $2.000 $1.450
SP MIXES SP-D SAC-A PG76-22
TON 2,858.000 $110.000 $99.000 $101.000 $105.000
TACK COAT
GAL 1,559.000 $3.000 $3.250 $4.000 $2.450
TMA (STATIONARY)
DAY 49.000 $105.000 $50.000 $340.000 $160.000
TMA (MOBILE OPERATION)
DAY 15.000 $165.000 $25.000 $965.000 $200.000
Totals: $856,972.698 $736,393.500 $746,487.270 $777,298.210