CHAMBERS FM 1410 (1420-02-012)

Items: 30

County: CHAMBERS
Length: N/A
Highway: FM 1410
District: BEAUMONT
Control Number: 1420-02-012
DBE Goal: N/A
Project: STP 2018(758)HES
Guaranty: N/A
Time: 28 WORKING DAYS
Engineer's Estimate: $378,198.90
Date: 04/04/2018 (8 years ago)
Contract Number: N/A
Type: PROVIDE ADDITIONAL SURFACE_WIDTH
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$378,198.90
Over/Under Est: -13.15% -$49,727.08
Over/Under Est: -10.9% -$41,210.29
Amt Left: 2.59% $8,516.79
Over/Under Est: -10.49% -$39,654.81
Amt Left: 3.07% $10,072.27
Delta: -0.46% -$1,555.48
Over/Under Est: 1.3% $4,911.00
Amt Left: 16.63% $54,638.08
Delta: -13.16% -$44,565.81

Bid Items & Bid Tabulations

30 Total 0 of 30
CHAMBERS  |  FM 1410  |  BEAUMONT  |  1420-02-012  |  04/04/2018  |  $378,198.90  |  STP 2018(758)HES  |  PROVIDE ADDITIONAL SURF_WIDTH  |  28 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
OLDCASTLE MATERIALS TEXAS, INC.
ANGEL BROTHERS HOLDINGS CORP.
FORDE CONSTRUCTION COMPANY, INC.
SUBGRADE WIDENING (ORD COMP)
STA 30.630 $300.000 $300.000 $550.000 $250.000 $84.000
BACKFILL (TY A OR B)
STA 30.630 $125.000 $200.000 $205.000 $365.000 $156.000
BROADCAST SEED (TEMP) (WARM)
SY 2,066.000 $0.200 $0.500 $0.700 $0.560 $0.550
BROADCAST SEED (TEMP) (COOL)
SY 2,066.000 $0.200 $0.500 $0.850 $0.560 $0.550
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 4,132.000 $0.400 $0.320 $0.380 $0.370 $0.360
VEGETATIVE WATERING
MG 35.000 $15.000 $15.000 $43.000 $20.000 $100.000
FL BS(RDWY DEL)(TY D GR 1-2)(FNAL POS)
CY 662.000 $70.000 $94.000 $78.000 $58.000 $79.000
CEMENT
TON 130.000 $200.000 $160.000 $200.000 $220.000 $195.000
CEMENT TREAT (MX EXST MATL & NW BS)(7")
SY 9,539.000 $3.500 $3.500 $3.600 $4.250 $6.000
PRIME COAT (AE-P)
GAL 1,908.000 $4.000 $3.000 $3.350 $3.500 $4.000
AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B)
CY 87.000 $200.000 $125.000 $195.000 $175.000 $198.000
ASPH (AC-15P OR AC-10-2TR)
GAL 3,434.000 $4.000 $6.500 $2.600 $3.000 $2.500
SUPERPAVE MIXTURES SP-C SAC-B PG64-22
TON 1,051.000 $90.000 $79.000 $80.000 $91.000 $95.000
MOBILIZATION
LS 1.000 $50,000.000 $30,000.000 $27,000.000 $34,000.000 $35,400.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $5,000.000 $1,500.000 $2,000.000 $4,500.000 $8,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 75.000 $30.000 $40.000 $30.000 $50.000 $82.880
ROCK FILTER DAMS (REMOVE)
LF 75.000 $10.000 $15.000 $8.200 $10.000 $41.440
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 220.000 $5.000 $10.000 $5.600 $4.000 $14.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 220.000 $1.000 $3.000 $1.050 $1.750 $1.000
INTERSECTIONS (ACP)
SY 514.000 $80.000 $30.750 $39.000 $32.000 $28.000
DRIVEWAYS AND TURNOUTS (SURF TREAT)
SY 168.000 $40.000 $36.000 $79.000 $28.000 $64.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 2.000 $200.000 $600.000 $255.000 $500.000 $700.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 346.000 $1.500 $1.000 $1.100 $1.500 $2.500
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 322.000 $0.800 $1.200 $1.000 $1.400 $1.200
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 6,099.000 $0.350 $0.360 $0.460 $0.420 $0.360
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 520.000 $0.400 $0.400 $0.620 $0.500 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 2,583.000 $0.400 $0.380 $0.520 $0.450 $0.380
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 10.000 $50.000 $70.000 $25.500 $85.000 $70.000
REFL PAV MRKR TY II-A-A
EA 56.000 $5.000 $4.000 $8.200 $4.650 $4.000
TMA (STATIONARY)
DAY 28.000 $200.000 $100.000 $150.000 $100.000 $150.000
Totals: $378,198.900 $328,471.820 $336,988.610 $338,544.090 $383,109.900